Planning Central has collected manufacturing data for a Work Order WO-2045 (Make Item AS1000), where actual duration of work order is 2 days. Item AS1000 manufacturing lead time is 1.25 days.
A plan is run and the Work Order WO-2045 is rescheduled.
Identify the duration of the rescheduled Work Order WO- 2045.
A plan is run and the Work Order WO-2045 is rescheduled.
Identify the duration of the rescheduled Work Order WO- 2045.
正解:C