PMP試験無料問題集「PMI Project Management Professional (2025 Version) 認定」
A hybrid project team is working on an upgraded version of software for their product owner. The team is also responsible for supporting the existing product and customers. For the last three sprints, the team had to stop their project work and focus on major support items for the product owner. The testers are struggling to cope with the constant changes to the plan, which has resulted in a number of emotional outbursts.
How should the project manager proceed?
How should the project manager proceed?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
A multinational company has a plan to expand their business into a new country where they currently have no presence A project manager is assigned to initiate this project After reviewing the business case, what should be considered first when developing an appropriate implementation strategy?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
During the third iteration of a project, the main sponsor retired from the company, and a new sponsor was appointed. The new sponsor is not familiar with the agile approach for project delivery, which leads them to request more control over the project team.
What should the project manager do?
What should the project manager do?
正解:B
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
A project team member identified a procurement risk and sent an email to the project sponsor highlighting the risk.
The sponsor forwarded the email to the project manager asking for further details. After speaking with the sponsor, the project manager decided to take preventive action.
Which document should the project manager review with their team?
The sponsor forwarded the email to the project manager asking for further details. After speaking with the sponsor, the project manager decided to take preventive action.
Which document should the project manager review with their team?
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
A project for a new product launch is in a very initial stage and the requirements are evolving Due to stiff competition in the market, the customer would like to launch the product keeping the scope flexible. The project team intends to start the work based on the forecast of a similar project delivered last year Which project approach suits the scenario?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
Early prototypes developed in a project show an unacceptably high detect rate. The quality management plan calls for a cause-and-effect analysis to address quality problems as they arise.
What is the protect manager's first step in addressing the problem?
What is the protect manager's first step in addressing the problem?
正解:B
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value What should the new project manager do next?
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
In a financial company, a strategic project has been planned to use a predictive approach. During project planning, the product leader requests that milestones be submitted for review. There is a defined scope and an established deadline to conclude the project.
What should the project manager do first to meet the product leader's expectations?
What should the project manager do first to meet the product leader's expectations?
正解:B
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)