質問 # 26
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.
There are 30 vendor stalls selling products related to the event.
The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
The project manager used the Agilometer to assess the prevailing agile environment and, consequently, took action to improve the low score achieved on the 'flexibility on what is delivered' slider.
When should the project manager undertake a further assessment in order to determine if further action is required to increase the slider score?
- A. Project retrospective.
- B. Release retrospective.
- C. Sprint retrospective.
- D. Sprint review.
正解:C
解説:
The sprint retrospective is an opportunity for the team to reflect on the sprint, discuss what went well, what could be improved, and how to enhance processes moving forward. Assessing the Agilometer score at this point allows the project manager and the team to evaluate the effectiveness of actions taken and make adjustments as needed to improve flexibility in future sprints.
質問 # 27
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through feespaid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.
There are 30 vendor stalls selling products related to the event.
The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
All public events supported by the LGA must be fully accessible to all visitors.
How should this requirement be recorded?
- A. Under the composition heading of project product description as a Must Have requirement.
- B. In the project product description for the tournament as a Customer Quality Expectation.
- C. In a user story: 'As the LGA, I want to allow access to all visitors so that everyone can attend the tournament'.
- D. On a burn chart as a feature to be delivered by the team within the current timebox.
正解:B
解説:
Recording this requirement as a Customer Quality Expectation highlights its importance to the overall success of the event. It ensures that accessibility is recognized as a critical aspect that the project must meet to satisfy stakeholders and attendees, aligning with the principles of inclusivity in public events.
質問 # 28
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Staff Training - Additional information
The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:
- A. staff members are able to give advice on health and fitness.
This is covered by four work packages:
1. Training syllabus:
* High-level design of the manual.
* Content of each module.
2. Course content for safety and professionalism:
* Detailed design of two modules:
* Health and Safety including basic first aid.
* Customer relations to look after people attending the event.
* Piloting the modules with a group of volunteers.
3. Course content tor giving advice on health and fitness:
* Detailed design of two modules:
* Exercise fundamentals including how to warm up and cool down.
* Healthy eating including what types of food are good for you.
* Piloting the modules with a group of volunteers.
4. Training delivery:
* Production of the training manual;
* Delivery of the training to the rest of the volunteers.
The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.
Using the Project Scenario and Staff Training Additional information, answer the following question:
The Staff Training Team had been working to the following assumption:
'All volunteers will be trained in all training materials.'
Quite late in the project, it has been identified that this assumption is incorrect. As a result, the team manager produced a chart of who needs to be trained in what modules. This was agreed with a customer representative and the team manager made the necessary amendments to the requirements in the backlog within the current timebox.
What BEST explains why the team manager's approach complies with the 'embrace change' target? - B. It applies the target poorly because the training acceptance criteria should be specified in the project product description.
- C. It applies the target well because visualization is the most effective way to communicate change.
- D. It applies the target poorly because the customer subject matter expert should represent the impacted stakeholders.
- E. It applies the target well because the training will be delivered in the most accurate way.
- F. the event is carried out safely and professionally;
正解:F
解説:
By recognizing the incorrect assumption and producing a chart to clarify who needs to be trained in which modules, the team manager is adapting to the new information and ensuring that the training is aligned with the actual needs. This responsiveness to change helps deliver training more effectively, reflecting the principle of embracing change to improve outcomes.
質問 # 29
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
Website showing the event details, competition rules, etc.
2. Team Registration functionality:
team name, player's names and ages;
contact information;
payment;
lunch pack requirements (includes any special dietary needs);
car parking requirements.
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
An online knowledge base about healthy lifestyles that includes a discussion forum.
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The Website team manager has identified the need for a supplier representative to work on the social media website.
Who can fulfil this need according to the 'defined roles and responsibilities' principle?
- A. The project manager who has a good overview of the entire project and the social media requirements.
- B. The senior user who is able to represent those who understand how social media channels are to be delivered.
- C. The team manager who is leading the delivery of the social media website.
- D. The senior supplier who has technical knowledge of the website and how it should be delivered.
正解:D
解説:
The senior supplier's technical knowledge and understanding of the website's delivery make them the most suitable candidate to represent the supplier's interests and ensure that the social media website meets the project requirements effectively.
質問 # 30
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out';
the training of LGA staff as volunteers to run and support the event;
back-office processes to handle the applications;
fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
advertisements:
a radio interview;
production of a hand-out/flyer;
banners and signs to put up around the town and at the event;
the provision of a website and social media content;
promotional posters to be displayed by local businesses.
