Activities in a project are discussed in a Work Breakdown Structure (WBS) session during the planning phase. Team members inform the project manager that whilst estimating the duration for activities, a lot of data exist about the effort required for each of them. Which estimation technique is best considered?
正解:D
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)