Which three features are part of Oracle Fusion Functional Setup Manager?

正解:A,C,E 解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
Your customer has the following setups on the project plan type that they are using for their projects:
Use Task Planned Dates as Task Assignment Dates = Yes
Automatically Roll Up Task Planned Dates = Yes
Synchronize Task Transaction Dates with Planned Dates = No
With these setups in place, you perform the following actions:
1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of
01-Jul-2016.
2. Create another new subtask (Sub Task 2) after the previous action is saved.
What would the correct behavior of the application be after these actions? (Choose the best answer.)

解説: (GoShiken メンバーにのみ表示されます)
Your client organization has recently undergone a restructuring exercise that has resulted in the creation of new jobs. The Resource Breakdown Structure (RBS) was previously created with existing jobs, and now the new jobs have been added to the existing Resource Breakdown Structure.
Identify the correct statement about the RBS and new resources. (Choose the best answer.)

解説: (GoShiken メンバーにのみ表示されます)
Your business user has created a purchase order (PO) that has the following attributes:
Accrue at Receipt = Yes
Matching Option = 2 way
Receipt Close Tolerance = 100%
After approval, the PO is closed for receiving without creating a receipt. An AP invoice is created by matching to the PO. The user now runs Create Accounting for Receiving Transactions and then the "Import and Process Cost transactions" ESS (Enterprise Scheduler Service) job using the Transaction Source parameter as "Oracle Payables". The user notices that there is no cost transferred to the projects. Identify two reasons for this problem. (Choose two.)

Your customer wants to see how quantity, cost, and revenue amounts are automatically distributed by using Spread Curve. Identify two period options that are available for this purpose. (Choose two.)

解説: (GoShiken メンバーにのみ表示されます)
Your organization has been using project class categories and codes for reporting purposes and is set up at the project level. You recently defined a new project type, Capital-Contract, and created new class categories named Build, Operate, and Transfer (BOT) and Build, Transfer, and Maintain (BTM), with class codes of Yes/No. But on creation of a project, you are unable to associate these class categories and codes.
Identify two setups that are mandatory for these class categories and codes to be displayed. (Choose two.)

解説: (GoShiken メンバーにのみ表示されます)
Your client has implemented Oracle Cloud Applications with their United States business unit and United Kingdom business unit. After six months, they acquired another company in China and added a China business unit. A project accountant in your organization is authorized to access transactions for the US, UK, and China business units. The project accountant can see the transactions for the US and UK business units but not for the China business unit.Why is he not able to see the transactions for the China business unit? (Choose the best answer.)

Your customer wants to perform billing based on the Percent Spent invoice method. Identify two setups that are required in project contracts for calculating invoice amounts as per their requirement. (Choose two.)

解説: (GoShiken メンバーにのみ表示されます)
Which application would you use to map application roles to external roles? (Choose the best answer.)

解説: (GoShiken メンバーにのみ表示されます)
Your organization has been awarded a new contract based on which you are allowed to sell:
* Items not tracked in inventory
* Inventory items
* Services
Which contract structure would fulfill your requirement of item sales? (Choose the best answer.)