Scenario 2: Travivve is a travel agency that operates in more than 100 countries. Headquartered in San Francisco, the US, the agency is known for its personalized vacation packages and travel services. Travivve aims to deliver reliable services that meet its clients' needs. Considering the impact of information security in its reputation, Travivve decided to implement an information security management system (ISMS) based on ISO/IEC 27001. In addition, they decided to establish and implement an information security risk management program. Based on the priority of specific departments in Travivve, the top management decided to initially apply the risk management process only in the Sales Management Department. The process would be applicable for other departments only when introducing new technology.
Travivve's top management wanted to make sure that the risk management program is established based on the industry best practices. Therefore, they created a team of three members that would be responsible for establishing and implementing it. One of the team members was Travivve's risk manager who was responsible for supervising the team and planning all risk management activities. In addition, the risk manager was responsible for monitoring the program and reporting the monitoring results to the top management.
Initially, the team decided to analyze the internal and external context of Travivve. As part of the process of understanding the organization and its context, the team identified key processes and activities. Then, the team identified the interested parties and their basic requirements and determined the status of compliance with these requirements. In addition, the team identified all the reference documents that applied to the defined scope of the risk management process, which mainly included the Annex A of ISO/IEC 27001 and the internal security rules established by Travivve. Lastly, the team analyzed both reference documents and justified a few noncompliances with those requirements.
The risk manager selected the information security risk management method which was aligned with other approaches used by the company to manage other risks. The team also communicated the risk management process to all interested parties through previously established communication mechanisms. In addition, they made sure to inform all interested parties about their roles and responsibilities regarding risk management. Travivve also decided to involve interested parties in its risk management activities since, according to the top management, this process required their active participation.
Lastly, Travivve's risk management team decided to conduct the initial information security risk assessment process. As such, the team established the criteria for performing the information security risk assessment which included the consequence criteria and likelihood criteria.
Based on scenario 2, has Travivve defined the responsibilities of the risk manager appropriately?

解説: (GoShiken メンバーにのみ表示されます)
An organization decided to use nonnumerical categories, i.e., low, medium, and high for describing consequence and probability. Which risk analysis methodology is the organization using?

解説: (GoShiken メンバーにのみ表示されます)
Scenario 1
The risk assessment process was led by Henry, Bontton's risk manager. The first step that Henry took was identifying the company's assets. Afterward, Henry created various potential incident scenarios. One of the main concerns regarding the use of the application was the possibility of being targeted by cyber attackers, as a great number of organizations were experiencing cyberattacks during that time. After analyzing the identified risks, Henry evaluated them and concluded that new controls must be implemented if the company wants to use the application. Among others, he stated that training should be provided to personnel regarding the use of the application and that awareness sessions should be conducted regarding the importance of protecting customers' personal data.
Lastly, Henry communicated the risk assessment results to the top management. They decided that the application will be used only after treating the identified risks.
Henry concluded that one of the main concerns regarding the use of the application for online ordering was cyberattacks. What did Henry identify in this case? Refer to scenario 1.\

解説: (GoShiken メンバーにのみ表示されます)
Scenario 1
The risk assessment process was led by Henry, Bontton's risk manager. The first step that Henry took was identifying the company's assets. Afterward, Henry created various potential incident scenarios. One of the main concerns regarding the use of the application was the possibility of being targeted by cyber attackers, as a great number of organizations were experiencing cyberattacks during that time. After analyzing the identified risks, Henry evaluated them and concluded that new controls must be implemented if the company wants to use the application. Among others, he stated that training should be provided to personnel regarding the use of the application and that awareness sessions should be conducted regarding the importance of protecting customers' personal data.
Lastly, Henry communicated the risk assessment results to the top management. They decided that the application will be used only after treating the identified risks.
Based on scenario 1, Bontton used ISO/IEC 27005 to ensure effective implementation of all ISO/IEC 27001 requirements. Is this appropriate?

解説: (GoShiken メンバーにのみ表示されます)
Scenario 8: Biotide is a pharmaceutical company that produces medication for treating different kinds of diseases. The company was founded in 1997, and since then it has contributed in solving some of the most challenging healthcare issues.
As a pharmaceutical company, Biotide operates in an environment associated with complex risks. As such, the company focuses on risk management strategies that ensure the effective management of risks to develop high-quality medication. With the large amount of sensitive information generated from the company, managing information security risks is certainly an important part of the overall risk management process. Biotide utilizes a publicly available methodology for conducting risk assessment related to information assets. This methodology helps Biotide to perform risk assessment by taking into account its objectives and mission. Following this method, the risk management process is organized into four activity areas, each of them involving a set of activities, as provided below.
1. Activity area 1: The organization determines the criteria against which the effects of a risk occurring can be evaluated. In addition, the impacts of risks are also defined.
2. Activity area 2: The purpose of the second activity area is to create information asset profiles. The organization identifies critical information assets, their owners, as well as the security requirements for those assets. After determining the security requirements, the organization prioritizes them. In addition, the organization identifies the systems that store, transmit, or process information.
3. Activity area 3: The organization identifies the areas of concern which initiates the risk identification process. In addition, the organization analyzes and determines the probability of the occurrence of possible threat scenarios.
4. Activity area 4: The organization identifies and evaluates the risks. In addition, the criteria specified in activity area 1 is reviewed and the consequences of the areas of concerns are evaluated. Lastly, the level of identified risks is determined.
The table below provides an example of how Biotide assesses the risks related to its information assets following this methodology:

Based on the table provided in scenario 8, did Biotide follow all the steps of the risk assessment methodology regarding the identification of assets?

解説: (GoShiken メンバーにのみ表示されます)
An organization has installed security cameras and alarm systems. What type of information security control has been implemented in this case?

解説: (GoShiken メンバーにのみ表示されます)