質問 # 43
Which of the following are cornerstones of SAP's security strategy? Note: There are 3 correct answers to this question

  • A. Secure Operations
  • B. Secure Company
  • C. Secure Projects
  • D. Secure Products
  • E. Secure Infrastructure

正解:A、B、D

解説:
* A is correct because Secure Company is one of the cornerstones of SAP's security strategy. It means that SAP ensures that its own organization, employees, and processes comply with the highest security standards and regulations.
* C is correct because Secure Operations is one of the cornerstones of SAP's security strategy. It means that SAP ensures that its cloud services are operated securely and reliably, with measures such as data protection, encryption, backup, monitoring, and incident response.
* E is correct because Secure Products is one of the cornerstones of SAP's security strategy. It means that SAP ensures that its software products are developed securely and follow best practices such as secure coding, testing, and patching.


質問 # 44
In which workstream do you execute an organizational change impact analysis?

  • A. Analytics
  • B. Application Design and Configuration
  • C. Data Management
  • D. Solution Adoption

正解:D

解説:
* B is correct because Solution Adoption is the workstream where you execute an organizational change impact analysis. The organizational change impact analysis is an activity that helps to assess the impact of the solution on the people, processes, and technology of the organization, and identify the change management actions that are needed to support the adoption and acceptance of the solution. Verified References:
* : SAP Activate Methodology for SAP S/4HANA Cloud, page 38


質問 # 45
Which task should you include in your procedure while preparing for a fit-to-standard analysis in an SAP Data Warehouse Cloud project?Note: There are 2 correct answers to this question.

  • A. Review SAP S/4HANA best practices availability for your country.
  • B. Review available SAP S/4HANA accelerators for the Data Management workstream
  • C. Review all the necessary Implementation Design Principles (IDPs).
  • D. Review all the necessary leading practice process diagrams.

正解:C、D

解説:
* B is correct because Implementation Design Principles (IDPs) are documents that provide guidance on how to configure and extend SAP Data Warehouse Cloud to meet customer-specific requirements1.
* D is correct because leading practice process diagrams are graphical representations of the business processes that are supported by SAP Data Warehouse Cloud and can be used as a reference for the fit-to-standard analysis2. Verified References:
* 1: SAP Data Warehouse Cloud Implementation Design Principles
* 2: SAP Data Warehouse Cloud Best Practices


質問 # 46
What is the objective of a sprint retrospective meeting?

  • A. Review and prioritize the backlog.
  • B. Provide formal feedback to the Project Manager.
  • C. Define the stakeholder management approach
  • D. Improve the Scrum process.

正解:D

解説:
* A is correct because improving the Scrum process is the objective of a sprint retrospective meeting. The sprint retrospective meeting is a time for the Scrum Team to reflect on how they worked together in the last sprint and identify ways to enhance their effectiveness and efficiency. Verified References:
* : What is a Sprint Retrospective? | Scrum.org


質問 # 47
Which of the following are SAP Activate workstreams?Note: There are 2 correct answers to this question.

  • A. Project Management
  • B. Data Migration
  • C. Change Management
  • D. Extensibility

正解:A、B

解説:
* B is correct because Project Management is one of the SAP Activate workstreams. The Project Management workstream covers all the activities related to planning, executing, monitoring, controlling, and closing the project. It includes tasks such as defining project scope, schedule, budget, resources, risks, issues, quality, communication, and stakeholder management.
* D is correct because Data Migration is one of the SAP Activate workstreams. The Data Migration workstream covers all the activities related to preparing, extracting, transforming, validating, and loading data from legacy systems to SAP systems. It includes tasks such as defining data migration strategy, scope, approach, tools, roles, responsibilities, quality criteria, and testing scenarios. Verified References:
* : SAP Activate Methodology Workstreams Names update
* : SAP Activate Testing Workstream


質問 # 48
What are the responsibilities of the product owner in release and sprint planning? Note: There are 2 correct answers to this question

  • A. Estimate the backlog user stories.
  • B. Define objectives for each release
  • C. Analyze the functional and technical dependencies between user stories
  • D. Prioritize backlog user stories by business priority.

正解:B、D

解説:
* A is correct because prioritizing backlog user stories by business priority is one of the responsibilities of the product owner in release and sprint planning. The product owner decides which user stories are more important and valuable for the customer and orders them accordingly in the product backlog.
* B is correct because defining objectives for each release is one of the responsibilities of the product owner in release and sprint planning. The product owner sets the goals and expectations for each release, based on the customer's vision and feedback, and communicates them to the project team and stakeholders. Verified References:
* : SAP Activate Project Management Certification Guide, page 112


質問 # 49
Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?

  • A. Project Manager's relative effort estimate that will be needed to implement and test the user story
  • B. Detailed bottom-up effort estimate by the product owner that breaks up each story into short tasks
  • C. Relative effort estimate in Ideal Person Days that reflects the best estimate by the project
  • D. Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity

正解:D

解説:
The team members reveal their cards simultaneously and discuss their estimates until they reach a consensus.
This technique is based on the concept of story points, which are units of measure for expressing the overall effort required to fully implement a user story. Story points are assigned to user stories based on their complexity, risk, and uncertainty.


