1z0-1057-20試験無料問題集「Oracle Project Management Cloud 2020 Implementation Essentials 認定」
You have a small project for a period of five months. Your budget amount for each month is spread evenly and is $1000 per month. The first month actual expense is $800 and there is a commitment for $600. Now you generate a forecast at the beginning of the second month. Identify the monthly Estimate-To-Complete (ETC) amount that the application would calculate for the remaining four periods, when the ETC generation method includes commitments. (Choose the best answer.)
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
You have been asked to set up one active person, who is not a team member in the project, as a quality manager for each quality task created under projects. However, when you try to assign the quality manager as Task Manager, you cannot find the person's name in the list of values. What is the reason for this problem?
(Choose the best answer.)
(Choose the best answer.)
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
You are implementing Project Portfolio Management (PPM) for a professional services firm. The firm rents multiple buildings for its operations. At the end of each month, they review the rent expense for the month and want to allocate the rental cost to all the projects and tasks that are executed by associates in each of the buildings. The source amounts must be proportionally allocated to the tasks based on the raw costs of the tasks from the previous month. Considering that all these costs are in General Ledger, what three allocation setups should you complete in PPM? (Choose three
正解:A,C,D
解答を投票する