質問 # 90
When measuring the temperature of an object using a radiometric imager, which two parameters have the greatest effect on accuracy of the temperature reading on the instrument?

  • A. Emissivity and background temperature
  • B. Range and span
  • C. Aperture and brightness
  • D. Relative humidity and ambient air temperature

正解:A


質問 # 91
Which of the following criteria is not normally used to determine if a piece of equipment is critical?

  • A. Its failure will result in loss of production.
  • B. The cost of repair or replacement is very high.
  • C. Its failure may result in the breach of environmental regulations.
  • D. Its failure will trigger the start-up of the spare.

正解:D


質問 # 92
Return on Assets (ROA) is determined by:

  • A. Net income/Total assets
  • B. Net income/Maintenance costs
  • C. Gross income/Total assets
  • D. Revenue/Total assets

正解:A


質問 # 93
What would dictate the basicminimum skill requirements for new Maintenance and Reliability employees?

  • A. The current level of plant (facility) technology
  • B. The content of the apprenticeship program
  • C. The skills available in the general workforce
  • D. The educational demographics of the region

正解:A


質問 # 94
What is the best way for a Maintenance and Reliability Program to use process parameters?

  • A. Correlate to changes in equipment condition
  • B. Assist in the explanation of failures
  • C. Assign detects to equipment and systems
  • D. Justify replacement equipment purchases

正解:A


質問 # 95
Which of the following statements best represents the primary objective of an inventory controlsystem for maintenance materials?

  • A. Reduce and sustain the maintenance costs of an organization.
  • B. Provide for accounting and managing of inventory.
  • C. Provide maintenance items when required and at the right price.
  • D. Balance the cost of inventory with the risk of running out of stock.

正解:D


質問 # 96
Inwhich of the following circumstances might it be appropriate to conduct a Failure Modes and Effects Analysis?

  • A. A custom-made production machine, critical to meeting production requirements, has failed for a third time in six months. The Maintenance Department has carefully inspected the machine after each failure, and each failure has been attributed to a loss of lubrication to the machine's bearings.
  • B. The Maintenance Department has assumed responsibility for maintenance of the equipment in a small production line acquired after buyout of a smaller competitor. The competitor uses equipment that is different from the company's existing equipment.
  • C. Corporate downsizing has reduced the staff of the Maintenance Department to two Reliability Technicians and two foremen for each craft (trade). These foremen will now manage contracted maintenance crews for all plant (facility) maintenance activities.
  • D. The Production Department has added a third production shift to meet increased sales. The new shift will be staffed mostly of new employees whose training consists of two weeks working with the day shift. Adding the third shift also increases equipment operating hours by 50%.

正解:B


質問 # 97
Two common reliability specifications to include in purchase orders for equipment are:

  • A. Availability (A) and Maximum Required Outage Time (MROT).
  • B. Guaranteed Uptime (GU) and Guaranteed Downtime (GD).
  • C. Mean Time Between Failures (MTBF) and Mean Time To Repair (MTTR).
  • D. Mean Time Between Repair (\1TBR) and Guaranteed Availability (GA).

正解:C


質問 # 98
Which ofthe following answers is not a critical factor in identifying customer requirements in developing a Maintenance and Reliability Program?

  • A. Validate customer requirements
  • B. Identify and prioritize requirements
  • C. Establish standard operating procedures
  • D. Define customer needs

正解:C


質問 # 99
What is the preferred method of obtaining failure information from operator rounds when the consequences of failure are severe and there is reason to doubt whether the tasks will be done without a formal reminder?

  • A. Train the operators in such a way that the inspections become second nature
  • B. Displaying the inspection schedule in a prominent location
  • C. Formal written or electronic checklist performed on a regular schedule
  • D. Maintenance checks incorporated into standard operating procedures

正解:C


質問 # 100
Which of the following is least likely to be linked to Maintenance and Reliability process improvements?

