A scrum master is observing the daily coordination meeting of an agile development team. The scrum master realizes that one of the developers is confused about a business rule for the solution they are building.
How should the scrum master address this issue?
How should the scrum master address this issue?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
The product owner is present at the sprint review meeting and states that an estimation for the end of the project must be shared with the company's steering committee. The scrum master declares that the team reached an average velocity of 40 story points per sprint, considering a biweekly iteration. The team members predict that there are 240 story points remaining.
What is the estimated project conclusion?
What is the estimated project conclusion?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)