VDCD510試験無料問題集「VMware Certified Advanced Professional 5 - Data Center Design (VDCD510) 認定」
---
You have been asked to design a system with the following VMware functionality enabled:
R001: VMware HA must be functional.
R002: VMware SRM can be used between two sites for DR processes.
R003: You must be able to see all hosts from a single pane of glass.
From these requirements:
You have been asked to design a system with the following VMware functionality enabled:
R001: VMware HA must be functional.
R002: VMware SRM can be used between two sites for DR processes.
R003: You must be able to see all hosts from a single pane of glass.
From these requirements:
正解:A
解答を投票する
解説: (GoShiken メンバーにのみ表示されます)
You are a virtualization consultant at a company that develops its own inhouse website trading systems. The new website will be deployed in a vSphere 5 platform, which consists of two clusters and four ESXi hosts (one for each project-the SDLC hosts-for all levels of testing and development prior to production deployment).
The production cluster has been configured for fully automated DRS and VMware HA. During the SDLC, the website platform was developed on a single development ESXi host inside a single VLAN. The system was successfully tested within the SDLC ESXi hosts and then deployed to the production cluster in a single vApp and a single VLAN.
Following a successful midweek, the new application starts to show signs of latency. Suddenly several applications across the cluster are being impacted by network latency issues. Metrics are collected and show that the amount of network traffic between the database and application servers of the new website platform are at 96% utilization on the physical switch links between ESXi hosts in the production cluster. What should you do?
The production cluster has been configured for fully automated DRS and VMware HA. During the SDLC, the website platform was developed on a single development ESXi host inside a single VLAN. The system was successfully tested within the SDLC ESXi hosts and then deployed to the production cluster in a single vApp and a single VLAN.
Following a successful midweek, the new application starts to show signs of latency. Suddenly several applications across the cluster are being impacted by network latency issues. Metrics are collected and show that the amount of network traffic between the database and application servers of the new website platform are at 96% utilization on the physical switch links between ESXi hosts in the production cluster. What should you do?
正解:B