A. For table splitting the usage of MIGMON is not mandatory
B. MIGMON can be used to reduce the unload and load time significantly
C. After the data load, it is necessary to run update statistics to achieve the best possible performance.
D. Depending on the database type, the database is installed with or without support through R3SETUPor SAPINST
E. The last step in each migration process is to create database specific objects by calling SAP programsvia RFC
A. Perform runtime tests of critical reports/transactions
B. Run Reports to compare results to those in the source system
C. Set up a test environment
D. Test typical transactions from day-to-day business
A. Test systems
B. Development system
C. Productive system
D. Quality assurance system
A. NZDT Workbench used as a central migration controller
B. Trigger-based logging of tables changes in the source system
C. NZDT workbench used as a central migration controller
D. Flexible migration scenarios with or without R3LOAD based export of remaining tables.
A. Homogenerous/Heterogeneous system copy manuals should be for the respective SAP Note numbers.
B. The manuals for homogeneous and heterogenous system copies can be downloaded from the SAPservice marketing place.
C. SAP notes are available on homogenous and heterogenous system copies
D. Complete information about OS.DB Migrations is available in the SAP services Marketplace and theSAP Developer Network.
A. Make sure to include the dates for test and final migration steps of every SAP system, not only forproductive systems.
B. Does the migration project schedule meet the migration requirements
C. Technical feasibility
D. Is the migration partner technology consultant SAP-certified for migration
A. Perform the follow- up tasks
B. Transport/share the data export to the target system
C. Generate the target database
D. Install migration tools and prepare source system
E. Load the data export into the target database
F. H,A,C,B,J,D,E,F,G,I
G. A,H,B,C,J,E,D,F,G,I
H. Install the database software in the target system
I. Install the SAP products on target system
J. Export data from the SAP source system
K. A,C,B,J,E,D,F,G,H,I
L. Configure the test environment
M. Perform extensive tests on the migrated system
N. A,B,C,J,E,D,F,G,H,I
A. The production migration source system
B. The migrated production system after the final migration