質問 17
What does the project status report allow project managers to do? (Choose two.)

  • A. Print as a PDF attachment
  • B. View the project Gantt chart
  • C. Show historical trend of project KPI's
  • D. View the WBS

正解: A,C

 

質問 18
What system role is needed to manage programs?

  • A. it_portfolio_manager_admin
  • B. it_program_manager
  • C. it_project_manager
  • D. it_program_manager_admin

正解: B

 

質問 19
Which roles can view reports on resource utilization and availability? (Choose two.)

  • A. pps_resource
  • B. resource_user
  • C. resource_manager
  • D. it_project_portfolio_user

正解: B,C

 

質問 20
If the Agile Development 2.0 plugin is activated, an idea can be converted into which of the following task types? (Choose three.)

  • A. SAFe feature
  • B. Story
  • C. Epic
  • D. Project
  • E. SAFe epic

正解: B,C,D

 

質問 21
How does a project manager request a change to a resource plan in the requested state?

  • A. Request change on resource plan
  • B. Email resource user.
  • C. Email resource manager
  • D. Use notes on resource plan.

正解: A

 

質問 22
In the base system, what is the default number of cards that can be displayed in the project workspace?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

正解: D

 

質問 23
What happens to the expense line after it is processed?

  • A. The actual amount incurred becomes part of the cost plan.
  • B. Nothing significant results.
  • C. The actual cost is recorded at the portfolio level.
  • D. The cost plan closes.

正解: A

 

質問 24
Where do you define 'Roles' requested via resource plans?

  • A. Resource roles under resource management.
  • B. No need to define it differently, they are same are system roles
  • C. Roles under system security
  • D. Under skill management modules

正解: A

 

質問 25
When a time card is approved, the actual time is stored in which two tables? (Choose two.)

  • A. Resource Event table
  • B. Resource Allocation Daily table
  • C. Resource Aggregate tables (Daily, Weekly, and Monthly)
  • D. Project Time table

正解: B,C

 

質問 26
A customer requires five (5) teamspaces to support different departments. What should you do?

  • A. Enable the teamspace property.
  • B. Contact the Account Representative to activate the teamspaces.
  • C. Use UI Policies and Business Rules to enable teamspaces.
  • D. Activate via each teamspace plugin.

正解: D

 

質問 27
What is the default schedule for a project?

  • A. 8-hour workday (from 9 to 5).
  • B. 8-hour workday (from 8 to 12 and 1 to 5).
  • C. 8-hour workday (from 9 to 12 and 1 to 6).
  • D. 9-hour workday (from 8 to 12 and from 1 to 5).

正解: B

 

質問 28
What is the demand workbench used for? (Choose two.)

  • A. Approving demands.
  • B. Displaying submitted demands to stakeholders.
  • C. Comparing demands with portfolios.
  • D. Comparing and prioritizing demands against other demands.

正解: B,D

 

質問 29
Who can submit Ideas?

  • A. Any IT user.
  • B. Any ITIL user.
  • C. Any user.
  • D. Any demand user.

正解: C

 

質問 30
Which 'Member Preference' automatically finds the most available resource(s) from the group and allocates to a plan using the allocation action?

  • A. Specific member.
  • B. Any member.
  • C. All members.
  • D. Any member and specific member.

正解: B

 

質問 31
What role can create or modify a rate model?

  • A. it_pps_admin.
  • B. release_admin.
  • C. push_admin.
  • D. time_card_admin.

正解: A

 

質問 32
The hourly rate is derived from the resource rate on the resource plan, if this option is selected.

  • A. Rate model
  • B. Planned cost
  • C. Rate override
  • D. Labor rate card

正解: A

 

質問 33
What applications are shared across teamspaces?

  • A. Agile, Test only.
  • B. Resource, Agile, Test
  • C. Project Financials, Agile, Test.
  • D. Resource, Project Financials, Agile

正解: B

 

質問 34
Which of the following roles can access the project administration application?

  • A. it_project_user.
  • B. it_pps_admin.
  • C. it_project_manager.
  • D. timecard_admin.

正解: B

 

質問 35
Plugins may be added to the base platform in one of the following ways: (Choose three.)

  • A. Activated by an admin (not by default).
  • B. Requested from ServiceNow.
  • C. Activated by an it_pps_admin.
  • D. Activated by an it_portfolio_manager.
  • E. Activated by default in the base ServiceNow system.

正解: A,B,E

 

質問 36
Depending on the execution type selected for a particular project, one of these dashboards will also be available:

  • A. Timecard Dashboard
  • B. User Manager Dashboard
  • C. Project Summary - Waterfall Dashboard
  • D. PMO Dashboard

正解: C

 

質問 37
In order for a business unit to have its own Idea Portal to retrieve data, what must be configured first?

  • A. Idea Portal URL
  • B. Idea categories
  • C. Idea module
  • D. A business unit cannot have its own its own Idea Portal

正解: C

 

質問 38
When creating a resource plan within a demand, how are the default dates on a resource plan determined?

  • A. Resource plan(s) cannot be created from demand
  • B. From portfolio date
  • C. Using demand created date
  • D. From demand start date and due date

正解: D

 

質問 39
What creates calendar entries on a users individual calendar? (Choose two.)

  • A. Planned resource plan.
  • B. Allocated resource plan.
  • C. Confirmed resource plan.
  • D. Approved resource plan.

正解: A,C

 

質問 40
Where are CAPEX and OPEX targets set for each fiscal year?

  • A. Demand Workbench
  • B. Program Workbench
  • C. Cost Plans
  • D. Portfolio Target

正解: D

 