A PRPC application has a work object that represents a corporate account with thousands of members. When a member of an account registers with the application a related transaction must be recorded. There are generally two approaches for this design:
1) Embed the transactions as a PageList in the account object
2) Create transaction objects that are linked to the account
Which of the following statements is most accurate regarding the impact of locking on choosing between these approaches? (Choose One)
1) Embed the transactions as a PageList in the account object
2) Create transaction objects that are linked to the account
Which of the following statements is most accurate regarding the impact of locking on choosing between these approaches? (Choose One)
正解:C
解答を投票する
An application, created by MyCo, has a number of rules implemented as decision tables that use "Title" as an input as seen in the sample rule below:
MyCo is finding a number of application defects caused by incorrect spellings in the title field. The valid titles are stored as field values. MyCo is requesting options to help prevent these types of errors. Which of the following approaches is most applicable? (Choose One)
MyCo is finding a number of application defects caused by incorrect spellings in the title field. The valid titles are stored as field values. MyCo is requesting options to help prevent these types of errors. Which of the following approaches is most applicable? (Choose One)
正解:C
解答を投票する
Review the following requirement:
A loan application has as part of its process a step that sends a letter to an individual. After the letter is sent, the loan officer cannot do anything to the loan application for 14 days. After those 14 days, the next step is for the loan officer to review the case details and make a processing decision. During those 14 days, the individual who received the letter may call up the front office and provide new information about the application at which point the 14day hold is lifted and the work is routed to the underwriter for the decision. The business says in most cases this call does not occur and the 14 days lapses.
Given the information provided which design is most appropriate? (Choose One)
A loan application has as part of its process a step that sends a letter to an individual. After the letter is sent, the loan officer cannot do anything to the loan application for 14 days. After those 14 days, the next step is for the loan officer to review the case details and make a processing decision. During those 14 days, the individual who received the letter may call up the front office and provide new information about the application at which point the 14day hold is lifted and the work is routed to the underwriter for the decision. The business says in most cases this call does not occur and the 14 days lapses.
Given the information provided which design is most appropriate? (Choose One)
正解:D
解答を投票する
In a PurchaseOrder application, the ReviewOrderInformation screen displays the purchase order to the user for them to verify the entries before submitting for processing. In this screen the button label must display Confirm instead of Submit. Which of the following is the best option to handle this requirement? (Choose One)
正解:C