質問 # 53
Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question
- A. In the operative WBS element
- B. In the project definition of a standard WBS
- C. In the project type
- D. In the project version
- E. In the project profile
正解:A、B、E
質問 # 54
Project Structures
You want to enable user fields for customer project. Therefore you create several field keys. What is the benefit of assigning a field key to the project profile?
- A. The field key is hard coded in the WBS element.
- B. The field key is the default value only for the WBS element.
- C. The tab user fields is invisible.
- D. The field key is the default value for the WBS element and the activities too.
正解:D
質問 # 55
How can you record external service activities with service master data? Note: There are 2 correct Answers to this question.
- A. Create a service entry sheet.
- B. Confirm the activities in the Cross-Application Time Sheet (CATS).
- C. Confirm the network activity for external services.
- D. Post a goods receipt in the goods movement application (MIGO).
正解:A、B
質問 # 56
Project structure
You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?
Note : there are 3 correct answer for this question.
- A. Standard network
- B. Standard Project definition
- C. Project milestone
- D. Project definition
- E. Project version.
正解:A、B、E
質問 # 57
Materials
Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled.
Which set of dates can be used for scheduled for network?
Note : there are 2 correct answer for this question.
- A. Planned dates
- B. Basic dates
- C. Forecast dates
- D. Baseline dates
- E. Fundamental dates
正解:A、C
解説:
In the SAP Project System, there are different sets of dates that can be scheduled for a network. Some of these sets of dates are:
Planned dates: These are the dates that you enter manually for the network activities and relationships. You can use planned dates to define your own scheduling scenario that may differ from the system-calculated dates.
Forecast dates: These are the dates that are calculated by the system based on the current progress and status of the network activities and relationships. You can use forecast dates to estimate the future dates of the network based on the actual data and remaining work. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html
質問 # 58
In your logistics project, you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?
- A. Capacity planner group in the network header
- B. Scheduling and capacity category
- C. Scheduling and distribution key
- D. Control key of an activity
正解:D
質問 # 59
Where do you control whether a project stock is managed as valuated or non-valuated project stock?
- A. In the project definition
- B. In the material master
- C. In the network activity
- D. In the WBS element
正解:B
解説:
To control whether a project stock is managed as valuated or non-valuated project stock, you have to maintain the setting in the material master. The material master is a set of data that defines the characteristics and properties of a material that can be produced or procured. The material master contains various views that store different types of information about a material, such as basic data, sales data, purchasing data, accounting data, and so on. In the accounting view of the material master, you can specify whether a material is relevant for valuated project stock or not by using the Valuation category field. The valuation category is a parameter that determines how a material is valuated in different stock accounts. If you select Q as the valuation category for a material, it means that the material is relevant for valuated project stock and its value is updated in Financial Accounting. If you leave the valuation category blank for a material, it means that the material is relevant for non-valuated project stock and its value is not updated in Financial Accounting. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 60
What are some of the advantages of using project simul-ations? Note: There are 3 correct answers to this question
- A. Multiple project simulations can be used simultaneously
- B. Project simulations allow posting of actual data
- C. Project simulations can be created without using an operational project as a template
- D. Project simulations can be used to plan structures and costs
- E. Project simulations can create purchase requisitions
正解:A、C、D
解説:
Project simulations are some of the advantages of using project simulations in SAP Project System. Project simulations are copies of projects that allow you to plan and simulate different scenarios without affecting operational projects. Project simulations can be created without using an operational project as a template, which means you can start from scratch or use a standard structure. Project simulations can be used to plan structures and costs, which means you can create and change WBS elements, networks, activities, and cost elements. Multiple project simulations can be used simultaneously, which means you can compare different alternatives and choose the best one. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 61
You use a WBS project structure with network and maintenance order. You want to schedule both the network and the maintenance order .
What do you have to consider?
- A. The maintenance orders must be assigned to WBS element.
- B. The maintenance orders must be assigned as sub-networks.
- C. The maintenance orders must be assigned to the same plant as the network.
- D. The maintenance order s must be assigned to the same budget profile as the project definition.
正解:C
質問 # 62
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?
- A. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing
- B. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element
- C. Activate commitment management in the project definition Enter the budget in the master data of the top WBS element
- D. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element
正解:A
解説:
To solve the problem of the system not preventing their project managers from exceeding their budgets, you have to activate availability control in the assigned budget profile and define the tolerance limits in customizing. The budget profile is a parameter that defines the basic settings for budgeting in your project, such as whether availability control is active or not. The tolerance limits are values that specify how much deviation from the budget is allowed before the system issues warnings or error messages. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 63
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct answers to this question
- A. Billing
- B. Quotation
- C. Sales order
- D. Inquiry
正解:A、D
質問 # 64
Which object is relevant in assembly processing to create an assembly order for the SD document?
- A. Control key
- B. Item category
- C. Project profile
- D. Requirement class
正解:D
質問 # 65
How can you record external service activities with service master data? Note: There are 2 correct answers to this question
- A. Create a service entry sheet
- B. Confirm the network activity for external service
- C. Confirm the activities in the Cross-Application Time Sheet (CATS)
- D. Post a goods receipt in the goods movement application (MIGO)
正解:B、D
質問 # 66
What could be a reason to use expert mode in the valuation method for results analysis?
- A. Billing WBS elements belonging to different company codes
- B. Usage of different line ID
- C. Valuation in different currencies
- D. Assignments of different accounts for postings to financial accounting
正解:B
解説:
One reason to use expert mode in the valuation method for results analysis is usage of different line ID. Results analysis is a function that allows you to calculate and post values for work in process (WIP), reserves for unrealized costs (RUC), profit from sales order stock (PSOS), and so on. Results analysis uses valuation methods to determine how these values are calculated based on various criteria, such as cost of sales method, percentage of completion method, revenue-based method, and so on. Expert mode is a type of valuation method that allows you to define your own logic and rules for results analysis by using formulas and conditions. One reason to use expert mode in the valuation method for results analysis is usage of different line ID. A line ID is a parameter that identifies a line item in results analysis data. A line ID can have various attributes, such as cost element group, value category, posting indicator, and so on. By using expert mode in the valuation method for results analysis, you can use different line ID for different scenarios or requirements that are not covered by the standard valuation methods. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
質問 # 67
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.
- A. Confirmations
- B. Settlement
- C. Progress analysis
- D. Milestone trend analysis
- E. Results analysis
正解:B、C、E
質問 # 68
What PPIDS master data is necessary for using PP/DS? Note: There are 2 correct answers to this question
- A. Material
- B. Location
- C. Production version
- D. Resource
正解:A、D
解説:
PPIDS master data is necessary for using PP/DS, which is a component of SAP APO that provides advanced planning and scheduling functions for production planning and detailed scheduling. PPIDS master data includes material and resource data. Material is a set of data that defines the characteristics and properties of a product that can be produced or procured. Resource is a set of data that defines the characteristics and capacities of a production facility that can be used to produce products. Reference: https://help.sap.com/doc/saphelp_scm700_ehp02/7.0.2/en-US/69/f3055130534338e10000000a154ce5/content.htm
質問 # 69
......