Alan has an ongoing contract with a supplier for the provision of gardening tools to his horti-culture business. He has been working with the supplier for over 20 years and has recently discovered that the supplier committed a breach in a warranty 3 years ago. Can Alan claim damages?
正解:B
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
GoGo Ltd has contracted Reny Manufacturing to produce a bespoke piece of equipment for them. It is an asset and costs a significant amount of money. A contract is drawn up which states that GoGo Ltd has the right to terminate the contract at any time for any reason. Halfway through production of the asset, GoGo Ltd calls Reny Manufacturing to cancel the order. Reny Manufacturing has incurred many costs already. Can GoGo Ltd cancel the order?
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)