An organization is evacuating their current datacenter and moving all workloads to a new datacenter. The organization has a total of 800 workloads to move, and the migration must be completed with no downtime within a planned change window that is scheduled to occur in four weeks.
What migration method will meet the requirements?
What migration method will meet the requirements?
正解:B
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
An architect was in an architectural workshop and noted the following business objectives:
* The solution must prioritize optimal end-to-end user shopping experience for customers accessing the website.
* The website must be available 24 x 7 x 365.
Which three conceptual model items relate to these business objectives? (Choose three.)
* The solution must prioritize optimal end-to-end user shopping experience for customers accessing the website.
* The website must be available 24 x 7 x 365.
Which three conceptual model items relate to these business objectives? (Choose three.)
正解:A,E,F
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
An architect is responsible for designing a new VMware Cloud Foundation (VCF)-based Private Cloud solution. During the requirements gathering workshop with key customer stakeholders, the following information was captured:
* The solution must ensure that all components meet a software version of N-1.
* The solution must ensure that all components meet a software version of N-1.
正解:B
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
An architect is expanding an existing private cloud infrastructure based on VMware Cloud Foundation (VCF).
The requirement is to deploy two additional instances of VCF at two separate datacenters within the existing private cloud with minimal additional footprint.
* Datacenter A is 90 miles from the existing VCF fleet instance with a network round trip time of 90ms.
* Datacenter B is 120 miles from the existing VCF fleet instance with a network round trip time of 120ms.
Which design decision would meet the requirement for this expansion?
The requirement is to deploy two additional instances of VCF at two separate datacenters within the existing private cloud with minimal additional footprint.
* Datacenter A is 90 miles from the existing VCF fleet instance with a network round trip time of 90ms.
* Datacenter B is 120 miles from the existing VCF fleet instance with a network round trip time of 120ms.
Which design decision would meet the requirement for this expansion?
正解:C
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
Discovery: Multiple business units (some from acquisitions) with separate AD instances. Each unit operates independently and requires dedicated development environments.
Requirement: Provide self-service provisioning through VCF Automation.
Which two design decisions should be included? (Choose two.)
Requirement: Provide self-service provisioning through VCF Automation.
Which two design decisions should be included? (Choose two.)
正解:D,E
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
During an initial design workshop with stakeholders, the architect was provided with an overview of the current state and other information required to proceed to the design phase.
The architect has assumed that the solution will need to support high availability for workloads.
Given the assumption, which statement should the architect document as a risk?
The architect has assumed that the solution will need to support high availability for workloads.
Given the assumption, which statement should the architect document as a risk?
正解:D
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)