The business analyst at Cloud Kicks received verbal acceptance of all user stories by the product owner and set the status of the user stories to ''Ready for Development'' on a spreadsheet. The development team later reports are unable to confirm which user stories are ready to be built.
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
Universal Containers is nearing the launch date for its new Salesforce Loyalty Management program. The business analyst (BA) has ensured the user acceptance testing (UAT) plan has the proper test scripts.
What is another important item the BA should look for in the UAT plan?
What is another important item the BA should look for in the UAT plan?
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
Cloud Kicks leadership wants to use custom code for functionality that can easily be created declaratively in Sates Cloud. The business analyst (BA) has been asked to advise leadership on how these approaches impact their solution options.
What is one of the BA's strongest arguments for using configuration over code?
What is one of the BA's strongest arguments for using configuration over code?
正解:B
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
Universal Containers is working to improve Salesforce adoption. Customer reps are utilizing many Salesforce features in the org, but sales reps are still relying on their personal spreadsheets.
What should the business analyst do to better understand the sales reps process in order increase Salesforce adoption?
What should the business analyst do to better understand the sales reps process in order increase Salesforce adoption?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
Northern Trail Outfitters (NTO) has completed a project with a third-party event organization platform to enhance its MVP Experience Site. Many features were left in the project backlog. NTO's IT team is beginning a new phase of work on the Experience Site to build additional features requested by business stakeholders and wants to include the items that were left in the backlog in the first phase.
How should the business analyst coordinate the user stories to most efficiently manage the new project timeline?
How should the business analyst coordinate the user stories to most efficiently manage the new project timeline?
正解:C
解答を投票する
Northern Trail Outfitters (NTO) is working with an implementation partner to transform its customer support team with Service Cloud. A new business analyst (BA) who is a replacement from the partner was introduced to NTO stakeholders during the discovery phase of the project. The new BA is still getting to know each of the stakeholders when they start the requirements workshop. The BA asks a stakeholder a discovery question and they seem irritated.
What should the BA do to build trust with the stakeholder as the project continues?
What should the BA do to build trust with the stakeholder as the project continues?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
Universal Containers is in the discovery phase of a new Service Cloud project. The lead business analyst (BA) review user stories written by junior Bas. The lead BA discovers these user stories are missing details, as how case routing should work. The lead BA asks the junior Bas to make revisions based on the intended audience for the user stories.
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
The Sen/ice Center at Universal Containers (UC) uses Service Cloud and Experience Cloud to manage its customer case lifecycle. UC wants to limit the number of interactions a customer has during the lifecycle. The project leader has asked the business analyst (BA) to visually illustrate the lifecycle.
Which document should the BA create?
Which document should the BA create?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
A business analyst (BA) sees that all the acceptance criteria they wrote for an upcoming project go live have passed unit testing.
How can the BA support the protect team to ensure the solution meets the business's needs before demoing it to the relevant stakeholders?
How can the BA support the protect team to ensure the solution meets the business's needs before demoing it to the relevant stakeholders?
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
The customer service director at Universal Containers wants a self-service portal for customers using Experience Cloud. The director has a limited budget and wants the solution delivered before the end of the quarter.
After assessing several potential options, which solution should the business analyst recommend?
After assessing several potential options, which solution should the business analyst recommend?
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
Cloud Kicks (CK) wants to Improve the current business process for moving orders from the warehouse to the customer as part of a Commerce Cloud Implementation. The business analyst would like to gather more Information to create the future state process.
Who is the most appropriate subject matter expert (SME) to confirm the current business process and elicit deeper understanding of CK's goals, opportunities, and pain points?
Who is the most appropriate subject matter expert (SME) to confirm the current business process and elicit deeper understanding of CK's goals, opportunities, and pain points?
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
The business analyst (BA) at Cloud Kicks is managing a project to build a recruiting app for the management and human resources (HR) teams. The HR director wants the app to help the team navigate the hiring process more efficiently. The BA designs a Stakeholder Wheel to better understand all of the people with an interest m the project.
Which level of influence should the BA place the MR Director on the stakeholder wheel?
Which level of influence should the BA place the MR Director on the stakeholder wheel?
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
The technical team at Cloud Kicks is trying to deliver one of its Salesforce customizations. The business analyst (BA) has been asked to put assignments, test plans, decisions, and milestones in writing and share this document with stakeholders so there is less potential for confusion.
Which tactical document should the BA use to capture features?
Which tactical document should the BA use to capture features?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)