A company is planning an upgrade from vSphere 4.x to vSphere 5. They currently have three dual CPU servers licensed for ESXi 4.1 Advanced
Each server has 256GB of RAM installed.
Their virtual machines are sized three ways.
Light. 1v CPU, 4GB RAM
Medium. 2v CPU, 8GB RAM
Heavy. 4 vCPU, 12GB RAM
The Production workload consists of.
20 Light servers
20 Medium servers
2 Heavy servers
The Development workload consists of.
10 Light servers
10 Medium servers
How will vSphere 5 licensing impact their upgrade? (Choose two.)
Each server has 256GB of RAM installed.
Their virtual machines are sized three ways.
Light. 1v CPU, 4GB RAM
Medium. 2v CPU, 8GB RAM
Heavy. 4 vCPU, 12GB RAM
The Production workload consists of.
20 Light servers
20 Medium servers
2 Heavy servers
The Development workload consists of.
10 Light servers
10 Medium servers
How will vSphere 5 licensing impact their upgrade? (Choose two.)
正解:A,D
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
An administrator deploys vCenter Server using the embedded Platform Services Controller.
After testing the deployment for a couple of months, it is determined that the environment would be better served with an external Platform Services Controller.
What should the administrator do to meet this new requirement?
After testing the deployment for a couple of months, it is determined that the environment would be better served with an external Platform Services Controller.
What should the administrator do to meet this new requirement?
正解:B
解答を投票する