質問 # 23
Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?
- A. Relative effort estimate in Ideal Person Days that reflects the best estimate by the project team
- B. Detailed bottom-up effort estimate by the product owner that breaks up each story into short tasks
- C. Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity
- D. Project Manager's relative effort estimate that will be needed to implement and test the user story
正解:C
質問 # 24
When applying a cloud mindset in a greenfield Implementation, which of the following should you consider?Note: There are 2 correct answers to this question.
- A. Apply SAP quality principles
- B. Use quality gates
- C. Use supported extensibility technologies
- D. Ensure transparency on deviations
正解:B、C
質問 # 25
When working with an Agile approach, what is the minimum planning requirement expected at the beginning of the Realize phase?
- A. Release plan and sprint ceremony guidelines should be finalized.
- B. Sprint planning and sprint durations should be defined for the first 2 to 3 sprints.
- C. User stories on product backlog should be in ready state for the first 2 to 3 sprints.
- D. Realize phase scope, planning, and budget should be completed and final.
正解:B
解説:
C is correct because in an Agile approach, the planning is done iteratively and incrementally, so the minimum requirement at the beginning of the Realize phase is to have sprint planning and sprint durations defined for the first 2 to 3 sprints. Verified :
質問 # 26
Which of the following is a key characteristic of the Agile project approach?
- A. Frequent and detailed project scheduling
- B. Iterative build with frequent inspections
- C. Frequent quality gates
- D. Formal and detailed documentation
正解:B
質問 # 27
Which of the following are Selective Data Transition scenarios? Note: There are 3 correct answers to this question
- A. Migration of transactional data
- B. Migration of open items
- C. Consolidation
- D. Migration of selected applications
- E. Migration of business units
正解:A、B、E
質問 # 28
What are the responsibilities of the product owner in release and sprint planning?
NOTE: There are 2 correct answers to this question.
- A. Prioritize backing user stories by business priority
- B. Estimate the backing user stories
- C. Analyse the functional and technical dependencies between user stories
- D. Define objectives for each release
正解:A、D
質問 # 29
Which of the following is the customer's responsibility in both on-premise and private cloud scenarios?
- A. Servers
- B. Operating system
- C. Middleware
- D. Database
正解:A
質問 # 30
What is the most granular level of the methodology you can view in the SAP Roadmap Viewer?
- A. Task
- B. Workstream
- C. Phase
- D. Deliverable
正解:A
解説:
C is correct because task is the most granular level of the methodology that you can view in the SAP Roadmap Viewer. A task is a specific activity that needs to be performed by a role within a deliverable. A task has a description, an effort estimation, and a list of accelerators that support its execution. Verified :
: [SAP Roadmap Viewer]
質問 # 31
Which end-to-end turn-key application lifecycle management (ALM) solution can support You in managing requirements and software development for large Agile project.
- A. Requirement management
- B. Solution manager test suite
- C. Focused build
- D. Change request management
正解:C
質問 # 32
What is the purpose of the solution validation activity in the explore phase? There are 3 correct answers to this question Response:
- A. Educate project participate
- B. Log additional scope items
- C. Verify technical installation
- D. Identify gaps
- E. Challenge changes to standard
正解:B、D、E
質問 # 33
According to the Definition of Done, which activity must be completed for each Sprint?
- A. The solution must be built and configured in the development system (DEV)
- B. Functionality must be released to the business
- C. Functionality must be tested in the production system (PROD)
- D. End-user training must be delivered.
正解:A
質問 # 34
Which of the following scenarios are enabled for the "selective data transition" Transition Path with the SAP landscape transformation tool?
There are 3 correct answers to this question
- A. Security migration
- B. Extraction of business units
- C. Consolidation through online data replication
- D. System upgrade
- E. System consolidation
正解:B、C、E
質問 # 35
Which of the following steps are part of the fit-to-standard process? Note: There are 2 correct answers to this question.
- A. Design to-be business process models
- B. Document integration requirements
- C. Enable customers on standard business processes
- D. Review Best Practices process flow
正解:C、D
解説:
B is correct because reviewing Best Practices process flow is one of the steps that are part of the fit-to-standard process. The Best Practices process flow is a diagram that shows the standard SAP functionality and configuration for a scope item. The project team reviews the Best Practices process flow with the customer to demonstrate how the solution supports their business processes, and to identify any gaps or extensions that need to be addressed.
D is correct because enabling customers on standard business processes is one of the steps that are part of the fit-to-standard process. The project team enables customers on standard business processes by providing them with access to a starter system, where they can explore and test the predefined configuration and sample data for each scope item. The project team also provides customers with training materials and guidance on how to use the solution. Verified :
質問 # 36
You are implementing SAP S/4HANA Cloud, public edition for your customer.How are your customer systems activated?
- A. Via the SAP Business Technology Platform
- B. Via the SAP Cloud ALM
- C. Via the Central Business Configuration System
- D. Via the SAP Contact Center
正解:C
解説:
C is correct because the Central Business Configuration System (CBC) is a tool that enables customers to activate their SAP S/4HANA Cloud, public edition systems by following guided steps and entering configuration data. Verified :
: Central Business Configuration Overview
質問 # 37
What does the Side-by-Side extensibility option mean?
- A. There are two SAP S/4HANA instances: one for standard code and another for custom developments.
