H20-923_V1.0試験無料問題集「Huawei HCSP-Field-Data Center Facility V1.0 認定」
After installing the FusionCol8000-C (110-440 kW), inject water to preserve the pressure for the chilled water pipes to how many MPa. After 30 minutes, check that no leakage occurs. Preserve the pressure for 24 hours. If the pressure drop is less than 0.01 MPa and no leakage occurs, the pipes do not leak.
正解:D
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)