質問 # 16
Which is NOT a way that tools are typically used?

  • A. Integrated
  • B. Individual
  • C. Connected
  • D. Collaborative

正解:C

解説:
The P3O Foundation (2013) manual identifies integrated, collaborative, and individual as typical ways tools are used, but not "connected" as a distinct category. Section 6.2.1 states, "Tools are typically used in an integrated manner across functions, collaboratively by teams, or individually by single users, depending on organizational maturity." The term "connected" (B) is not defined as a usage mode; it may imply a technical link but lacks specific application in the P3O context. The 2013 edition focuses on these three usage patterns to align with P3M3 maturity levels, ensuring tools support PPM effectively. Options A, C, and D are explicitly recognized, making B the correct choice for an atypical use. This clarity aids in selecting appropriate tool strategies.
Reference: P3O Foundation (2013) manual, Section 6.2.1, AXELOS.


質問 # 17
Which is a benefit of the portfolio prioritization and optimization technique?

  • A. Supports senior management investment decisions by aligning programmes to strategy
  • B. Highlights programme issues requiring intervention
  • C. Documents repeatable processes enabling increased PPM maturity
  • D. Provides resource capacity to the portfolio when required

正解:A

解説:
The P3O Foundation (2013) manual identifies that the portfolio prioritization and optimization technique supports senior management investment decisions by aligning programmes with strategy. Section 6.3.1 states,
"This technique supports senior management by prioritizing and optimizing the portfolio to align programmes and projects with strategic objectives, aiding investment decisions." This differs from highlighting issues (A), documenting processes (B), or providing capacity (C), which are secondary outcomes. The 2013 edition emphasizes its strategic decision-making role, ensuring resources focus on high-value initiatives. This enhances portfolio effectiveness.
Reference: P3O Foundation (2013) manual, Section 6.3.1, AXELOS.


質問 # 18
Why is the same function carried out with a different focus by different offices within a P3O model?

  • A. To understand the capability to be delivered by the being supported
  • B. To consider risk from a strategic viewpoint
  • C. To provide appropriate decision support to the customers of each office
  • D. To provide ongoing prioritization of change initiatives

正解:C

解説:
The P3O Foundation (2013) manual explains that the same function is performed with different focuses by various P3O offices to provide tailored decision support. Section 5.3.1 states, "Different offices within a P3O model perform the same functions with varying focuses to deliver appropriate decision support tailored to the needs of their specific customers, such as portfolio or programme teams." This contrasts with prioritization (A), capability understanding (B), or strategic risk (D), which are specific outcomes rather than the reason for focus variation. The 2013 edition highlights this customization to meet diverse organizational needs, enhancing efficiency and relevance. This approach supports effective governance across levels.
Reference: P3O Foundation (2013) manual, Section 5.3.1, AXELOS.


質問 # 19
Which technique ensures resources with the right expertise are allocated to PPM roles?

  • A. P3O information portal
  • B. Facilitation - workshop techniques
  • C. Skills development and maintenance
  • D. Management dashboards

正解:C

解説:
The P3O Foundation (2013) manual identifies skills development and maintenance as the technique to ensure resources with the right expertise are allocated to PPM roles. Section 6.3.2 states, "Skills development and maintenance techniques assess and enhance the expertise of resources, ensuring they are appropriately allocated to PPM roles within the P3O." This differs from information portals (A), which share knowledge, dashboards (C), which report data, or workshops (D), which facilitate collaboration. The 2013 edition emphasizes this training to match skills with roles, enhancing P3O effectiveness. This supports efficient resource utilization.
Reference: P3O Foundation (2013) manual, Section 6.3.2, AXELOS.


質問 # 20
Which information should a Business Case for a P3O provide?

  • A. Reasons why any form of P3O is needed
  • B. Processes to be implemented by the P3O
  • C. Roles of the staff working in the P3O
  • D. Appointed Head of P3O

正解:A

解説:
The P3O Foundation (2013) manual specifies that a Business Case for a P3O should provide reasons for its need. Section 4.2.2 states, "The Business Case must articulate the reasons why any form of P3O is required, including the benefits and justification for investment, to gain senior management approval." This contrasts with staff roles (B), processes (C), or the Head's appointment (D), which are implementation details. The
2013 edition emphasizes this justification as the core purpose, ensuring strategic alignment and resource commitment. This approach secures buy-in and supports the P3O's establishment.
Reference: P3O Foundation (2013) manual, Section 4.2.2, AXELOS.


