更新された2025年10月テストエンジン練習CFI-I問題集と練習試験合格させます [Q59-Q76]

Share

更新された2025年10月テストエンジン練習CFI-I問題集と練習試験合格させます

問題集お試しセットCFI-Iテストエンジンで問題集トレーニングには100問あります

質問 # 59
What is the maximum area allowed for draft stops provided between a suspended ceiling and the floor above?

  • A. 1,500 ft² (140 m²)
  • B. 3,000 ft² (280 m²)
  • C. 500 ft² (46 m²)
  • D. 1,000 ft² (93 m²)

正解:D

解説:
Comprehensive and Detailed Step-by-Step Explanation:
Draft Stops and Fire Protection:
Draft stops are installed to limit the spread of smoke and heat in concealed spaces, such as the area between a suspended ceiling and the floor above.
According to NFPA 13 (Standard for the Installation of Sprinkler Systems), Section 8.15.1.2.4, the maximum area for draft stops is 1,000 ft² (93 m²).
Purpose of Limiting Area:
Limiting the area to 1,000 ft² ensures smoke and fire are contained within smaller sections, slowing the spread and improving fire control by sprinklers.
Other Options Explained:
Option A (500 ft²): Too small; not the maximum allowed under NFPA 13.
Option C (1,500 ft²) and Option D (3,000 ft²): Exceed the allowable area for draft stops.
Summary:
The maximum area allowed for draft stops provided between a suspended ceiling and the floor above is 1,000 ft² (93 m²) per NFPA 13.


質問 # 60
What is the minimum required total stair width in a non-sprinklered hotel with an occupancy capacity of 650?

  • A. 130 in. (3,302 mm)
  • B. 217 in. (5,512 mm)
  • C. 195 in. (4,953 mm)
  • D. 455 in. (11,557 mm)

正解:C

解説:
Comprehensive and Detailed Step-by-Step Explanation:
Egress Width Calculation:
According to NFPA 101 (Life Safety Code), Section 7.3.3.1, for non-sprinklered occupancies, the required stair width is 0.3 inches per occupant.
Calculation:
Occupancy capacity = 650 people
Required stair width = 0.3in.×650=195inches0.3 \, \text{in.} \times 650 = 195 \, \text{inches}0.3in.×650=195inches.
Other Options Explained:
Option A (130 in): Too small for 650 occupants.
Option C (217 in): Exceeds the requirement.
Option D (455 in): Far exceeds the requirement.
Summary:
The minimum required total stair width for a non-sprinklered hotel with an occupancy capacity of 650 is 195 inches.


質問 # 61
When may acoustical and decorative materials such as cotton, hay, paper, straw, moss, split bamboo, and wood chips be used as decorations within an assembly occupancy?

  • A. When they meet independent third-party certification
  • B. When flame-retardant treated to the satisfaction of the AHJ
  • C. When small quantities are used
  • D. Materials not permitted

正解:B

解説:
Acoustical and decorative materials pose a significant fire hazard due to their combustibility. According to NFPA 101, Life Safety Code, Section 10.3.1, and related standards:
Such materials may only be used if they are flame-retardant treated or inherently noncombustible.
The treatment must be to the satisfaction of the Authority Having Jurisdiction (AHJ), ensuring compliance with testing requirements (e.g., NFPA 701).
Small quantities (B): Even small quantities can pose risks, so this is insufficient justification.
Third-party certification (C): While helpful, AHJ approval is still required.
Reference:
NFPA 101, Section 10.3.1: Requirements for interior finishes, decorations, and trim.
NFPA 701: Testing standards for flame retardancy of textiles and materials.


質問 # 62
Spray undercoating or spray body lining of vehicles shall be conducted a minimum of what distance from open flames or spark-producing equipment?

  • A. 20 ft (6,100 mm)
  • B. 10 ft (3,048 mm)
  • C. 5 ft (1,524 mm)
  • D. 3 ft (914 mm)

正解:A

解説:
The minimum distance required for spray undercoating or spray body lining of vehicles from open flames or spark-producing equipment is specified in NFPA 33, Standard for Spray Application Using Flammable or Combustible Materials.
Spraying operations involving combustible coatings pose a significant fire risk due to flammable vapors, which can ignite from open flames or sparks.
To ensure safety, these operations must be conducted at least 20 feet (6,100 mm) away from ignition sources, as vapors can travel and accumulate in the surrounding air.
3 ft (914 mm) (A) and 5 ft (1,524 mm) (B) are insufficient to prevent ignition.
10 ft (3,048 mm) (C) may be acceptable for certain low-risk operations but does not meet the requirements for vehicle spray applications.
Reference:
NFPA 33, Section 9.3: Minimum distance from open flames and spark-producing equipment.


