What parent object can have child objects?

解説: (GoShiken メンバーにのみ表示されます)
A project manager has been asked to work on a cross-departmental company-wide initiative. There will be many individuals assigned to each task.
What should the project manager ask users to do when it comes to completing tasks?

解説: (GoShiken メンバーにのみ表示されます)
Two team members are assigned to a task that is expected to start this Tuesday based on the predecessor and the task constraint, but the Planned Start Date is showing as this Friday.
Why may this be the case?

解説: (GoShiken メンバーにのみ表示されます)
Which project Condition is set when the Progress Status of the project is Behind or At Risk?

解説: (GoShiken メンバーにのみ表示されます)
Due to a time sensitive shift in priorities, the timeline of a project needs to be adjusted. What step should the Project Owner take before adjusting the task timeline to avoid sending notifications to the project team?

解説: (GoShiken メンバーにのみ表示されます)
A project manager is assigned to a new Workfront request. The requestor has asked that three team members receive notifications when any updates are posted to the request.
How should the project manager keep these team members apprised of updates?

解説: (GoShiken メンバーにのみ表示されます)
A team lead needs to regularly report on the adherence of budget and timeline of a group of projects.
What should the team lead use to organize these projects to allow them to be tracked together?