質問 # 21
Which is an important factor when working in a distributed model?

  • A. Staff physically co-located to ensure team cohesion
  • B. Effective use of information portals
  • C. Functional roles work in the same location
  • D. Use of sophisticated tools and techniques

正解:B

解説:
The P3O Foundation (2013) manual identifies effective use of information portals as a key factor in a distributed model. Section 5.3.1 states, "In a distributed P3O model, effective use of information portals is crucial to facilitate communication and coordination among geographically dispersed teams." This contrasts with co-location (B), same-location roles (C), or sophisticated tools (D), which are impractical or less critical in distributed settings. The 2013 edition emphasizes technology's role in overcoming distance, ensuring consistent information sharing. This supports efficient collaboration and governance in decentralized structures.
Reference: P3O Foundation (2013) manual, Section 5.3.1, AXELOS.


質問 # 22
Which P3O capability is MOST likely to result in being able to stop inappropriate programmes?

  • A. Reduction in overheads dealing with conflicting resources
  • B. Reduction in resource
  • C. Ongoing alignment of programmes with strategic objectives and targets
  • D. Increased ability to bundle related requests for change for programmes

正解:C

解説:
The P3O Foundation (2013) manual indicates that ongoing alignment with strategic objectives is the capability most likely to stop inappropriate programmes. Section 2.2.3 states, "Ongoing alignment of programmes with strategic objectives and targets enables the P3O to identify and terminate initiatives that no longer support organizational goals." This contrasts with resource reduction (A), overhead reduction (C), or bundling requests (D), which address efficiency or coordination rather than strategic fit. The 2013 edition emphasizes this alignment as a core P3O function, ensuring resources focus on value-adding initiatives. This capability enhances governance effectiveness.
Reference: P3O Foundation (2013) manual, Section 2.2.3, AXELOS.


質問 # 23
Which describes the people or skills required for a Portfolio Office?

  • A. Skills of Portfolio Office staff are the same as those for a role in a COE
  • B. Should be resourced with people wanting to move into project management
  • C. Should be resourced with a large number of administrative staff
  • D. Needs enough people who are able to interpret and challenge data

正解:D

解説:
The P3O Foundation (2013) manual indicates that a Portfolio Office requires staff skilled in interpreting and challenging data. Section 3.5.3 states, "The Portfolio Office should be staffed with individuals capable of interpreting complex data, challenging assumptions, and providing analytical support to inform portfolio decisions." This contrasts with aspirations for project management (A), identical COE skills (B), or heavy administrative staffing (D), which do not align with the analytical focus. The 2013 edition emphasizes the need for analytical expertise to support portfolio prioritization and risk management, ensuring strategic decision-making. This skill set is critical for the Portfolio Office's role in providing high-level support and insights.
Reference: P3O Foundation (2013) manual, Section 3.5.3, AXELOS.


質問 # 24
Which is a functional area within a P3O model?

  • A. Virtual Office
  • B. Hub Portfolio Office connected by spokes
  • C. COE functions or services
  • D. Flexible resource pool

正解:C

解説:
COE (Centre of Excellence) functions or services are a functional area within a P3O model, per the P3O Foundation (2013) manual. Section 5.3.4 states, "The Centre of Excellence provides a functional area within the P3O, offering standards, guidance, and best practices to support PPM maturity." This contrasts with Hub Portfolio Offices (A), which are structural models, Virtual Offices (C), which are temporary setups, and Flexible Resource Pools (D), which are resource mechanisms. The 2013 edition highlights the COE's role in standardizing processes, making it a core P3O component. This ensures consistent support across the organization.
Reference: P3O Foundation (2013) manual, Section 5.3.4, AXELOS.