質問 # 63
A blue-coded sprinkler head has a maximum ceiling temperature of:

  • A. 150°F (66°C)
  • B. 225°F (107°C)
  • C. 300°F (149°C)
  • D. 100°F (38°C)

正解:B

解説:
Comprehensive and Detailed Step-by-Step Explanation:
Sprinkler Head Color Coding:
Sprinkler heads are color-coded to indicate their maximum ceiling temperature and activation range, as defined in NFPA 13 (Standard for the Installation of Sprinkler Systems).
Blue color corresponds to a maximum ceiling temperature of 225°F (107°C), with an activation temperature range of 200°F to 225°F.
Other Options Explained:
Option A (100°F): Incorrect; corresponds to uncolored or ordinary-temperature sprinkler heads.
Option B (150°F): Incorrect; corresponds to intermediate-temperature sprinkler heads (yellow-coded).
Option D (300°F): Exceeds the blue-coded range; corresponds to orange-coded high-temperature sprinklers.
Summary:
A blue-coded sprinkler head has a maximum ceiling temperature of 225°F (107°C).


質問 # 64
What is the maximum permitted height for stored Class 2 oxidizers in a nonsprinklered retail sales area that is open to the public?

  • A. 6 ft (1.8 m)
  • B. 5 ft (1.5 m)
  • C. 12 ft (3.7 m)
  • D. 3 ft (1.0 m)

正解:B

解説:
Comprehensive and Detailed Step-by-Step Explanation:
Storage of Class 2 Oxidizers:
Per NFPA 430 (Code for the Storage of Liquid and Solid Oxidizers), Section 6.3.4, in nonsprinklered retail sales areas open to the public, Class 2 oxidizers must not be stored at heights exceeding 5 feet (1.5 meters).
Why 5 Feet is the Limit:
Limiting the height reduces the risk of spills, accidental damage, and fire spread in a retail environment.
Other Options Explained:
Option A (3 ft): Too restrictive; NFPA allows up to 5 ft.
Option C (6 ft) and Option D (12 ft): Exceed the maximum permitted height for nonsprinklered areas.
Summary:
The maximum height for stored Class 2 oxidizers in a nonsprinklered retail area open to the public is 5 feet (1.5 meters).


質問 # 65
All of the following information regarding a fire prevention inspection must be maintained by the AHJ EXCEPT:

  • A. A summary of the violations found
  • B. Responsible party at the inspection
  • C. The final deposition of all violations
  • D. The date of the service of notices

正解:B

解説:
Comprehensive and Detailed Step-by-Step Explanation:
Fire Prevention Inspection Documentation:
Per NFPA 1 (Fire Code), Section 1.7.4, the AHJ (Authority Having Jurisdiction) must maintain specific records related to fire inspections to ensure compliance and provide a legal record.
Required Information Includes:
Date of the service of notices (A): Ensures proper communication and enforcement of violations.
Final disposition of all violations (B): Indicates whether violations were corrected or actions taken.
Summary of violations found (C): Documents what issues were identified during the inspection.
Why Responsible Party (D) is Excluded:
While the responsible party may be part of the inspection process, it is not a mandatory record to be maintained permanently by the AHJ under NFPA 1.
Summary:
The responsible party at the inspection is not a required record for fire prevention inspections.


質問 # 66
In occupancies where a Class A or Class B interior finish is required, which of the following is the allowable amount of Class C materials?