- B. SAP S/4HANA extensions are context-aware and focused on tight integration.
- C. Reporting is transferred to an enterprise data warehoused based on SAP BW/4HANA
- D. Extensibility is based on the SAP Business Transformation Platform (BTP) and published APIs.
正解:D
解説:
C is correct because extensibility based on the SAP Business Technology Platform (BTP) and published APIs is what the Side-by-Side extensibility option means. Side-by-Side extensibility is a type of extensibility that allows customers to create custom applications or extensions that run on a separate platform, such as SAP BTP, and communicate with the SAP S/4HANA system via published APIs. Side-by-Side extensibility enables customers to enhance their SAP S/4HANA solution without modifying the core code or configuration, and to leverage the capabilities of SAP BTP, such as cloud services, development tools, or integration options. Verified :
質問 # 38
According to the Definition of Done, which activity must be completed for each Sprint?
- A. End-user training must be delivered
- B. The solution must be built and configured in the development system (DEV)
- C. Functionality must be released to the business
- D. Functionality must be tested in the production system (PROD)
正解:B
解説:
B is correct because according to the Definition of Done, the solution must be built and configured in the development system (DEV) for each Sprint. This means that all user stories in the Sprint backlog must be completed, tested, and accepted by the product owner in the DEV system before moving to the next Sprint. Verified :
質問 # 39
Which of the following are levels in the structure of an SAP Best practices solution package?
There are 2 correct answers to this question
- A. Scope items
- B. Business process scenarios
- C. Configuration guides
- D. Building blocks
正解:A、D
質問 # 40
In which phase will the customer develop a preliminary strategy for building a target Operations and Support organizational model?
- A. Prepare phase
- B. Run phase
- C. Discover phase
- D. Explore phase
正解:A
質問 # 41
What criterion does the product owner use to sequence the product backlog?
- A. Business priority
- B. Complexity
- C. Resource availability
- D. Relative effort
正解:A
解説:
A is correct because the product owner is responsible for prioritizing the product backlog based on the business value and urgency of each user story3. Verified :
3: SAP Activate Project Management Certification Guide, page 112
質問 # 42
Which collaboration features are available in the SAP Community? Note: There are 2 correct answers to this question.
- A. Comment on Key Deliverables
- B. Tweet questions
- C. Update Key Deliverable wikis
- D. Ask questions
正解:A、D
解説:
B is correct because asking questions is one of the collaboration features that are available in the SAP Community. The SAP Community allows users to post questions on various topics and get answers from other users, experts, or moderators.
C is correct because commenting on key deliverables is one of the collaboration features that are available in the SAP Community. The SAP Community allows users to comment on the key deliverables that are published by SAP or other users, such as blog posts, articles, videos, podcasts, or webinars. Verified :
: SAP Community Home
質問 # 43
Which of the following considerations apply when determining the project methodology? Note: There are 3 correct answers to this question.
- A. Project fit
- B. Solution fit
- C. Implementation fit
- D. Organizational fit
- E. Project Manager fit
正解:A、B、D
質問 # 44
Which of the following are Selective Data Transition scenarios? Note: There are 3 correct answers to this question
- A. Migration of transactional data
- B. Migration of selected applications
- C. Migration of open items
- D. Consolidation
- E. Migration of business units
正解:A、D、E
解説:
A is correct because migration of business units is one of the Selective Data Transition scenarios. It allows the customer to move specific business units or company codes from their source system to SAP S/4HANA, while keeping the rest of the system unchanged.
B is correct because consolidation is one of the Selective Data Transition scenarios. It allows the customer to merge multiple source systems into one SAP S/4HANA system, while harmonizing and simplifying the data and processes.
E is correct because migration of transactional data is one of the Selective Data Transition scenarios. It allows the customer to move selected transactional data (such as open items, balances, and documents) from their source system to SAP S/4HANA, while preserving the historical data in the source system.
SAP Activate Project Management Certification Guide, page 128
質問 # 45
Via which media does SAP provide ready-to-run systems for SAP S/4HANA deployment? There are 2 correct answers to this question
- A. SAP cloud appliance library
- B. SAP App centre
- C. SAP Solution Builder tool
- D. Blu -ray disks
正解:A、D
質問 # 46
Which of the following tools can support you in managing requirements and software development for implementation projects? Note: There are 2 correct answers to this question
- A. SAP Cloud ALM
- B. SAP Focused Run
- C. Focused Insights for SAP Solution Manager
- D. Focused Build for SAP Solution Manager
正解:A、D
解説:
B is correct because Focused Build for SAP Solution Manager is a tool that supports the management of requirements and software development for implementation projects. It provides features such as requirements-to-deploy process, collaboration platform, quality gate management, and test management.
D is correct because SAP Cloud ALM is a tool that supports the management of requirements and software development for implementation projects. It provides features such as project task management, solution documentation, change request management, and test management. Verified :
質問 # 47
Which artifacts are created within application design and configuration workstream in the explore Phase of the "New implementation of SAP S/4HANA" There are 3 correct answers to this question
- A. Roles and authorizations management concept
- B. Delta requirements list-register
- C. Organisation structure specification
- D. Detailed design-business process
- E. Project procedure-mock-up modeling
正解:A、B、D
質問 # 48
......