TMMI-P_IND試験無料問題集「ISQI TMMi Professional (IND only) 認定」
A test organization is at the initial TMMi level and is trying to implement the TMMi level 2 process areas.
One of the improvement goals for the current year is to improve management and control of test environments.
Which of the following specific practices needs to be addressed as part of SG 3 "Manage and Control Test Environments" of the Test Environment process area?
One of the improvement goals for the current year is to improve management and control of test environments.
Which of the following specific practices needs to be addressed as part of SG 3 "Manage and Control Test Environments" of the Test Environment process area?
正解:B
解答を投票する
A test process assessment against TMMi levels 2 and 3 has been performed on an international outsourcing software organization. Although many practices, as required by the TMMi model, are already in place, projects suffer from poor test estimations.
Which of the following process areas would need specific attention to address the above mentioned shortcoming?
Which of the following process areas would need specific attention to address the above mentioned shortcoming?
正解:C
解答を投票する
The evolutionary testing model of Gelperin and Hetzel has served as a foundation for historical level differentiation in the TMMi. The evolutionary testing model describes a number of test phases.
Which of the following phases of the evolutionary testing model is associated with Maturity Level 1 "Initial" of the TMMi?
Which of the following phases of the evolutionary testing model is associated with Maturity Level 1 "Initial" of the TMMi?
正解:C
解答を投票する
Study the following description:
"Testing is multi-levelled: there are component, integration, system and acceptance test levels. For each identified test level there are specific testing objectives defined in the organization-wide or program-wide test strategy. The processes of testing and debugging are differentiated." To which TMMi maturity level does this description apply?
"Testing is multi-levelled: there are component, integration, system and acceptance test levels. For each identified test level there are specific testing objectives defined in the organization-wide or program-wide test strategy. The processes of testing and debugging are differentiated." To which TMMi maturity level does this description apply?
正解:A
解答を投票する