質問 # 30
What phase will decide on which projects are started, based on a clearly defined objective?

  • A. Post-project
  • B. Pre-Project
  • C. Foundations
  • D. Feasibility

正解:B


質問 # 31
Which purpose relates to the instrumental Success Factors?

  • A. Inform the development of the Terms of Reference
  • B. Informs the development of the Business Case
  • C. Underpins the prioritization of requirements
  • D. Positions DSDM projects for a successful outcome

正解:B


質問 # 32
During what phase should the strategy for Iterative Development be considered?

  • A. Pre-Project
  • B. Foundations
  • C. Evolutionary Development
  • D. Feasibility

正解:B


質問 # 33
When initially creating MoSCoW priorities, what is the primary focus?

  • A. Iterative Development priorities
  • B. Project priorities
  • C. Project increment priorities
  • D. Timebox priorities

正解:B


質問 # 34
Identify the missing word in the following sentence.
The Business Sponsor is known as the project [?] because they are committed to the solution and the delivery approach.

  • A. Champion
  • B. director
  • C. Visionary
  • D. Governor

正解:C


質問 # 35
What does DSDM refer to the Minimum Usable Subset?

  • A. All requirements in the functional specification
  • B. The Must Have requirements
  • C. Those requirements that have passed user acceptance testing
  • D. The Must, Should and Could have requirements

正解:B


質問 # 36
Which technique allows for testing the achievailability of objectives?

  • A. Timeboxing
  • B. Modeling
  • C. MoSCoW
  • D. Facilitated Workshop

正解:D


質問 # 37
What DSDM product is identified as a governance product because if may be used for purposes such as prioritization of a project within a portfolio?

  • A. Business Case
  • B. Prioritized Requirements List
  • C. Feasibility Assessment
  • D. Terms of Reference

正解:D


質問 # 38
How is Quality ensured during Evolutionary Development?

  • A. By facilitating session to enable a group to work to achieve an agreed goal
  • B. By managing objectives in a fixed time period
  • C. By continuous verification
  • D. By understanding and managing priorities

正解:A


質問 # 39
What DSDM product reflects the approach to the management of the project as a whole and considers, from a management perspective, how the project will be organized and planned?

  • A. Foundation Summary
  • B. Delivery Plan
  • C. Terms of Reference
  • D. Management Approach Definition

正解:A


質問 # 40
Which of the following is a stated benefit of using DSDM?
1. The business is better able to direct development
2. Designs are based on predicted
3. The risk of building the wrong solution Is reduced
4. Deployment is more likely to go smoothly

  • A. 1, 3, 4
  • B. 2, 3, 4
  • C. 1, 2, 4
  • D. 1, 2, 3

正解:A


質問 # 41
Which competence is NOT required within the Solution Development team?

  • A. Willingness to work with other
  • B. Technical expertise
  • C. All members to be multi-skilled experts
  • D. Business knowledge

正解:C


質問 # 42
Which of the following statements about the technical Coordinator role is true?
The technical Coordination provides the same function from a technical perspective as the Business Ambassador does from a business perspective.
The technical Coordinator is responsible for ensuring that the solution confirm to the requested technical standards.

  • A. Only 2 is true
  • B. Only 1 is true
  • C. Both 1 and 2 are true
  • D. Neither 1 or 2 is true

正解:A


質問 # 43
What role is responsible for interpreting the needs of the Business Sponsor and communicating these to the team?

  • A. Technical Coordinator
  • B. Team Leader
  • C. Business Visionary
  • D. Business Analyst

正解:C


質問 # 44
During what phase should a baseline of the Evolving Solution be put into operational use?

  • A. Post-Project
  • B. Deployment
  • C. Evolutionary Development
  • D. Foundations

正解:B


質問 # 45
Which practice provides an interactive environment in which all key players can contribute to the outcome?

  • A. Timeboxing
  • B. Facilitied Wordshop
  • C. Iterative Development
  • D. Modelling

正解:B


質問 # 46
How is contingency typically managed in a DSDM project?

  • A. Not needed in a DSDM project.
  • B. Managed by varying time and cost
  • C. Allowed adding a percentage to the high-level estimates.
  • D. Managed by varying the features to be delivered.

正解:D


質問 # 47
When should the quality of the evolving solution first be tesed?

  • A. At the end of a Timebox
  • B. At the end of a project.
  • C. As part of the iterative Development process
  • D. At the end of each increment

正解:C


質問 # 48
......