  • A. 20 percent
  • B. 10 percent
  • C. 5 percent
  • D. 15 percent

正解:B

解説:
The use of interior finish materials is regulated by NFPA 101, Life Safety Code, Section 10.2.3. In occupancies where Class A or Class B interior finishes are required:
A limited percentage of Class C materials may be allowed as incidental decoration or finish, provided it does not pose significant fire risk.
The allowable amount of Class C materials is limited to 10 percent of the total wall and ceiling area within the space.
This restriction ensures that the overall fire performance of the interior finish remains within acceptable safety limits.
5 percent (A): Too restrictive compared to NFPA allowances.
15 percent (C) and 20 percent (D): Exceed the permissible amount under Class A or B requirements.
Reference:
NFPA 101, Section 10.2.3: Interior finish requirements and allowable material classifications


質問 # 67
To transfer Class I flammable liquids by pressurizing the tank, which of the following conditions must be met?
I . Inert gas is used to pressurize the tank.
II . Air is used to pressurize the tank.
III . A pressure relief device shall be provided.
IV . An interlock shall be installed on the container.

  • A. I and IV
  • B. I and III
  • C. II and IV
  • D. II and III

正解:B

解説:
Transferring Class I flammable liquids involves strict safety conditions to prevent fire or explosion risks. According to NFPA 30, Flammable and Combustible Liquids Code:
Inert gas (I): Pressurizing the tank with inert gas (e.g., nitrogen) is required to prevent the creation of a flammable atmosphere. Air (II) is not acceptable because it introduces oxygen, which can result in combustion.
Pressure relief device (III): A pressure relief device is mandatory to prevent over-pressurization, which could cause a tank failure or explosion.
Interlock (IV): While useful for operational safety, it is not specifically required for pressurizing tanks.
Reference:
NFPA 30, Chapter 18: Requirements for transferring flammable liquids under pressure.


質問 # 68
Guard posts protecting hazardous material use, dispensing, or storage areas from vehicles must be a minimum of how many feet (meters) from the tank?

  • A. 2 ft (0.6 m)
  • B. 5 ft (1.5 m)
  • C. 4 ft (1.2 m)
  • D. 3 ft (0.9 m)

正解:B

解説:
Comprehensive and Detailed Step-by-Step Explanation:
Guard Post Requirements:
Per NFPA 1 (Fire Code), Section 60.5.1.9, guard posts installed to protect hazardous material areas from vehicular impact must be placed at least 5 feet (1.5 m) from the tank.
Purpose of the 5-Foot Requirement:
Ensures adequate buffer space between the vehicle barrier and hazardous materials, reducing the risk of damage or spills from accidental collisions.
Other Options Explained:
Options A (2 ft), B (3 ft), and C (4 ft): Do not meet the minimum distance requirement under NFPA standards.
Summary:
Guard posts must be installed 5 feet (1.5 m) from hazardous material tanks to ensure proper protection.


質問 # 69
Which of the following systems has a quick-opening device?

  • A. Dry-pipe system
  • B. Preaction system
  • C. Wet-pipe system
  • D. Deluge system

正解:A

解説:
Comprehensive and Detailed Step-by-Step Explanation:
Quick-Opening Devices:
A quick-opening device is used in dry-pipe sprinkler systems to accelerate the operation of the system and reduce the delay caused by air in the pipes.
Why Dry-Pipe Systems Use It:
Dry-pipe systems are filled with air or nitrogen instead of water. When a sprinkler activates, the air must be released before water can flow.
Quick-opening devices, like accelerators or exhausters, speed up the release of air to minimize response time.
Other Options Explained:
Option B (Wet-pipe system): Always filled with water; no delay or need for quick-opening devices.
Option C (Preaction system): Uses air but often requires detection activation, not quick-opening devices.
Option D (Deluge system): Opens immediately but does not require quick-opening devices as pipes are already open.
Summary:
A dry-pipe system uses a quick-opening device to reduce activation delays caused by air in the pipes.


質問 # 70
Which one of the following is a primary reason for issuing a permit?

