A. Cost Plus Award Fee Contract (CPAF)
B. Time and Material Contract (TandM)
C. Cost Plus Incentive Fee Contract (CPIF)
D. Firm-Fixed -Price Contract (FFP)
A. Project scope statement
B. Project charter
C. Project document updates
D. Scope management plan
A. Planning
B. Executing
C. Monitoring and Controlling
D. Initiating
A. Create WBS
B. Perform Qualitative Risk Analysis
C. Direct and Manage Project Execution
D. Administer Procurements
A. out of the hands of the customer.
B. out of the process.
C. in line with a measured degree of conformity.
D. in a specified range of acceptable results.
A. Phase transitions
B. High-level deliverables
C. Success criteria
D. Project objectives
E. Cost
A. Estimate Costs
B. Determine Budget
C. Control Costs
D. Manage Cost Plan
A. Transfer
B. Exploit
C. Avoid
D. Accept
A. Cost estimates
B. Basis of estimates
C. Cost baseline
D. Control thresholds
A. Plan Resource Management
B. Define Activities
C. Estimate Activity Durations
D. Develop Schedule
E. Acquire Resources
A. Prompt lists and data analysis
B. Data analysis and risk audits
C. Reports and representations of uncertainty
D. Interpersonal and team skills and project management Information system