Drag and drop the Rapid PVST+ forwarding slate actions from the loft to the right. Not all actions are used.


正解:

Explanation:

A Cisco engineer notices thai two OSPF neighbors are connected using a crossover Ethernet cable. The neighbors are taking too long to become fully adjacent. Which command must be issued under the interface configuration on each router to reduce the time required for the adjacency to reach the FULL state?
正解:B
解答を投票する
A network engineer is configuring a new router at a branch office. The router is connected to an upstream WAN network that allows the branch to communicate with the head office. The central time server with IP address 172.24.54.8 is located behind a firewall at the head office. Which command must the engineer configure so that the software clock of the new router synchronizes with the time server?
正解:B
解答を投票する
Drag and drop the TCP/IP protocols from the left onto the transmission protocols on the right


正解:

Explanation:


Refer to the exhibit. Local access for R4 must be established and these requirements must be met:
* Only Telnet access is allowed.
* The enable password must be stored securely.
* The enable password must be applied in plain text.
* Full access to R4 must be permitted upon successful login.
Which configuration script meets the requirements?
正解:D