質問 # 25
Which of the following are recommended for the implementation of a P3O model?
1. Follow a recognized programme or project methodology
2. Define a budget and associated timescales to deliver
3. Appoint a P3O Sponsor
4. Use a programme approach to implement a single office P3O staffed by one individual

  • A. 1,2,4
  • B. 1,3,4
  • C. 1,2,3
  • D. 2,3,4

正解:C

解説:
The P3O Foundation (2013) manual recommends following a recognized methodology, defining a budget and timescales, and appointing a P3O Sponsor for implementation. Section 4.2.1 states, "Implementation should follow a recognized programme or project methodology, include a defined budget and timescales, and involve appointing a P3O Sponsor to provide leadership." However, using a programme approach for a single- office P3O staffed by one individual (4) is not recommended due to scalability and governance issues. The
2013 edition emphasizes a structured approach to ensure success, with the Sponsor driving strategic alignment and methodology providing a framework. Options B, C, and D include the impractical fourth element, making A the correct choice for a robust implementation process.
Reference: P3O Foundation (2013) manual, Section 4.2.1, AXELOS.


質問 # 26
Which of the following statements about how a P3O should integrate with the wider organization are true?
1. Operates independently of other functions within the organization
2. Typically relies on dedicated full-time resources to provide financial functions needed

  • A. Only 1 is true
  • B. Neither 1 or 2 is true
  • C. Only 2 is true
  • D. Both 1 and 2 are true

正解:B

解説:
The P3O Foundation (2013) manual indicates that a P3O should not operate independently nor rely solely on dedicated full-time resources for financial functions, making both statements false. Section 5.1.2 states,
"The P3O model should integrate seamlessly with existing organizational functions, leveraging shared resources and aligning with corporate governance." Independence (1) is impractical as P3O relies on collaboration, while financial functions (2) are typically supported by existing organizational structures rather than dedicated P3O resources (Section 7.2). The 2013 edition emphasizes integration and resource sharing to enhance efficiency, contradicting both options. Thus, D is correct, ensuring the P3O complements rather than duplicates organizational capabilities, supporting a cohesive change management framework.
Reference: P3O Foundation (2013) manual, Sections 5.1.2 and 7.2, AXELOS.


質問 # 27
Which is a section of the Blueprint?

  • A. Vision Statement
  • B. Business process swimlanes
  • C. Processes (including operational costs and performance levels)
  • D. Information portal

正解:A

解説:
The P3O Foundation (2013) manual identifies the Vision Statement as a section of the Blueprint. Section
4.3.3 states, "The Blueprint includes a Vision Statement that outlines the desired future state of the P3O model, guiding its development and implementation." This differs from business process swimlanes (A), which are tools, information portals (B), which are delivery mechanisms, and processes (D), which are detailed operational elements. The 2013 edition emphasizes the Vision Statement's role in setting strategic direction within the Blueprint, a key implementation document. This ensures alignment with organizational goals throughout the P3O lifecycle.
Reference: P3O Foundation (2013) manual, Section 4.3.3, AXELOS.


質問 # 28
Which is NOT a use of integrated tools?

  • A. Uses a single installation of the tool across the organization
  • B. Allows multiple people to multiple sets of information
  • C. Supports a single business change initiative with multiple users
  • D. Links information across business change initiatives in a hierarchical manner

正解:B

解説:
Integrated tools in the P3O Foundation (2013) manual are designed to streamline information management across change initiatives, but they do not inherently allow multiple people to access multiple sets of information independently. Section 6.2.3 notes, "Integrated tools link information hierarchically across portfolios, programmes, and projects, support multiple users for a single initiative, and utilize a single installation for organizational consistency." Option B, however, suggests fragmented access, which contradicts the integrated nature of these tools, aiming for a unified data view. Options A, C, and D align with the manual's description of facilitating collaboration and standardization. The 2013 guidance stresses that integrated tools enhance efficiency by centralizing data, making B an incorrect use case. This ensures clarity and consistency in decision-making processes.
Reference: P3O Foundation (2013) manual, Section 6.2.3, AXELOS.


質問 # 29
What types of office does a P3O typically consist of?