Using the Project Scenario and Marketing Additional information, answer the following question:
The Marketing Team have noted in their daily stand-up that they cannot work out the versions and review status of the information and photos which will appear on the website pages.
Which core practice might be the MOST useful to immediately help with the 'managing product delivery' process?
- A. Carry out a safe-to-fail experiment to identify a better way of working.
- B. Identify the effect of delaying the delivery of a web page in a daily stand-up.
- C. Visualize the status of the work using a 'ticket' board with 'swim lanes'.
- D. Refer to a cumulative flow diagram to identify the status of the remaining work.
正解:C
解説:
Using a 'ticket' board with 'swim lanes' allows the Marketing Team to visualize the different versions and review statuses of the information and photos for the website. This practice helps clarify the current state of work, promotes transparency, and facilitates better communication within the team, ultimately supporting effective management of product delivery.
質問 # 31
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications;
an event village to support the 'family day out';
the training of LGA staff as volunteers to run and support the event;
back-office processes to handle the applications;
fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Staff Training - Additional information
The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:
- A. the event is carried out safely and professionally;
- B. The health and safety training must be delivered before the planned football tournament takes place.
- C. staff members are able to give advice on health and fitness.
This is covered by four work packages:
1. Training syllabus:
* High-level design of the manual.
* Content of each module.
2. Course content for safety and professionalism:
* Detailed design of two modules:
* Health and Safety including basic first aid.
* Customer relations to look after people attending the event.
* Piloting the modules with a group of volunteers.
3. Course content tor giving advice on health and fitness:
* Detailed design of two modules:
* Exercise fundamentals including how to warm up and cool down.
* Healthy eating including what types of food are good for you.
* Piloting the modules with a group of volunteers.
4. Training delivery:
* Production of the training manual;
* Delivery of the training to the rest of the volunteers.
The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.
Using the Project Scenario and Staff Training Additional information, answer the following question:
The Staff Training Team have developed the following user story:
'As the LGA, I want all volunteers to have received mandatory health and safety training so that we can ensure that the event takes place in a safe environment for the public.' Which reason explains why the team should deliver the user story in accordance with the 'be on time and hit deadlines' target? - D. The volunteers will take time to understand the training before they can apply it safely.
- E. The health and safety training should be left out if it cannot be delivered before the football tournament.
- F. The training must be delivered so that the volunteers understand the health and safety requirements.
正解:C
解説:
Timely delivery of the health and safety training is crucial to ensure that all volunteers are adequately prepared before the event. Meeting this deadline is essential for ensuring a safe environment for the public during the football tournament, making it a priority to adhere to the schedule.
質問 # 32
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre oftown has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.
There are 30 vendor stalls selling products related to the event.
The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
There is limited space in the Event Village to accommodate all of the equipment, e.g. the trampolines, 'kidz- zone', food tent, car park and changing rooms.
It is difficult to assess whether there is sufficient space from the design drawings. One of the team has suggested physically drawing out the actual space occupied by each facility at the site.
Which statement BEST describes whether this approach is a good application of the frequent releases focus area?
- A. It is a good approach because a design should be an interim stage of the Event Village work package.
- B. It is a poor approach because visiting the site of the Event Village is NOT classed as a sub-product.
- C. It is a good approach because a physical representation will deliver something of use to the project.
- D. It is a poor approach because releases need to be put into operational use to receive any feedback.
正解:C
解説:
Creating a physical representation of the space occupied by each facility allows the team to visualize and assess the spatial arrangement more effectively. This tangible output is beneficial for the project, providing a clear understanding of how the various components fit together within the limited space, which aligns with the principle of delivering usable outcomes frequently.
質問 # 33
Which is a reason for 'blending and weaving' PRINCE2 with agile at all levels within a project?
- A. Projects should be established with the intention of NOT delivering everything.
- B. To adjust a 'command and control' culture for product delivery.
- C. PRINCE2 Agile is NOT a substitute for PRINCE2.
- D. To allow teams to self-organize whilst staying in control.
正解:D
解説:
This approach enables teams to adopt Agile practices while maintaining the governance and structure provided by PRINCE2, promoting both flexibility and control in project delivery.
質問 # 34
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out';
the training of LGA staff as volunteers to run and support the event;
back-office processes to handle the applications;
fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.
There are 30 vendor stalls selling products related to the event.
