What action should the Project Manager take to plan the deployment activities?

Most of the Customer Services staff are working with the new processes. However, there are a number of remaining staff who don't want to be trained in the new technologies and wish to continue supporting the old business areas.
Which is the MOST appropriate intervention from the Customer Service Director?

解説: (GoShiken メンバーにのみ表示されます)
What action should the Project Manager take during the Close-Out of Timebox C?

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about applying controls to the end of Development Timebox C.
What action should the Project Manager take when considering the End of Timebox Review?

The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people's social experience to guide management actions. Answer the following questions about the use of David Rock's SCARF framework to increase the motivation for change.
On seeing plans for the office move, the Selco staff are worried that some desk allocations do not have access to natural light. The relocation leadership team held a workshop as soon as the issue was raised and has allocated these desks to be 'hot-desks,' not used by staff permanently based in the office.
Is this an appropriate approach to reward the brain in the need for 'certainty,' and why?

解説: (GoShiken メンバーにのみ表示されます)
Which 2 statements explain why the Timber Tigers' Site Manager would be an appropriate Solution Developer?

Answer the following questions about the use of the Agile principles.
Final checks carried out on the rooms delivered in Timebox A show that two of the items do NOT meet the required Must Have standards related to the use of traditional wall coverings and paints. These items have therefore been recognised as NOT delivered and will have to be re-planned.
Which Agile principle MOST influences this course of action?

A difference of opinion on the outcome of an earlier project has created a
'them and us' culture between the Sales Department and the Operations
Department.
What action should the Project Manager take to resolve this?

解説: (GoShiken メンバーにのみ表示されます)
An external web developer is to be contracted to create the new coffee bar insurance area on the existing web site. The chosen web developer will only agree to work on a 'fixed price for a fixed specification' contract.
What action should the Project Manager take?

解説: (GoShiken メンバーにのみ表示されます)
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
The requirement to 'install a heat reclamation system' shows as a Should Have in the Prioritised Requirements List. During Investigation in Solution Development Timebox B, the Project Manager advised the team NOT to set detailed acceptance criteria for this requirement until later in the Timebox, since the requirement may have to be dropped and the work would be wasted.
Is this an appropriate action related to acceptance criteria?