Allen is the project manager for his organization. He is reviewing the resource requirements for his organization. He has discovered that his project needs Henry, the application developer, for two months, but Henry has a conflict and is already scheduled with another project manager in the organization. This is an example of which of the following?

おすすめの解答:D 解答を投票する

Section: Volume B
Explanation:
Because this project needs the specific resource of Henry, the application developer, and Henry is not available, it is considered as a resource constraint. Recall that a constraint is anything that limits the project manager's option.
Incorrect Answers:
A: While there may be some competition for skilled resources, such as Henry, the application developer, it is not the best answer for this question.
B: This is likely a matrix organization, but it is not the best answer for this question.
C: A resource requirement is simply the need for an application developer.

Mizutani 2024-03-30 02:58:19

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。