The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
As a: Footballer participating in the event
I want to: Have a private cubicle to change in before my football match, without having to wait for more than
5 minutes
So that: I can be ready for the game
Which statement explains whether the 'function' in this user story is appropriate?
- A. The function is poor because it contains a performance element that is better suited to a technical story.
- B. The function is poor because it does NOT contain any prioritization of the requirement.
- C. The function is good because it contains a time element that can be measured.
- D. The function is good because it contains a solution for the requirement.
正解:A
解説:
While the user story describes the desired functionality of having a private cubicle, the inclusion of a specific performance element (waiting time of no more than 5 minutes) is more aligned with non-functional requirements, which are typically documented as technical stories. This could lead to confusion about the primary function being requested, as it mixes functional and performance criteria.
質問 # 35
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
Website showing the event details, competition rules, etc.
2. Team Registration functionality:
team name, player's names and ages;
contact information;
payment;
lunch pack requirements (includes any special dietary needs);
car parking requirements.
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
An online knowledge base about healthy lifestyles that includes a discussion forum.
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The project has been set up with multiple teams - one for each area of delivery. Each team has its own team manager.
The LGA employee who is an expert in health has been appointed to act as customer representative to all four of the delivery teams.
What BEST explains how this approach tailors the organization theme?
- A. It tailors the theme well because the customer representative should work full time on the project.
- B. It tailors the theme poorly because a customer subject matter expert should provide expert knowledge on health.
- C. It tailors the theme poorly because each delivery team should have dedicated resources and a stable team.
- D. It tailors the theme well because the customer representative provides specialist information to the teams.
正解:D
解説:
Appointing a customer representative with expertise in health ensures that all delivery teams have access to specialized knowledge and insights that can inform their work. This role supports the teams effectively by providing relevant information and ensuring that the project aligns with customer needs and expectations, enhancing collaboration across multiple teams.
質問 # 36
Which describes a characteristic of business as usual (BAU) work?
- A. A delivery which is part of a larger programme of work.
- B. Lists of routine modifications, received regularly during the life of existing products. )
- C. A new team selected to address a specific problem or opportunity.
- D. A collection of difficult tasks that are managed together.
正解:B
解説:
Routine Operations: BAU encompasses the standard activities and processes that are necessary for the daily functioning of an organization. This includes tasks that are performed regularly and consistently to maintain services, products, and overall operations.
Regular Modifications: BAU work often involves minor updates or modifications to existing products or services. These modifications are typically routine in nature, aimed at improving efficiency, fixing issues, or adapting to changes in the environment without major disruption.
Maintenance and Support: BAU includes maintenance tasks such as monitoring systems, providing customer support, and ensuring compliance with regulations. These tasks ensure that existing products and services continue to function effectively.
Predictable and Structured: Unlike projects that may have a defined start and end date, BAU work is ongoing and tends to follow established procedures. This predictability helps organizations manage their resources effectively.
Focus on Stability: The goal of BAU work is to maintain stability within the organization. While it may involve some level of change (like routine modifications), the primary focus is on ensuring that existing operations run smoothly.
質問 # 37
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
Website showing the event details, competition rules, etc.
2. Team Registration functionality:
team name, player's names and ages;
contact information;
payment;
lunch pack requirements (includes any special dietary needs);
car parking requirements.
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
An online knowledge base about healthy lifestyles that includes a discussion forum.
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
The project manager has agreed with the Website team manager delivering the Social Media work package that the team should try using the Kanban method along with their existing Scrum approach to improve delivery.
The team is now going to use a Kanban board as part of their information radiator.
Which explains the additional benefit of combining these two agile approaches during the 'managing product delivery' process?
- A. Using Kanban limits the amount of scope change on the project and therefore increases velocity.
- B. By using Kanban, collaborative working is enabled between members of the Website Team delivering the social media.
- C. Using Kanban limits the amount of work being carried out by the team, with the aim of improving delivery during the sprint.
- D. A Kanban board makes the status of the Social Media work package visible to the delivery team.
正解:D
解説:
A Kanban board provides a visual representation of the workflow, making it easy for the team to see the status of tasks within the Social Media work package. This increased visibility helps the team manage their work more effectively, identify bottlenecks, and facilitate communication, enhancing overall productivity and coordination during the delivery process.
質問 # 38
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
advertisements:
a radio interview;
production of a hand-out/flyer;
banners and signs to put up around the town and at the event;
the provision of a website and social media content;
promotional posters to be displayed by local businesses.
