John works as a project manager of the NHQ Project. He has created the project network diagram as shown in the figure:
Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days?
Based on the project network diagram, how much float is available for Activity H if Activity B is delayed by four days and Activity E is delayed by two days?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
You work as a Project Manager for Dreams Unlimited Inc. You are looking for performance efficiencies of a project. The related key values are provided in the table below: MeasurementsValues BCWP (or EV)325 BCWS (or PV) 300 ACWP (or AC)410 What is the schedule variance (SV) of the project at the current point of time?
正解:D
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
You are the project manager for your organization. You are discussing an upcoming project with management and they would like you to begin decomposing the project work packages into activities as soon as possible. You have explained to the management that you would like to involve your roject team before the decomposition of the work packages begins. Why would you want your project team to involve in this activity?
正解:D
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
Nancy is the project manager of the JJJ Project. This project has recently been approved by the project customer as complete so Nancy must now finalize the administrative closure. Nancy needs to create the final project report to report the successes and failures in the project. Who should Nancy deliver this final project report to if she is participating in a projectized structure?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
You have a project to install 45,900 emergency exit signs throughout a university campus. You have a crew of 45 project team members to install the signs and they are making good progress on the installation but it looks like they'll miss the promised end date. Your project requires all of the signs to be installed one week before classes are scheduled to begin. You elect to crash the project in an effort to shorten the installation duration activity. What does it mean to crash the project?
正解:B
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
You are the project manager for your organization. You have created the project schedule and have presented it to the management for their approval. Management decides to enforce resource leveling heuristics on your project schedule. What will likely happen to your project now?
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
You are the project manager of the NHQ project. Your project has a budget of $1,258456 and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty-five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Based on the current performance value what should you report to management regarding the variance at completion?
正解:D
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
You work as a project manager for BlueWell Inc. Your project requires the project team to paint 1,500 hotel rooms. Your project team reports that it will take them approximately 4 hours to paint each hotel room. You reason, then, that it will take 6,000 hours to paint all of the hotel rooms. What type of an estimate are you creating in this scenario?
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
You work as the project manager for BlueWell Inc. You are recording the activity status for your project team's performance in the project. Based on the current performance your project is likely to be three months late. What type of communication should be generated based on this performance issue?
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
You are the project manager for your organization. You are working with your virtual team to create activity duration estimates for your current project. This virtual team is comprised of team members from around the world. Much of this process will be completed by geographical locations though some conferences will require all the team members to participate and to coordinate the activities that will interact between the different sites. The project manager must consider all of the following when creating the activity duration estimates except for which one?
正解:B
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
CORRECT TEXT
Fill in the blank with an appropriate phrase.
The __________ includes a description of any collateral services required, such as performance
reporting or post-project operational support for the procured item.
Fill in the blank with an appropriate phrase.
The __________ includes a description of any collateral services required, such as performance
reporting or post-project operational support for the procured item.
正解:
SOW