The program manager compiles a program performance report for review by the program governance board. The performance report indicates that the scope, quality and schedule objectives have been me, but costs and resource utilization are higher than expected. The program can no longer deliver the planned return-on-investment within an acceptable level and the intended benefits have not yet been realized
After further analysis of the performance indicators the program manager should do which of the following*?

Based on the estimated work area size, what is the MAXIMUM number of work areas that a telecommunications enclosure shall serve?

One of the constituent project managers asks a new program manager to obtain approval for an additional key project requirement.
A tolerance range is set, if the tolerance range is too narrow on a program what effect will multiple minor changes have on the program?

Which two of the following apply during a project's close out process? (Choose two.)

A large international manufacturing company is centralizing its IT which is currently spread over 16 countries. The transition means physically regrouping the infrastructure and aligning processes and organizations.
The high-level scope of this transformation encompasses three main areas.
1. The technology area-assessing which technology/tooling should be retained for the target data center
2. The policies and procedure area-aimed at establishing a common set of processes supporting the new way of delivering services
3. The HR area-assuring the new organization best fits the diversity of the countries and functional domains, while offering equivalent compensations for comparable functions
You have selected your team and you are preparing the business case to support 1) the team selections you made and 2) your recommendation to proceed to the program's next phase
Which document should be present m your business case?

Which two of the following components are included in a backbone distribution system (BDS)? (Choose two.)

In new construction, what is the percentage of pay phones that must be equipped with volume controls?

Who prepares the submittals that are reviewed and approved to ensure that the clients design criteria is met in regards to material selection?

CORRECT TEXT
A program experiences issues during execution. The stakeholders are concerned and the program manager feels pressure to act on these issues.
What tool should be used to trigger a planned response when receiving lower than expected results'?

A large automaker begins a program to create the next-generation car. As the program team is composed, key stakeholders are identified Key stakeholders for the program should include which of the following?

You have just finished a design calling for 15 telecommunications outlets. You received word that the owner has increased his requirements by 40%.
What size commercial DD (distribution device) is required to accommodate the increase?

During bidding the ICT distribution designer should review the bid responses for compliance and completeness. Afterwards, the designer should report the findings and recommendations to the

A program manager for the construction of a ship reviews the program management plan with a shipyard representative. The shipyard representative indicates that while 65 percent progress was anticipated only 60 percent has been achieved
What should the program manager do to ensure benefits realization?

A component protect of a multiyear program delivers all expected products and services as anticipated. The component project manager obtains approvals from the stakeholders and transitions the benefits to operations
What should the program manager do next?

For a cable tray installed within an ER, the RECOMMENDED access headroom is: