Which of the following are critical success factors for the introduction of standard tools and techniques to the P3O model?
1.Identify the benefits a tool will provide to an organization before focussing on its features
2.Ensure the complexity of the tools and techniques matches the capability maturity of the organization
3.Implement new tools as part of an organizational change programme
4.Implement tools simultaneously across all programmes and projects
1.Identify the benefits a tool will provide to an organization before focussing on its features
2.Ensure the complexity of the tools and techniques matches the capability maturity of the organization
3.Implement new tools as part of an organizational change programme
4.Implement tools simultaneously across all programmes and projects
正解:C
解答を投票する
Which of the following describe the governance responsibilities of a P3O model?
1.Provides the governance and control backbone for an organization's change initiatives
2.Provides a single source for all data relating to the organization's change initiatives
3.Implements rules for decision-making relating to programmes and projects
4.Makes decisions on behalf of the main board
1.Provides the governance and control backbone for an organization's change initiatives
2.Provides a single source for all data relating to the organization's change initiatives
3.Implements rules for decision-making relating to programmes and projects
4.Makes decisions on behalf of the main board
正解:C
解答を投票する
Which of the following actions are recommended when implementing a P3O model with Hub Portfolio Offices?
1.Appoint a P3O Sponsor to act as Senior Responsible Owner
2.Allow temporary offices to define their own standards and processes
3.Run the implementation as a programme with appropriate governance
4.Use appropriate programme management lifecycles and processes
1.Appoint a P3O Sponsor to act as Senior Responsible Owner
2.Allow temporary offices to define their own standards and processes
3.Run the implementation as a programme with appropriate governance
4.Use appropriate programme management lifecycles and processes
正解:A
解答を投票する