MB-320試験無料問題集「Microsoft Dynamics 365 Supply Chain Management, Manufacturing 認定」

You have updated a cost category price from $5.00 to S7.00. You process a production order which uses the cost category. After ending the order, you realize a new standard cost was not calculated after the price update. You need to validate how this impacted the financial voucher transactions. What transaction would you see in the general ledger?

解説: (GoShiken メンバーにのみ表示されます)
You maintain responsible resource calendars and production orders for a manufacturing company. All production resources use the same production calendar.
A machine in the facility is defective and must be closed for repairs for the next two days.
You need to configure the resource calendar to close the resource for production for the next two days.
What should you do?

A customer produces light projection toys for holiday decorations throughout the year.
You are in the first month of a season. Production flows take one day to complete.
The floor supervisor reports that seasonal production targets will not be met. You review the Kanban schedule board and identify thousands of unplanned jobs.
You need to plan the jobs to be completed two weeks prior to the start of the next season.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.

解説: (GoShiken メンバーにのみ表示されます)
You are responsible for training the operations staff on production transactions in Dynamics 365 for Finance and Operations. The company uses backflushing for material consumption principles.
You need to train the operators on how to report unintended scrap.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution.
NOTE: Each correct selection is worth one point.

Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.
After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.
A company uses Dynamics 365 Supply Chain Management to manage production configuration.
A product designer creates a remote control toy that can be purchased with different tire sizes.
Sales representatives need to perform product configuration for the custom tire variants when they create a new order.
Solution: Select the custom tire size when filling out each sales order line.
Does the solution meet the goal?

解説: (GoShiken メンバーにのみ表示されます)
You are the production supervisor at a chemical processing plant. You must track attributes for each batch of chemicals. Automated quality orders must be generated when a batch order for these chemicals is reported as finished.
You need to ensure that the values of attributes are updated and tracked.
What three actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.

正解:A,B,C 解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
A manufacturing company is implementing Dynamics 365 Supply Cham Management.
Bill of materials (BOMs) must be calculated using standard cost principles.
Miscellaneous charges must be included in the unit cost price. The explosion mode must arways be enforced as single level.
You need to configure the system to meet the requirements.
Which configuration should you enable for each requirement? To answer, drag the appropriate configurations to the correct requirements. Each configuration may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
正解:
You are a functional consultant for Contoso Entertainment System USA.
You need to configure the system to ensure that the production release to warehouse process either performed manually or via batch.
To complete this task, sign in to Dynamics 365 portal.
正解:
See explanation below
Explanation:
Navigate to Production control > Setup > Production parameters.
Configure the Production line release parameter to Release BOM and formula lines via a batch job or as a manual interaction.
Reference:
https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/releasing-bom-and-formula-lines-to-warehouse
A company uses manufacturing execution for processing of production orders.
Multiple production orders from last week need to be ended.
You need to process the time registrations to allow the orders to end.
Which four steps should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
正解:

1 - Add clock-out registrations.
2 - Calculate registrations.
3 - Approve registrations.
4 - Transfer registrations.
You are a functional consultant for Contoso Entertainment System USA (USMF).
The factory of USMF has a shift that runs during the hours of 06:00 to 14:00 from Monday to Friday.
You plan to create a calendar that will use the shift.
You need to create the factory shift in the system.
To complete this task, sign in to Dynamics 365 portal.
正解:
See explanation below
Explanation:
You need to configure a working time template to define the hours 06:00 to 14:00. Then you set up a working time calendar to define the working days. For this question, we just need to configure the working time template.
Click Organization administration > Common > Calendars > Working time templates. Click New to create a new line.
On the Overview tab, in the Working time template field, enter an alphanumeric identifier of up to 10 characters.
In the Name field, enter a descriptive name for the template.
Select the tab that corresponds to the day of the week that you want to define working hours for, and click Add to create a new line.
In the From field, enter the starting time for the day or the period.
In the To field, enter the ending time for the day or the period. This can be defined as a day, a shift, or a temporary stop in operation, such as a lunch period.
In the Efficiency field, enter the efficiency percentage.
In the Property field, select the property for the selected day's working time template.
Repeat steps 4 through 8 for each day of the week.
A customer produces light projection toys for holiday decorations throughout the year. Vendors have negotiated rebate agreements as a condition of their contact. The contract also contains the visual templates required for the customer to use in a season.
Units of measure for deliverables are the same unit of measure as on the agreement The agreement is valid as of the date a purchase order is generated You need to configure the vendor rebate agreements.
What should you do?

解説: (GoShiken メンバーにのみ表示されます)
You need to configure system attributes.
Which attribute types should you use? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
正解:
You are the production planner for a manufacturing company.
After running operations scheduling for a production order, the following error message displays:

You need to identify the cause of the error.
Which two actions should you perform? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.