LEED-AP-ID-C試験無料問題集「USGBC LEED AP Interior Design + Construction (LEED AP ID+C) V4 認定」
A project's installed water fixtures do not exceed WaterSense maximum levels. Which compliance path should the LEED AP select under Water Efficiency Prerequisite, Indoor Water Use Reduction, and what type of documentation is required to demonstrate compliance with this path?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
A project team is pursuing certification for a performing arts center in an urban neighborhood. The project will earn one point from the Location and Transportation Credit, Surrounding Density and Diverse Uses. The project team is considering the Location and Transportation Credit for Reduced Parking Footprint. Which of the following needs to be included in the credit calculation?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
A project has performed an energy model which has resulted in the following energy end use consumption:

To meet the requirements for Energy and Atmosphere Credit, Advanced Energy Metering, Option 2.
Advanced Metering, energy meters must be installed for energy end uses in

To meet the requirements for Energy and Atmosphere Credit, Advanced Energy Metering, Option 2.
Advanced Metering, energy meters must be installed for energy end uses in
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)