Using the Project Scenario and Marketing Additional information, answer the following question:
The project manager has agreed that the 'Mission Control' room will have an issue register on the wall for project issues and all teams will display their own issue register on their own team wall as well.
Which BEST explains if this approach is suitable?
- A. A spreadsheet that all teams have access to would be a more agile way of working.
- B. Each team will be able to physically log and update issues during their daily stand-ups.
- C. The issue registers may be difficult to keep synchronized across the teams so this should be avoided.
- D. A more formal approach would encourage issues to be raised that might otherwise be missed.
正解:B
解説:
Having issue registers displayed on the team walls allows for immediate visibility and encourages team members to log and discuss issues as they arise during daily stand-ups. This promotes a culture of transparency and collaboration, making it easier for teams to manage and address issues in a timely manner.
質問 # 39
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
advertisements:
a radio interview;
production of a hand-out/flyer;
banners and signs to put up around the town and at the event;
the provision of a website and social media content;
promotional posters to be displayed by local businesses.
Using the Project Scenario and Marketing Additional information, answer the following question:
Many Marketing Team members were expressing frustration that some members of the team had worked only on specific products and had not helped in the delivery of others. Therefore, the Marketing Team produced a Glad! Sad! Mad! board during a recent retrospective.
Which statement explains why this approach to identifying issues is appropriate for the 'controlling a stage' process?
- A. Glad! Sad! Mad! is a feedback technique used in a retrospective to monitor the progress of a team.
- B. The retrospective empowers the delivery teams to work with a visual approach durinq a timebox.
- C. Glad! Sad! Mad! is a feedback technique that focuses on feelings and helps to identify improvements.
- D. A retrospective should identity all areas of improvement that should be actioned by a team.
正解:C
解説:
The Glad! Sad! Mad! board allows team members to express their feelings about their experiences during the stage, helping to surface issues and areas for improvement. This emotional feedback can be crucial in identifying specific challenges within the team dynamics and product delivery, facilitating better control and adjustments for future stages.
質問 # 40
Which BEST describes an agile method or approach that can be integrated with PRINCE2 Agile?
- A. Providing guidance on tailoring any applicable principles, themes and processes.
- B. Favoring processes and tools over individuals and interactions.
- C. Reducing quality testing in order to deliver within agreed deadlines.
- D. Encouraging system improvement through visualization and controlling work in progress.
正解:D
解説:
This approach aligns with Agile principles, emphasizing continuous improvement and effective workflow management, which can complement the structured framework of PRINCE2 Agile.
質問 # 41
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
advertisements:
a radio interview;
production of a hand-out/flyer;
banners and signs to put up around the town and at the event;
the provision of a website and social media content;
promotional posters to be displayed by local businesses.
Using the Project Scenario and Marketing Additional information, answer the following question:
Nine timeboxes are scheduled for the marketing work.
Which baseline product is MOST relevant for defining which marketing product will be released in each timebox?
- A. Project brief.
- B. Project product description.
- C. Business case.
- D. Work package.
正解:B
解説:
The project product description outlines the key deliverables of the project and their acceptance criteria. This product serves as a reference for the marketing team to determine which marketing products should be delivered in each timebox, ensuring that all releases align with the overall project goals.
質問 # 42
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.
Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
advertisements:
a radio interview;
production of a hand-out/flyer;
banners and signs to put up around the town and at the event;
the provision of a website and social media content;
promotional posters to be displayed by local businesses.
Using the Project Scenario and Marketing Additional Information, answer the following question:
For which marketing product would a quality method of automated test-driven development be MOST suited?
- A. The radio interview.
- B. The newspaper advertisements.
- C. The banners for the Event Village.
- D. The text and links for the website.
正解:D
解説:
Automated test-driven development (TDD) is particularly well-suited for digital products like website content, where code and links can be continuously tested for functionality and correctness. This approach allows for rapid iterations and ensures that updates do not introduce errors, making it ideal for maintaining the quality of web content.
質問 # 43
......
時間限定!今すぐ無料アクセスPRINCE2-Agile-Practitioner練習試験用問題:https://drive.google.com/open?id=1E5zEAqy4047vC2OPjite6i3qlh1dCdnA
オンライン試験練習テストと詳細な解説付き!:https://www.goshiken.com/PRINCE2/PRINCE2-Agile-Practitioner-mondaishu.html