1z0-1057-20試験無料問題集「Oracle Project Management Cloud 2020 Implementation Essentials 認定」

Your customer wants to see how quantity, cost, and revenue amounts are automatically distributed by using Spread Curve. Identify two period options that are available for this purpose. (Choose two.)

解説: (GoShiken メンバーにのみ表示されます)
You have four resources in your organization: P, Q, R, and S.
Resource P - Project or resource calendar is active.
Resource Q - Project resource request dates are within the project or resource calendar effective dates.
Resource R - Resource calendar is complex, it does not contain seven days, and it contains more than one pattern and shift.
Resource S - Number of working days within the requested date range is not zero on the project or resource calendar.
Identify the resource for whom Resource Availability Capacity Score will not be calculated. (Choose the best answer.)

解説: (GoShiken メンバーにのみ表示されます)
Identify three correct statements about the integration of Primavera P6 Enterprise Project Portfolio Management and Oracle Project Portfolio Management Cloud. (Choose three.)

正解:B,C,E 解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
In your customer site, the capitalized interest calculation is implemented on their project types. Which option represents the costs considered in the interest calculation? (Choose the best answer.)

解説: (GoShiken メンバーにのみ表示されます)
You have projects and tasks defined with transaction controls, which does not allow certain types of charges to the project. Your business needs to create invoices in AP with this project every period and hence would like to make the process easier by creating a distribution set. As you create the distribution set, you notice that these distribution set lines are not validated against the project transaction controls and you are allowed to save it without any validation errors. Identify the reason why the project transaction controls are not applied. (Choose the best answer.)

解説: (GoShiken メンバーにのみ表示されます)
Your customer complains that their project resources do not report their time promptly, which has resulted in incorrect reporting of project performance. What should you do to fix this problem? (Choose the best answer.)

Your customer wants to assign the Net 45 payment term to all sets except for the corporate business unit specific set, which is assigned the Net 15 payment term. At transaction entry, the list of values for payment terms consists of only one set of data: the set that is assigned to the transaction's business unit.
Which reference data sharing method would you set up to meet the customer requirement? (Choose the best answer.)

You have closed the project accounting period with a warning, but you are unable to close the accounting period due to an error.
Identify two reasons for this problem. (Choose two.)

解説: (GoShiken メンバーにのみ表示されます)
Your company creates a separate project for infrastructure services, so as to track these costs separately and then allocate to various projects that use the services of the infrastructure team. You want to allocate these costs by first attributing a fixed percentage of the source amount to each project and then spread it across tasks based on the actual labor hours charged to each task.
Which allocation basis method would you use to meet this requirement? (Choose the best answer.)

解説: (GoShiken メンバーにのみ表示されます)