The function of the ATS input unit / MCCB input unit of the integrated UPS is ().

The alarm management functions supported by the ECC800 are (). (Multiple choice)

正解:A,B,C,D 解答を投票する
During the use of the battery pack, the appearance is normal, but there is no current during charging, and the voltage drop is zero at the moment of discharge, and it cannot be discharged. What could be happened in the following?

When a fire occurs in the cabinet, what is used to activate the gas fire extinguishing device on site?

In the stable operation of the NeCol5000-A35kW air conditioner compressor, the oil level observed by the oil sight is regarded as qualified at the ( ) position.

When the UPS is parallel, it is necessary to check the input phase sequence of each UPS main bypass, but the output phase sequence is not required.

Smart ETH sockets support up to () cascading.

When the NetCol5000-C commissions the drainage device, lift the high floater by hand for 5 seconds. At this time, the dual water pump is turned on at the same time, and the "discharge abnormality alarm" appears.

NeteCol can assign operational rights to user groups, or assign operational rights directly to users.