  • A. Permanent and transitioning
  • B. Virtual and decentralized
  • C. Co-located and centralized
  • D. Permanent and temporary

正解:D

解説:
The P3O Foundation (2013) manual states that a P3O typically consists of permanent and temporary offices.
Section 5.1.1 notes, "A P3O model typically comprises permanent offices, such as the Organization Portfolio Office, and temporary offices, such as Programme or Project Offices, to support the change lifecycle." This differs from transitioning (A), co-located/centralized (B), or virtual/decentralized (C), which describe specific configurations or states. The 2013 edition highlights this dual structure to address both ongoing and project- specific needs, ensuring flexible support across the organization.
Reference: P3O Foundation (2013) manual, Section 5.1.1, AXELOS.


質問 # 30
How should the Head of P3O overcome the barrier of 'lack of focus on the full P3O model'?

  • A. Gain acceptance of component offices delivered in tranches
  • B. Address culture changes through targeted communications
  • C. Develop minimalist processes with tailoring guidelines
  • D. Build a vision and Business Case

正解:D

解説:
The P3O Foundation (2013) manual suggests the Head of P3O should overcome the 'lack of focus' barrier by building a vision and Business Case. Section 4.2.3 states, "To address the lack of focus on the full P3O model, the Head of P3O should develop a clear vision and robust Business Case to secure organizational commitment and alignment." This differs from tranche acceptance (A), process development (C), or cultural communication (D), which address different challenges. The 2013 edition emphasizes strategic clarity to unify efforts, ensuring the P3O's comprehensive adoption. This approach drives successful implementation.
Reference: P3O Foundation (2013) manual, Section 4.2.3, AXELOS.


質問 # 31
Which describes P3O assurance services?

  • A. Carried out by the delivery function
  • B. Integrated into the programme being assured
  • C. Independent of the programme being assured
  • D. Supports Programme Managers in delivery

正解:C

解説:
The P3O Foundation (2013) manual describes P3O assurance services as independent of the programme being assured. Section 7.3.2 states, "P3O assurance services are provided independently of the programme or project being assessed to ensure objective evaluation and compliance with governance standards." This contrasts with integration (B), delivery function involvement (C), or support for Programme Managers (D), which compromise objectivity. The 2013 edition emphasizes this independence to maintain credibility and effectiveness in oversight, supporting strategic alignment and risk management. This ensures unbiased assurance across change initiatives, enhancing organizational trust in P3O processes.
Reference: P3O Foundation (2013) manual, Section 7.3.2, AXELOS.


質問 # 32
Which receives the benefit of the governance provided by a P3O?

  • A. Business as usual
  • B. Change initiatives
  • C. Commercial
  • D. Finance

正解:B

解説:
The P3O Foundation (2013) manual states that change initiatives receive the benefit of P3O governance.
Section 2.1.2 notes, "The P3O model provides governance to ensure the success of change initiatives, including programmes and projects, by aligning them with strategic objectives." This differs from finance (A), business as usual (C), or commercial (D), which are supported indirectly. The 2013 edition focuses on P3O's role in enhancing change delivery through oversight and decision support. This ensures change initiatives are effectively managed and delivered, maximizing organizational value.
Reference: P3O Foundation (2013) manual, Section 2.1.2, AXELOS.


質問 # 33
Which is NOT a specific area where KPIs should be set as a minimum to measure a P3O model's success?

  • A. Reduced cost of skilled resources
  • B. Improved portfolio balance in terms of overall risk
  • C. Enhanced contribution to strategic objectives
  • D. Overall programme success rates in relation to benefits realization

正解:A

解説:
The P3O Foundation (2013) manual specifies that KPIs for measuring P3O success should focus on strategic and performance outcomes, not cost reduction of skilled resources. Section 7.3.1 states, "Key Performance Indicators for a P3O should include enhanced contribution to strategic objectives, improved portfolio risk balance, and programme success in benefits realization." Reduced cost of skilled resources (A) is not listed as a minimum KPI, as it relates to operational efficiency rather than the P3O's core success metrics. The 2013 edition prioritizes outcome-based measures to align with strategic goals, ensuring the P3O' s value is assessed through effectiveness (B, C, D) rather than cost savings. This focus supports robust governance and decision-making.
Reference: P3O Foundation (2013) manual, Section 7.3.1, AXELOS.


質問 # 34
Which is a purpose of the Consultancy and Performance Management role?