  • A. To establish the economic feasibility of a project
  • B. To allow the requester to meet less restrictive code requirements
  • C. To meet fire insurance requirements
  • D. To make the jurisdiction aware of potentially hazardous situations or conditions

正解:D

解説:
Comprehensive and Detailed Step-by-Step Explanation:
Purpose of Permits:
Permits are issued primarily to ensure the jurisdiction (Authority Having Jurisdiction - AHJ) is aware of potentially hazardous situations or conditions and can enforce compliance with fire and safety codes.
Permits also provide an opportunity to inspect operations, processes, or structures to ensure safety.
NFPA References:
According to NFPA 1 (Fire Code), permits are required for activities that could pose risks, such as hazardous materials, fire protection system installations, and occupancy changes.
Other Options Explained:
Option A (To meet fire insurance requirements): Permits are not issued for insurance purposes, although compliance may indirectly affect insurance.
Option C (Less restrictive code requirements): Permits are not for bypassing codes.
Option D (Economic feasibility): Economic factors are unrelated to the permitting process.
Summary:
Permits are issued to make the jurisdiction aware of potentially hazardous situations or conditions and ensure compliance with fire safety regulations.


質問 # 71
Any person may appeal a decision of the AHJ to the board of appeals when which of the following conditions exist?

  • A. The true intent of the code or ordinance has been incorrectly interpreted
  • B. The decision reportedly creates a financial hardship
  • C. The decision was rendered outside the normal business hours of the AHJ
  • D. The specific type of facility has not been built in the jurisdiction

正解:A

解説:
Comprehensive and Detailed Step-by-Step Explanation:
AHJ (Authority Having Jurisdiction):
The AHJ refers to the individual or entity with the responsibility for enforcing codes, standards, or ordinances related to fire safety and building construction. Examples include fire marshals, building officials, or fire inspectors.
Basis for Appeal:
Appeals are typically allowed when a decision made by the AHJ is believed to be inconsistent with the true intent of the code or ordinance.
This aligns with NFPA 1 (Fire Code) and NFPA 101 (Life Safety Code), which emphasize correct application and interpretation of fire and life safety codes.
If an inspector applies a provision incorrectly or misinterprets its intent, stakeholders can appeal to ensure proper enforcement.
Other Options Explained:
Option A: "The decision reportedly creates a financial hardship"
Financial hardship is not a valid basis for an appeal. Codes exist to ensure public safety, and compliance cannot be waived simply due to cost.
Option C: "The decision was rendered outside the normal business hours of the AHJ" The time of the decision does not affect its validity. Decisions must adhere to the codes regardless of when they are made.
Option D: "The specific type of facility has not been built in the jurisdiction" The absence of a particular facility type does not invalidate the AHJ's decisions or the applicability of the code.
Code References:
NFPA 1 (Fire Code), Section 1.10 - Board of Appeals:
NFPA 1 explicitly states that an appeal may occur when the true intent of the code is questioned or has been incorrectly interpreted.
NFPA 101, Section 1.4 - Equivalency and Appeals:
Ensures proper evaluation of the AHJ's interpretation when there is a dispute over compliance.
Summary:
The true intent of the code must be upheld to ensure safety and consistency. When the AHJ's decision appears to misrepresent the intent of the code or ordinance, the affected party has the right to appeal.


質問 # 72
New underground and limited access structures require an approved, supervised, automatic sprinkler system, when the occupant load meets or exceeds how many people?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

正解:A

解説:
Comprehensive and Detailed Step-by-Step Explanation:
Sprinkler System Requirement:
According to NFPA 101 (Life Safety Code), Section 11.8, new underground and limited-access structures with an occupant load of 20 or more people are required to have an approved, supervised automatic sprinkler system.
Why 20 People is the Threshold:
Underground and limited-access structures pose unique fire and life safety challenges due to restricted egress and ventilation.
Automatic sprinkler systems mitigate fire hazards by controlling or suppressing the fire, allowing time for evacuation.
Other Options Explained:
Option A (10 people): Not the specified threshold.
Option C (40 people) and Option D (50 people): Too high; NFPA sets the limit at 20 people for these structures.
Summary:
An automatic sprinkler system is required when the occupant load in new underground or limited-access structures meets or exceeds 20 people.


質問 # 73
Which of the following requires an emergency plan?

  • A. A special amusement building
  • B. A two-story office building
  • C. A grocery store
  • D. A three-story parking garage

正解:A

解説:
Comprehensive and Detailed Step-by-Step Explanation:
Emergency Plan Requirements:
According to NFPA 101 (Life Safety Code), Section 12.4.1, special occupancies like special amusement buildings are required to have an emergency plan due to their unique fire hazards, including lighting effects, confined pathways, and high fire risk.
Why Special Amusement Buildings Need a Plan:
These structures often have complex layouts and unique hazards, increasing the need for a clear and practiced emergency plan.
Other Options Explained:
Option A (Parking garage): Typically does not require an emergency plan unless additional hazards exist.
Option B (Grocery store): Emergency plans are usually required for larger assembly or high-risk occupancies.
Option C (Two-story office building): Generally does not require an emergency plan unless it exceeds occupancy thresholds.
Summary:
A special amusement building requires an emergency plan due to its unique fire and egress hazards.


