質問 225
A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls, and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project, which could impact other components if delays occur. The program manager's attempts to reach the stakeholder via email also fail.
What should the program manager do next?
- A. Escalate the issue to the program governance board, as delays will impact the program
- B. Update the program risk register to reflect a realized risk and execute the documented risk response
- C. Escalate the issue to the stakeholder's supervisor
- D. Attempt to call the key stakeholder; if unsuccessful, visit their office to identify potential risks
正解: D
解説:
Explanation
Section: Volume D
質問 226
Your program exists within a matrix structure. Your program has eight projects that all share resources from around the organization. You are concerned that some of the project team members may be over allocated and want to create a chart that will reflect the utilization of resources. What kind of chart can show the utilization of project team members used in your program?
- A. Resource network diagram
- B. Resource histogram
- C. Resource breakdown structure
- D. Pareto chart
正解: B
質問 227
Mike is the program manager of the NHQ Program. Mike and a vendor are in disagreement over the deliverable the vendor has created for Mike's program. Mike does not believe the vendor has correctly created the deliverable, while the vendor is adamant that his company has indeed completed the contract. Both parties have documented their stance in the debate.
This is an example of what?
- A. Breach of contract
- B. Claim
- C. Issue
- D. Risk
正解: B
解説:
Section: Volume A
質問 228
You are the program manager for your organization and you are preparing to launch several constituent projects within your program. You need to ensure that each project manager is authorized to utilize the appropriate project and program resources in order to complete the project requirements. What document do you need to create for each constituent project in your program to ensure that each project manager can use the appropriate resources?
- A. Roles and responsibilities chart
- B. Project resource requirements document
- C. Project scope statement
- D. Project charter
正解: D
解説:
Section: Volume A
質問 229
Which of the following tools and techniques are parts of the Administer Program Procurements process? Each correct answer represents a complete solution. Choose all that apply.
- A. Contract performance review
- B. Supplier performance review
- C. Budget management system
- D. Inspection and audits
正解: A,C,D
解説:
Section: Volume C
質問 230
Which of the following individual should respond to the risk with the preplanned risk response?
- A. Risk owner
- B. Key stakeholder
- C. Project sponsor
- D. Project manager
正解: A
解説:
Section: Volume D
質問 231
What schedule analysis simulation tool allows you, the project manager, to review possible combinations of events such as optimistic, most likely and pessimistic outcomes for your project?
- A. pert
- B. gert
- C. pmis
- D. Monte Carlo
正解: D
解説:
Section: Volume B
質問 232
You are the program manager of a new program in your organization. This program will last for one year and your program team will work full-time on the effort. The nature of the work requires that the program team work closely together for the next year, but many of the program team members have never met one another.
You decide to take the team on an outing where they can work together through challenges, learn teamwork, and get to know one another. This is an example of what process?
- A. Team development
- B. Cost of quality
- C. Forming
- D. Storming
正解: A
質問 233
A multi-year complex program will deliver advanced driver assistance system (ADAS) components for autonomous vehicles. Several key stakeholders are concerned because they have not been regularly involved with the program and do not understand the program's benefits.
What should the program manager do to address these key stakeholders' concerns?
- A. Create a progress report to share with stakeholders after the next status meeting.
- B. Update the communications management plan after meeting with the program steering committee.
- C. Capture stakeholder expectations, and revise the stakeholder engagement plan.
- D. Meet with the stakeholders and update the stakeholder map.
正解: C
質問 234
Your program will create new software and install new hardware for your organization. Some of the goals of the program is to improve employee morale, improve customer service, and boost customer satisfaction. These intangible goals need metrics. What program stakeholder is responsible for quantifying these goals?
- A. Business analyst
- B. Program customer
- C. Program director
- D. Program manager
正解: D
解説:
Section: Volume B
質問 235
You are the project manager for the JJY Project, which is similar to the HHG Project you managed last quarter. You would like to model the current project scope on the previous project to save time and effort. This is an example of what kind of scope definition?
- A. Template driven
- B. Organizational process assets
- C. Analogous estimating
- D. Parametric scope definition
正解: A
質問 236
You are the program manager for your organization. Management has assigned you to a new program that has been chartered. Your team is in the process of the Manage Program Issues process. One of the two outputs of this process is change requests. Which one of the following is the other one?
- A. Audit reports
- B. Program management plan
- C. Program performance reports
- D. Program issues register updates
正解: D
解説:
Section: Volume C
質問 237
What is the present value of a program that will be worth $3,567,000 if it lasts for six years and the rate of return is five percent?
- A. $2,502,750
- B. $2,661,750
- C. $3,532,000
- D. $1,550,850
正解: B
質問 238
Robert is the program manager for his organization which operates in a matrix structure.
Resources in Robert's program will be utilized on several projects in and out of his program. He wants to be certain that all of the resources will be planned accordingly and that the project managers communicate with one another about when the resources will be needed and utilized in the projects. What plan should Robert create along with the project managers to ensure that the resources are scheduled and managed effectively?
- A. Resource calendar
- B. Resource management plan
- C. Program management calendar
- D. Schedule management plan
正解: B
解説:
Section: Volume B
質問 239
Company A acquires company B, which leads to a two-year program to integrate the processes and systems.
Company B uses a different project management process, and the company's staff is unhappy about the acquisition. As a result, company B's project team fails to provide status and cost data in a format that conforms to the program standards.
What should the program manager do first?
- A. Inform the stakeholders of this issue as soon as possible
- B. Remind the project manager of the relevant program standards
- C. Work with the reports provided to extract the required information
- D. Change the program standards, aligning them with the project standards
正解: B
質問 240
Mary has just completed a large program for her organization. What should Mary now do with the program records that she has created throughout the program?
- A. The program records should be archived with the program customer.
- B. The program records should be archived as part of organizational process assets.
- C. The program records should be archived with the program sponsor.
- D. The program records should be archived as part of enterprise environmental factors.
正解: B
質問 241
In your organization there are rules and procedures that the program manager must follow and abide by before the program can begin and must continue to follow once the program is in execution. What term is assigned to the enforcement of these program management rules and procedures?
- A. Organizational process assets
- B. Program governance
- C. Program standards
- D. Process analysis
正解: B
解説:
Section: Volume B
質問 242
Complete the following phrase about quality management:
Quality is ____ into a program, not ____ into a program.
- A. Planned, inspected
- B. Built, inspected
- C. Planned, controlled
- D. Executed, controlled
正解: A
質問 243
Paula is program manager for her organization. It has come to her attention that several of the projects within her program have stalled which has now caused her project to be delayed. Paula is required by her organization to create a certain type of report when there are variances in the program dealing with time and cost. What type of report is Paula likely to create in this instance?
- A. Exceptions report
- B. Earned Value Management report on the schedule performance index
- C. Quality Control Report
- D. Status report
正解: A
質問 244
Which of the following documents sets the project objectives?
- A. Project charter
- B. Project schedule
- C. Project scope statement
- D. Project organization chart
正解: C
質問 245
......