During stage 3, several BuildyBrick subcontractors are working on different work packages. The project manager is concerned that lessons identified by one team will not reach the others and could lead to rework, delay or additional cost. The project manager therefore holds a fortnightly cross-team 'lunch and learn' session.
Is this an appropriate application of the 'learn from experience' principle, and why?

解説: (GoShiken メンバーにのみ表示されます)
As stage 3 approaches its end, the project manager seeks supplier-related advice from the CEO of BuildyBrick, acting in the senior supplier interest, about planning the testing and inspections in stage 4.
Under which 'directing a project' activity is this informal consultation provided?

解説: (GoShiken メンバーにのみ表示されます)
During stage 1, the City Council purchasing team must prepare the contract that will govern BuildyBrick's later design and construction work. The project manager agrees with the purchasing team the products, time and cost for this work package.
Which practice is being applied through the 'controlling a stage' process?

解説: (GoShiken メンバーにのみ表示されます)
BuildyBrick is demobilizing after delivering the shopping centre on time and within budget. Before the remaining supplier personnel leave, the project manager checks that the Council's operations and facilities teams are ready to receive, operate and maintain the completed centre.
Why is this an appropriate application of the 'confirm project acceptance' activity?

解説: (GoShiken メンバーにのみ表示されます)
During initiation, the project team holds a product-based planning workshop to break the site-preparation and foundation products into greater detail. The analysis identifies the need for a more comprehensive and costly environmental impact assessment because of Louistown's 'green town' status.
During which 'initiating a project' activity should this workshop take place?

解説: (GoShiken メンバーにのみ表示されます)
In stage 4, work is late because the survey and utilities teams have not shared information needed by other teams, and morale is falling. The project manager considers a short weekly coordination forum for questions and information sharing, but rejects it solely because it would take time away from delivery.
Is this an appropriate approach to leading a successful team, and why?

解説: (GoShiken メンバーにのみ表示されます)