  • A. Creates, maintains and distributes good practice
  • B. Identifies, monitors and resolves issues
  • C. Provides benefits realization support
  • D. Assists with budget control

正解:A

解説:
The Consultancy and Performance Management role's purpose includes creating, maintaining, and distributing good practice, as per the P3O Foundation (2013) manual. Section 3.5.5 states, "The Consultancy and Performance Management function is responsible for creating, maintaining, and distributing good practice guidance to enhance PPM maturity across the organization." This differs from budget control (A), benefits realization (C), or issue management (D), which are handled by other roles like the Portfolio Analyst or Programme Office. The 2013 edition underscores this role's focus on standardizing processes, supporting P3O's goal of improving performance through shared knowledge. This ensures consistent application of best practices.
Reference: P3O Foundation (2013) manual, Section 3.5.5, AXELOS.


質問 # 35
What can be used to assess and document the current state of PPM functions?

  • A. P3M3 assessments
  • B. Capacity planning for resource management
  • C. Complexity modelling
  • D. P3O vision

正解:A

解説:
The P3O Foundation (2013) manual identifies P3M3 assessments as the tool to assess and document the current state of PPM functions. Section 6.1.2 states, "P3M3 assessments are used to evaluate and document the current maturity and capability of PPM functions within an organization, providing a baseline for improvement." This differs from capacity planning (A), complexity modelling (B), or P3O vision (C), which serve other purposes. The 2013 edition highlights P3M3's role in benchmarking, supporting P3O's implementation by identifying gaps. This ensures a data-driven approach to enhancing PPM maturity.
Reference: P3O Foundation (2013) manual, Section 6.1.2, AXELOS.


質問 # 36
What is the MOST appropriate use of project planning software for an organization at P3M3 maturity level 1?

  • A. Individual
  • B. Integrated
  • C. Networking
  • D. Collaborative

正解:A

解説:
For an organization at P3M3 maturity level 1, the P3O Foundation (2013) manual suggests the most appropriate use of project planning software is individual, reflecting its basic process capability. Section 6.2.1 notes, "At P3M3 maturity level 1, organizations typically use project planning software on an individual basis due to limited process integration and collaboration maturity." Collaborative (A), integrated (C), and networking (D) uses require higher maturity levels (e.g., 2 or 3), where standardized processes and data sharing are established. The 2013 edition aligns this with the initial stage's focus on basic project management, where tools are used ad hoc by individuals rather than across teams. This approach supports gradual improvement toward more sophisticated usage.
Reference: P3O Foundation (2013) manual, Section 6.2.1, AXELOS.


質問 # 37
Which is delivered by the Blueprint's information flows?

  • A. Management of risk
  • B. Realization of benefits
  • C. P3O implementation plan
  • D. Principle of management by exception

正解:D

解説:
The P3O Foundation (2013) manual indicates that the Blueprint's information flows deliver the principle of management by exception. Section 4.3.3 states, "The Blueprint's information flows support the principle of management by exception by providing senior management with critical data to focus on deviations rather than routine operations." This differs from the implementation plan (A), risk management (B), or benefits realization (D), which are separate processes. The 2013 edition highlights this principle as a governance mechanism, enabling efficient oversight by escalating only significant issues. This enhances P3O's strategic focus during implementation.
Reference: P3O Foundation (2013) manual, Section 4.3.3, AXELOS.


質問 # 38
Which P3O model features a single permanent office providing strategic planning and portfolio support?

  • A. Virtual Office
  • B. Organization Portfolio Office
  • C. Flexible resource pool
  • D. P3O model with Hub Portfolio Offices

正解:B

解説:
The Organization Portfolio Office (OPO) is a single permanent office designed to provide strategic planning and portfolio support, as per the P3O Foundation (2013) manual. Section 5.3.2 states, "The Organization Portfolio Office is a centralized, permanent entity that delivers strategic planning, portfolio prioritization, and oversight across the organization." This contrasts with Hub Portfolio Offices (A), which are decentralized with local support, Virtual Offices (C), which are temporary and flexible, and Flexible Resource Pools (D), which focus on resource allocation rather than strategic functions. The 2013 edition highlights the OPO's role in aligning the entire change portfolio with organizational strategy, making it the correct model for this purpose. This centralized approach ensures consistent governance and decision-making.
Reference: P3O Foundation (2013) manual, Section 5.3.2, AXELOS.