An organization Is Implementing a new electronic medical record and has employed a project manager. At the first meeting, the project manager observes the following:
* The team estimates It Is one-fourth finished with Identifying benchmark organizations.
* Team members have not yet begun to identify the current state.
- They are halfway through collecting public data, which puts them slightly behind schedule for that task.
Which of the following tools should the quality Improvement project manager recommend?
* The team estimates It Is one-fourth finished with Identifying benchmark organizations.
* Team members have not yet begun to identify the current state.
- They are halfway through collecting public data, which puts them slightly behind schedule for that task.
Which of the following tools should the quality Improvement project manager recommend?
正解:B