
合格させるGAQM CSM-001試験最速合格
準備CSM-001問題解答でCSM-001試験問題集
質問 # 58
Which of the following might the Scrum Team discuss during a Sprint Retrospective?
- A. Skills needed to improve the Development Team's ability to deliver
- B. The way the Scrum Team does Sprint Planning
- C. All of the above
- D. Methods of communication
- E. Its Definition of Done
正解:C
質問 # 59
A classification for any development methodology based on iterative and incremental development, where requirements and solutions evolve through collaboration between self-organizing, cross-functional teams is called:
- A. Scrum
- B. Application Development
- C. Agile Development
- D. Waterfall Development
正解:C
解説:
Explanation/Reference:
質問 # 60
During the sprint review the project is assessed against the ____________
- A. Sprint Planning
- B. Sprint retrospective
- C. Sprint goal
- D. Sprint review
正解:C
質問 # 61
True or False: Scrum is a collaborative effort involving developers and customers in an ongoing dialog?
- A. False
- B. True
正解:B
質問 # 62
___________________is responsible for the Scrum process, facilitate the team and protect the team from outside noise.
- A. Product Owner
- B. Scrum Owner
- C. Stakeholder
- D. Scrum Master
正解:D
質問 # 63
Under what circumstances should separate Product Backlogs be maintained?
- A. There are multiple product features being developed by the same team.
- B. There are multiple teams working on the components of the same product. Each team should an independent Product Backlog
- C. There are several Product Owners for one product. Each Product Owner should have their own Product Backlog
- D. There are multiple teams working on independent products. Each unique combination of team and product should have an independent Product Backlog
正解:D
質問 # 64
Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?
- A. This forces Product Owners to focus on what is really important for the team to develop.
- B. The development team cannot meet their Sprint commitment to complete work if requirements are changing
- C. A Sprint cycle is not enough time for senior management review and approve changes
- D. The development team must be able to limit the Product Owner authority
正解:A
質問 # 65
What is an ideal size for a Scrum team?
- A. 0
- B. 1
- C. 2
- D. 3
正解:C
質問 # 66
Who acts as a facilitator between Product Owner and Team in a project?
- A. Process Owner
- B. ScrumMaster
- C. Developer
- D. Stakeholder
正解:B
質問 # 67
How many hours per day should a person on a Scrum team work?
- A. 14 hours.
- B. However many hours are needed to get the work done.
- C. An "ideal day" measuring only when he or she is productive.
- D. A sustainable pace, usually from 7-8 hours per day.
正解:D
質問 # 68
What is the Scrum?
- A. Scrum is a complete process to develop software
- B. It's not a Agile Framework
- C. A framework within which people can address complex adaptive problems, while productively and creativelydelivering products of the highest possible value
- D. None of above
正解:C
質問 # 69
What happens when the Sprint is cancelled?
- A. The completed Sprint Backlog items are evaluated for a release and incomplete items are put back to the Product Backlog
- B. The Scrum Team disbands immediately
- C. The completed Sprint Backlog items are evaluated for a release and incomplete items are ignored.
- D. The complete Sprint Backlog is put back to the Product Backlog
正解:A
質問 # 70
_____________ can change the priority of items in the _________ backlog at any time.
- A. The Product Owner(s); Sprint
- B. The Scrum Master; Sprint
- C. The Team; Product
- D. The Product Owner(s); Product
正解:D
質問 # 71
Upon what type of process control is Scrum based?
- A. Defined
- B. Complex
- C. Empirical
- D. Hybrid
正解:C
質問 # 72
Which of the following is not a Scrum cycle activity?
- A. Weekly inspection
- B. Sprint retrospective
- C. Sprint planning
- D. Daily scrum
正解:A
質問 # 73
......
リアルGAQM CSM-001試験問題 [更新されたのは2023年]:https://www.goshiken.com/GAQM/CSM-001-mondaishu.html
無料CSM-001試験問題集には合格させるお手軽に試験合格:https://drive.google.com/open?id=1seW7YMhFLHKLrBn8_Rmgx9H4jX_crRb3