質問 # 18
You are using networks and external activities in your project The purchase requisition has been created. What is the sequence for the following business transactions and documents?
- A. . Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt -> invoice receipt
- B. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt
- C. Vendor selection -> Purchase order handling -> Invoice receipt- Purchase order monitoring -> Goods receipt
- D. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval
正解:B
質問 # 19
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.
- A. Saving a goods receipt
- B. Saving a purchase order
- C. Saving a supplier invoice
- D. Saving a service entry sheet
正解:A、D
質問 # 20
The various work packages in the project are described as individual______________. Choose the correct answer.
- A. Activities
- B. Tasks
- C. Project definitions
- D. WBS elements
正解:D
質問 # 21
Cost & budget
A service Company use project management and they complain that the system does not prevent their project manager from exceeding their budget.
What action do you have tsolve the problem?
- A. Activate commitment
- B. Activate availability control in the assign budget profile. Defined the tolerance limit in the customizing.
- C. Activate availability control for the important WBS element. Define the tolerance limit on each WBS element.
- D. Activate availability control For projects in the control area. Enter the plan data for each WBS element.
- E. management in the project definition. Enter the budget in the master data of the top WBS element.
正解:B
質問 # 22
How can you update the degree of processing for an activity?
- A. By scheduling the activity
- B. By using results analysis
- C. By confirming the activity
- D. By changing the activity
正解:C
質問 # 23
Project Structure
You plan double the work on each internal activity for multiple project. What do you recommend?
- A. Double the work of each internal activity, one after another, in the project Builder.
- B. Use mass change (CNMASS) in the project system.
- C. Use mass change within the project Builder (CJ20N).
- D. Double the capacity in the work center.
正解:B
質問 # 24
What is the reason for assigning billing plans in customer projects?
- A. Billing plans are copied automatically to the sales order item.
- B. Billing plans are prerequisites for quotation creation.
- C. Billing plans are used for revenue planning.
- D. Billing plans enable the billing process to be carried out.
正解:D
質問 # 25
You want to use subnetworks during the project. Which of the following statements describes subnetworks?
- A. The scheduling type of a subnetwork is always copied from the superior network.
- B. A subnetwork cannot be defined for a superior subnetwork.
- C. Maintenance orders can be defined as subnetworks.
- D. Subnetworks must be scheduled separately from the superior network.
正解:C
質問 # 26
Which of the following apply to dynamic item processor (DIP)? Note: There are 3 correct Answers to this question.
- A. DIP is used to create a quotation.
- B. Sources can be based on line items.
- C. Usage of cost elements is mandatory.
- D. Sales prices are maintained in the DIP profile.
- E. Material determination is mandatory.
正解:A、B、D
質問 # 27
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?
- A. Extended capacity evaluation
- B. None
- C. Structure overview
- D. Individual overview capacity requirements
- E. Capacity load work center view
正解:D
質問 # 28
Which planning method can prevent further rescheduling of activities?
- A. Capacity requirements activation
- B. Workforce planning
- C. Capacity leveling
- D. Partial confirmation of activities
正解:A
質問 # 29
What PPIDS master data is necessary for using PP/DS? Note: There are 2 correct answers to this question
- A. Production version
- B. Location
- C. Resource
- D. Material
正解:A、D
質問 # 30
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.
- A. The material is assigned to the activity as a non-stock material.
- B. The material master is set to external procurement.
- C. The availability check for material components indicates missing parts.
- D. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never".
正解:C、D
質問 # 31
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.
- A. Maintain subordinate internal activity elements assigned to other work centers.
- B. Trigger automatic capacity leveling inside the project planning board.
- C. Increase the capacities of the work center in the project planning board.
- D. Shift activities backward or forward on the time axis where more capacities are available.
正解:B、D
質問 # 32
Where do you control whether a project stock is managed as valuated or non-valuated project stock?
- A. In the material master
- B. In the WBS element
- C. In the project definition
- D. In the network activity
正解:C
質問 # 33
Cost and Budget
What function are available for period end-closing in the project System?
- A. Confirmation
- B. Settl ement
- C. Milestone trend analysis
- D. Result analysis
- E. Progress analysis
正解:C、D、E
質問 # 34
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?
- A. Set up the requirement date aligned with the activity start date and an offset of 5 days.
- B. Set up the requirement date aligned with the activity start date and a negative offset of 5 days.
- C. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
- D. Set up the requirement date manually as February 5.
正解:A
質問 # 35
Project Structure
Which statement regarding the creation of a new work breakdown structure (WBS element) are true?
Note : there are 3 correct answer for this question.
- A. A new work breakdown structure must contain up to 10 levels.
- B. The WBS structure can contain several level 1 WBS element, (es configurable por perfil de proyecto)
- C. A WBS element of the new project can be assigned to a different project definition.
- D. WBS element can be a planning element, an account assignment element, and a billing element at the same time.
- E. You can create several WBS elements per level.
正解:B、D、E
質問 # 36
......