Consider a scenario where you have started by displaying the planned costs for the entire project and how these planned costs are distributed among the various value categories for WBS element WBS 2.
You then want to analyze the planned costs of WBS element WBS 2 for value category 620 according to cost distribution to the various periods.
Which type of reporting allows you to achieve this?
Please choose the correct answer.
Response:
You then want to analyze the planned costs of WBS element WBS 2 for value category 620 according to cost distribution to the various periods.
Which type of reporting allows you to achieve this?
Please choose the correct answer.
Response:
正解:C