What are main innovations in manufacturing in SAP S/4HANA?
There are 3 correct answers to this question.
Response:

正解:C,D,E 解答を投票する
How can you avoid order proposals for planned independent requirements with dates in the past?
There are 2 correct answers to this question.
Response:

What are some of the advantages of using Kanban?
There are 2 correct answers to this question.
Response:

In the Manage Shortage view of the new SAP Fiori app "Monitor Material Coverage", what do the stars
indicate?
Please choose the correct answer.
Response:

During planning you are facing an overload situation on a resource. Which activities do you consider to
create a feasible production plan?
There are 3 correct answers to this question.
Response:

正解:A,B,D 解答を投票する
What capabilities does SAP S/4HANA embedded analytics provide?
There are 2 correct answers to this question.
Response:

Which of the following is used by the MRP Live planning run in SAP S/4HANA?
Please choose the correct answer.
Response:

In order to use strategy 70 - Planning At Assembly Level, what order field must be set besides the
planning strategy?
Please choose the correct answer.
Response:

Which of the following are included as SAP S/4HANA Sales Simplifications?
There are 3 correct answers to this question.
Response:

正解:A,B,E 解答を投票する
Which of the following are capabilities of multidimensional reporting in SAP S/4HANA embedded
analytics?
There are 3 correct answers to this question.
Response:

正解:B,D,E 解答を投票する