DRAG DROP
You are a project manager in an organization that is using Microsoft PPM. You are managing a 12-month project. Resources have been working on the project for six months.
You need to determine how the project is tracking against the initial goals in terms of duration, work and cost.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.

You are a project manager in an organization that is using Microsoft PPM. You are managing a 12-month project. Resources have been working on the project for six months.
You need to determine how the project is tracking against the initial goals in terms of duration, work and cost.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order.

正解:

Explanation:

References:
https://support.office.com/en-us/article/Create-or-update-a-baseline-or-an-interim-plan-
7E775482-AC84-4F4A-BBD0-592F9AC91953
HOTSPOT
You are a project manager in a large organization. During the project, some tasks have slipped, but the dependencies are still valid.
You are reviewing the project's Gantt chart.

Use the drop-down menus to select the answer choice that answers each question.

You are a project manager in a large organization. During the project, some tasks have slipped, but the dependencies are still valid.
You are reviewing the project's Gantt chart.

Use the drop-down menus to select the answer choice that answers each question.

正解:

HOTSPOT
You are a project manager for an organization that uses visibility projects in Microsoft PPM.
For each of the following statements, select Yes if the statement is true. Otherwise, select
No.

You are a project manager for an organization that uses visibility projects in Microsoft PPM.
For each of the following statements, select Yes if the statement is true. Otherwise, select
No.

正解:

Explanation:

References:
https://support.office.com/en-gb/article/Publish-a-project-b4c7593d-0844-4d28-bf2c-
5ddff2498e33
Your organization is using Microsoft PPM to manage large projects. Within the Microsoft PPM environment, you use SharePoint sites with task lists to manage smaller projects. You turn on the Timesheets feature.
You must collect information about the time that resources spend on all projects.
You need to ensure that you can capture timesheet data from the existing SharePoint task lists.
Which two actions will achieve the goal? Each correct answer presents a complete solution.
You must collect information about the time that resources spend on all projects.
You need to ensure that you can capture timesheet data from the existing SharePoint task lists.
Which two actions will achieve the goal? Each correct answer presents a complete solution.
正解:B,D