有効なAgilePM-Foundationテスト解答APMG-International AgilePM-Foundation試験PDF問題を試そう [Q27-Q51]

Share

有効なAgilePM-Foundationテスト解答APMG-International AgilePM-Foundation試験PDF問題を試そう

APMG-International AgilePM-Foundation認定リアル2023年最新の模擬試験合格させます

質問 # 27
Which information is given in the Solution Architecture Definition?

  • A. A high-level design framework for the solution.
  • B. The strategy for testing
  • C. The tools and standards to be used in Evolutionary Development
  • D. A snapshot of the evolving business, solution and management products

正解:D


質問 # 28
What DSDM Principles requires the transparency of all work being performed by the team?

  • A. Principle 66-Develop iteratively
  • B. Principle 1 - Build incrementally from Firm Foundations
  • C. Principle 8-Demonstrate Control
  • D. Principle 1- Focus on the Business Need

正解:C


質問 # 29
Which of the following statements about the technical Coordinator role is true?
The technical Coordination provides the same function from a technical perspective as the Business Ambassador does from a business perspective.
The technical Coordinator is responsible for ensuring that the solution confirm to the requested technical standards.

  • A. Both 1 and 2 are true
  • B. Only 2 is true
  • C. Neither 1 or 2 is true
  • D. Only 1 is true

正解:B


質問 # 30
During what phase should the strategy for Iterative Development be considered?

  • A. Foundations
  • B. Evolutionary Development
  • C. Pre-Project
  • D. Feasibility

正解:A


質問 # 31
What role is responsible for interpreting the needs of the Business Sponsor and communicating these to the team?

  • A. Business Analyst
  • B. Team Leader
  • C. Business Visionary
  • D. Technical Coordinator

正解:C


質問 # 32
During what DSDM phase is it established how quality to be assured?

  • A. At the start of Evolutionary Development
  • B. As part of Foundations
  • C. During each timebox during Evolutionary Development
  • D. During Feasibility

正解:B


質問 # 33
When is a Timebox Plan updated?

  • A. As needed by the Project Manager
  • B. At the Daily Start-ups
  • C. Each time a Timebox is completed
  • D. At Timebox Kick-ups

正解:C


質問 # 34
Which of the following is a stated benefit of using DSDM?
1. The business is better able to direct development
2. Designs are based on predicted
3. The risk of building the wrong solution Is reduced
4. Deployment is more likely to go smoothly

  • A. 2, 3, 4
  • B. 1, 2, 3
  • C. 1, 3, 4
  • D. 1, 2, 4

正解:C


質問 # 35
How is Quality ensured during Evolutionary Development?

  • A. By facilitating session to enable a group to work to achieve an agreed goal
  • B. By understanding and managing priorities
  • C. By managing objectives in a fixed time period
  • D. By continuous verification

正解:A


質問 # 36
What DSDM product describes how the benefits have actually accrued following a period in live operation?

  • A. Delivery Plan
  • B. Project Review Report
  • C. Prioritized Requirement List
  • D. Benefits Assessment

正解:D


質問 # 37
How is contingency typically managed in a DSDM project?

  • A. Not needed in a DSDM project.
  • B. Managed by varying time and cost
  • C. Allowed adding a percentage to the high-level estimates.
  • D. Managed by varying the features to be delivered.

正解:D


質問 # 38
According to the DSDM principle 'Never Compromise Quality, when should the overall level of quality to be delivered within the solution be agreed?

  • A. During evolutionary development
  • B. Whenever the level of solution quality is known.
  • C. When the Business Advisor is available
  • D. At the start of the project

正解:A


質問 # 39
How does the Post-Project phase add value to a project?

  • A. Checks how well the expected business benefits have been met
  • B. Iteratively explores the low- level detail of the requirements
  • C. Define how the operation of the solution will be managed
  • D. Brigs a baseline of the Evolving Solution into operational use

正解:A


質問 # 40
Which statement about change is correct for DSDM?

  • A. Project operate with a changing world
  • B. Change is inevitable and males estimating very difficult
  • C. Avoid change whenever possible
  • D. Change is a symptom of an inability to define requirements properly

正解:A


質問 # 41
Which plain defined by DSDM, has a planning horizon that includes the end of a project?

  • A. Delivery
  • B. High-Level
  • C. Detailed
  • D. Timebox

正解:A


質問 # 42
Which of the following support the DSDM philosophy and principles?

  • A. Phases, productivity, power and process
  • B. Plans, projects, process and people
  • C. Process, people, products and practices
  • D. People, products, phase and plans

正解:C


質問 # 43
In what phase is it first established whether further investigation of the project is justified?

  • A. Foundations
  • B. Evolutionary Development
  • C. Pre-Project
  • D. Feasibility

正解:D


質問 # 44
Which of the following are recognized DSDM styles of Timebox?
1. Unstructured
2. Consolidated

  • A. Neither 1 or 2 is true
  • B. Only 2 is true
  • C. Only 1 is true
  • D. Both 1 and 2 are true

正解:D


質問 # 45
What role is responsible for the delivery of the project from Foundations through to Deployment?

  • A. Business Sponsor
  • B. Project manager
  • C. Business Visionary
  • D. Technical Coordinator

正解:B


質問 # 46
What phase will create Solution increments?

  • A. Foundations
  • B. Evolutionary Development
  • C. Feasibility
  • D. Deployment

正解:B