  • A. Improved product design
  • B. Lower operating costs
  • C. Better availability capability
  • D. Reduced rework

正解:B


質問 # 101
Total quality management focuses all employees on producing products that meet customer needs. This is done by:

  • A. Sharing information with all levels in the organization
  • B. Developing a high level of expertise in all employees
  • C. Balancing the needs of all stakeholders in the organization
  • D. Eliminating processes that waste time and materials

正解:B


質問 # 102
A maintenance superintendent (manager) has just joined the company and has read the company's statement of strategic direction in which it says. "Our most important goal is to increase the return on capital investment in our plants (facilities). All management incentive compensation will be reflected in the achievement of this goal" The new superintendent (manager) has asked the plant (facility) manager for a copy of the plan to achieve the company's goal The plant (facility) manager explains that such a plan does not exist, nor is there time to do one. The best next step for the superintendent (manager) should be to:

  • A. Develop and present a maintenance plan to increase return on capital investment to management.
  • B. Discuss the role of maintenance in improving return on capital investment with the head of manufacturing.
  • C. Wait until the plant (facility) manager develops a plan to improve return on capital investment and then develop the maintenance plan.
  • D. Develop a program to defer maintenance tasks to reduce expenses and increase return on capital investment.

正解:A


質問 # 103
Which of the following is the best definition of a work-team?

  • A. The team defines mission and direction Supervision and the team are responsible for accomplishing the goals.
  • B. The team defines direction and conducts peer performance assessments.
  • C. Supervision defines mission, direction, and assesses performance. The team is largely self-governing and is responsible for accomplishing goals.
  • D. Supervision provides all work direction and holds the team accountable for results.

正解:C


質問 # 104
You are the maintenance manager for a manufacturing plant (facility) that runs 24 hours a day, seven days a week. The product is selling well. The business is healthy. Which consideration will bring the most value to your business when planning your next major shutdown of your operating area?

  • A. Make full utilization of manpower during the shutdown period
  • B. Keeping the cost within budget
  • C. Delay the shutdown until an equipment failure forces the plant (facility) down
  • D. Limit the work to only jobs that require a shutdown to perform

正解:D


質問 # 105
Motor current analysis reveals an unbalanced motor current in excess of 40% when the motor is loaded to over
70% of its nameplate full bad ampere rating. What should you suspect and or what should you do?

  • A. Order more on-line tests to confirm the problem, allowing production to continue as long as possible.
  • B. Order the motor to be removed from service immediately, since failure due to overheated winding insulation is imminent.
  • C. Do nothing. Current unbalance is normal in a motor that is not fully loaded.
  • D. Atthe first opportunity, shut down the motor and have motor circuit analysis performed to locate the cause so it can be corrected.

正解:A


質問 # 106
After management leadership and employee involvement, what is the next step in creating a good safety and health program?

  • A. Examination and analysis of work processes and working conditions
  • B. Finding the right person to be the safety and health manager
  • C. Getting employee engagement and buy-in
  • D. Kick-off event such as a safety and health lair

正解:A


質問 # 107
A plant (facility) has acquired three new screw pumps to replace centrifugal pumps. Within two months of installation it is found the seals have deteriorated allowing the release of hazardous chemicals into the work place. Which of the following is the best step that the maintenance or reliability leader could have taken to prevent this failure from occurring?

  • A. Assured an experienced maintenance representative worked on the design review of the pumps
  • B. Reviewed and selected manufacturer's to bid on the screw pumps based on their past performance
  • C. Participated in the development of manufacturer's standards for screw pumps and seal designs
  • D. Ensured the project provided an enclosure to contain fluids in the event of a seal leak

正解:A


質問 # 108
One of our five pumps fails each month. We have been getting 45 days of service out of our dryer belts. We have to fix five piping leaks per month. We have had to replace three of our 25 air cylinders in the last two years. If a Pareto diagram was created for this failure data, which equipment type would show the highest failure frequency?

  • A. Dryer belts
  • B. Pumps
  • C. Piping
  • D. Air cylinders

正解:C


質問 # 109
For which of the following elements is the maintenance manager directly responsible?

  • A. Equipment failure probability
  • B. Equipment operating practices
  • C. Optimization of maintenance costs
  • D. Life cycle costs of equipment

正解:C


質問 # 110
Reliability predictions are often expressed in terms of Mean Time Between Failures (MTBF) or its reciprocal.The reciprocal is known as the:

  • A. Service Life.
  • B. Mean Time To Failure.
  • C. Failure Rate.
  • D. Failure Mode.