質問 # 74
Which of the following is not the responsibility of the installing contractor when pursuing approval of sprinkler systems and private fire service mains?

  • A. Complete and sign the appropriate contractor's materials and test certificates
  • B. Perform all required acceptance tests
  • C. Perform annual tests on all existing systems
  • D. Notify the AHJ of the time and date testing will be performed

正解:C

解説:
Responsibilities of the installing contractor for sprinkler systems and private fire service mains are specified in NFPA 13, Standard for the Installation of Sprinkler Systems:
Notify the AHJ (A): The contractor must inform the AHJ about the date and time of acceptance tests.
Perform all required acceptance tests (B): Contractors are responsible for conducting these tests to ensure the system meets NFPA standards.
Complete and sign test certificates (D): The contractor must certify the materials and tests by completing and signing the appropriate documents.
Perform annual tests on all existing systems (C): This is not the contractor's responsibility. Annual testing and maintenance are typically handled by the building owner or their representative under NFPA 25, Standard for the Inspection, Testing, and Maintenance of Water-Based Fire Protection Systems.
Reference:
NFPA 13, Chapter 24: Responsibilities of the installing contractor.
NFPA 25: Maintenance and testing responsibilities for existing systems.


質問 # 75
What is the process used by a jurisdiction to adopt an NFPA code or standard into law by reference?

  • A. The title and publishing information is referenced in a law, ordinance, or similar instrument.
  • B. The entire document and effective date are copied into a law, ordinance, or similar instrument.
  • C. The jurisdiction publishes the document information and effective date in a public notice.
  • D. The jurisdiction notifies the NFPA that they will be enforcing a specific code or standard.

正解:A

解説:
Comprehensive and Detailed Step-by-Step Explanation:
Adoption by Reference:
Adoption by reference is a legal process where a jurisdiction incorporates an NFPA code or standard into law without reproducing the entire document.
The title and publishing information are referenced in a law, ordinance, or similar legal instrument.
Benefits of Adoption by Reference:
Avoids duplicating lengthy documents.
Ensures that the most recent, standardized NFPA code or standard is legally enforceable.
Other Options Explained:
Option A (Public notice): Public notices inform stakeholders but are not the legal process for adoption.
Option B (Notify NFPA): Notifying NFPA is not part of the adoption process.
Option D (Copy entire document): Copying the full text is unnecessary and inefficient.
Summary:
The adoption process involves referencing the title and publishing information of the NFPA code or standard in a law, ordinance, or similar instrument.


質問 # 76
......


NFPA CFI-I 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • 防火システムと設備: このセクションでは、防火技術者のスキルを評価し、消火システム、警報システム、携帯用消火器の運用準備状況を判断することに重点を置いています。
トピック 2
  • 占有タイプ: このセクションでは、集会施設、教育施設、医療施設など、さまざまな占有タイプの火災および生命安全システムを評価する受験者の能力がテストされます。
トピック 3
  • 危険物質および材料の保管、取り扱い、使用: このモジュールでは、消防検査官のスキルを測定し、機器、プロセス、および操作における危険な状態の認識が含まれます。
トピック 4
  • 管理: この試験セクションでは、消防検査官のスキルを測定し、検査レポートの作成、許可の必要性の特定、計画の見直しが必要な時期の認識などをカバーします。また、苦情の調査、適用可能な規則の特定、法的手続きへの参加も含まれます。測定される重要なスキルの 1 つは、調査結果を書面によるレポートで明確に伝えることです。

 

NFPA CFI-I問題集カバー率リアル試験問題:https://www.goshiken.com/NFPA/CFI-I-mondaishu.html

リアルCFI-I問題集でNFPA問題集PDF:https://drive.google.com/open?id=1sd5ayl7cfL0OJ7xNDRwg0KjiGs-FU8VO