PK0-004試験無料問題集「CompTIA Project+ Certification 認定」

A senior manager asks a project manager for an estimated budget on a new project.
Which of the following is the BEST step for the project manager to take?

A PM notes a feature that was delivered does not appear in the latest requirement document. The PM immediately submits a change request for remediation. Which of the following actions has the PM omitted?

A project manager wants to introduce the practice of a WBS to the PMO, but the other managers believe this will create extra work. Which of the following would BEST communicate the need for a WBS to the other managers? (Select TWO).

Objectives and tasks are equally assigned by two different managers.
Which of the following BEST describes this organization type?

Which of the following will MOST likely result in changes to the project plan?

A key stakeholder has asked project team members to work overtime on special projects. This is undermining the success of a time-sensitive project because the project team is too tired to complete the deliverables.
Which of the following steps should the project manager take to BEST resolve the issue?

A project has just finished performance testing and found that the application can only handle 100 concurrent users where the requirement was to handle 500 concurrent users.
In which of the following components of the project plan should this be documented?

A project manager notices several of the action items discussed during a team-building exercise have been ignored by the project team. Although the team-building exercise was well attended and feedback was well received, nothing was accomplished.
To make the meetings more productive, which of the following steps should the project manager take? (Choose two.)

A team member was assigned a new task during a meeting. The team member did not complete the task by the end of the phase, and the PM is looking for evidence to escalate the issue. Which of the following documents could help in this situation?

A team member was replaced on a project by a new team member of equal capability. Which of the following should the project manager do FIRST?

During the planning phase, the project manager meets with the project team to determine the tasks team to determine the task and their relationship.
Which of the following should the project manager receive from the team members? (Select two.)

A firm, fixed-price project is on pace to exceed the maximum defect rate identified in the project charter. The customer has stated the project must be delivered on time.
Which of the following is the BEST option for the project to complete on time and within parameters?

A project manager needs status on the project timeline.
Which of the following team members should provide an update?

A project task has been completed ahead of schedule. Which of the following is the MOST appropriate next step?

A contract manager is reconciling project invoices and needs to charge work performed by an outside contractor to a general ledger.
Which of the following would be the BEST project document to reference for this information?

Based on the table below:

Which of the following is the critical path?

A project manager is scheduling activities and determines one activity cannot be completed until another activity is completed. Which of the following dependency relationships is represented?

In the review of a project status report, the slack is negative. Which of the following should the project manager tell the stakeholders?