A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits.
Which of the following actions should the program manager take?
Which of the following actions should the program manager take?
正解:D
解答を投票する
A company is releasing a new product geared toward a specific geographic are a. The program manager has received the program objectives and developed the program roadmap which consists of six program components Approval from the program governance board has been obtained.
What is the program manager's next step?
What is the program manager's next step?
正解:D
解答を投票する
External resources are required for a program. The program manager receives bids from multiple vendors and presents the top vendor to the program governance board. One program governance board member asks the program manager to select a vendor that was dismissed early in the selection process because they were not on the approved vendor list The program manager learns that this program governance board member has a personal connection to this vendor What should the program manager do?
正解:B
解答を投票する
An unforeseen geopolitical risk impacts a program to establish a company's operations abroad. Stakeholders now want to establish a risk response team to define a mitigation plan. Ultimately what appeared to be a significant risk resulted in a negligible risk.
What should the program manager recommend to stakeholders for future similar situations?
What should the program manager recommend to stakeholders for future similar situations?
正解:C
解答を投票する
A new program manager joins a mufti-year program that has been underway for almost a year. During interviews, several stakeholders state that they do not understand how the program will help the organization At the next stakeholder meeting, what should the program manager present to address their concerns?
正解:B
解答を投票する
A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change.
To whom should the change request be presented?
To whom should the change request be presented?
正解:D
解答を投票する