質問 # 50
What is the difference between the "New Implementation of SAP S/4HANA Cloud, public edition" and the
"New Implementation of SAP S/4HANA, private edition" transition paths? Note: There are 2 correct answers to this question

  • A. SAP S/4HANA Cloud, public edition does NOT offer built-in capabilities for extensibility, while SAP S/4HANA Cloud, private edition offers a full development environment
  • B. Upgrades of SAP S/4HANA Cloud, public edition are based on SAP timelines, and upgrades of SAP S/4HANA Cloud private edition are based on timelines agreed between SAP and the customer
  • C. SAP S/4HANA Cloud, private edition uses the Implementation Guide (IMG) and SAP S/4HANA Cloud, public edition uses SAP Central Business Configuration.
  • D. -I SAP S/4HANA Cloud, private edition is only available through SAP Cloud services and with embedded implementation services from SAP

正解:B、C

解説:
* C is correct because upgrades of SAP S/4HANA Cloud, public edition are based on SAP timelines, and upgrades of SAP S/4HANA Cloud, private edition are based on timelines agreed between SAP and the customer. This is one of the differences between the two transition paths. SAP S/4HANA Cloud, public edition has mandatory quarterly upgrades that are performed by SAP, while SAP S/4HANA Cloud, private edition has optional upgrades that are scheduled by the customer in coordination with SAP.
* D is correct because SAP S/4HANA Cloud, private edition uses the Implementation Guide (IMG) and SAP S/4HANA Cloud, public edition uses SAP Central Business Configuration. This is another
* difference between the two transition paths. SAP S/4HANA Cloud, private edition allows more flexibility and customization in the configuration, while SAP S/4HANA Cloud, public edition follows a guided and standardized configuration process. Verified References:
* : [SAP S/4HANA Cloud Editions]
* : [Central Business Configuration Overview]


質問 # 51
Which tool do you use to configure SAP S/4HANA Cloud, public edition?

  • A. SAP Solution Manager
  • B. SAP Central Business Configuration
  • C. IMG (Implementation Guide)
  • D. SAP Cloud ALM

正解:B

解説:
* C is correct because SAP Central Business Configuration is the tool that you use to configure SAP S/4HANA Cloud, public edition. It provides a guided configuration process that helps you to activate your system, enter configuration data, and validate your settings. Verified References:
* : Central Business Configuration Overview


質問 # 52
What criterion does the product owner use to sequence the product backlog?

  • A. Business priority
  • B. Relative effort
  • C. Resource availability
  • D. Complexity

正解:A

解説:
* A is correct because the product owner is responsible for prioritizing the product backlog based on the business value and urgency of each user story3. Verified References:
* 3: SAP Activate Project Management Certification Guide, page 112


質問 # 53
What information does the project team need before they can correctly estimate the relative size of backlog user stories? Note: There are 2 correct answers to this question.

  • A. Available project resources
  • B. Benchmark user story
  • C. Definition of Ready
  • D. Definition of Done

正解:C、D

解説:
Definition of Done is the information that the project team needs before they can correctly estimate the relative size of backlog user stories. Definition of Done is a set of criteria that determines when a user story is considered complete and ready for acceptance by the product owner. It helps the team to align their expectations and assumptions on each user story, and provide consistent and reliable estimates.


質問 # 54
What criteria does the product owner use to sequence the backlog?Note: There are 2 correct answers to this question.

  • A. Business priority
  • B. Complexity of the story
  • C. Release planning schedule
  • D. Technical dependencies

正解:A、D

解説:
* A is correct because technical dependencies are one of the criteria that the product owner uses to sequence the backlog. Technical dependencies are the relationships between user stories that affect their order of implementation. For example, some user stories may require other user stories to be completed first, or some user stories may have a common prerequisite or constraint.
* C is correct because business priority are one of the criteria that the product owner uses to sequence the backlog. Business priority is the measure of how important and valuable a user story is for the customer and the stakeholders. The product owner decides which user stories are more urgent and beneficial, and places them higher in the backlog. Verified References:
* : Product Backlog


質問 # 55
Which additional scope option does the strategic advisory service for cloud analytics offer?Note: There are 2 correct answers to this question

  • A. SAP Activate methodology for the Intelligent Enterprise
  • B. SAP S/4HANA for central finance
  • C. Baseline package
  • D. Extended package

正解:C、D

解説:
* A is correct because the extended package is an additional scope option that the strategic advisory service for cloud analytics offers. It provides a deeper analysis of the customer's current analytics landscape and a more detailed roadmap for the cloud analytics transformation.
* C is correct because the baseline package is an additional scope option that the strategic advisory service for cloud analytics offers. It provides a high-level assessment of the customer's current analytics landscape and a general roadmap for the cloud analytics transformation. Verified References:
* : Strategic Advisory Service for Cloud Analytics


質問 # 56
What is the difference between the System Conversion and New Implementation transition paths to SAP S/4HANA? Note: There are 2 correct answers to this question.

  • A. Data is converted in System Conversion and migrated in New Implementation of SAP S/4HANA in the Realize phase.
  • B. Custom code is adjusted in System Conversion and developed in New Implementation of SAP V U S/4HANA in the Realize phase.
  • C. Custom code is developed in System Conversion and adjusted in New Implementation of SAP u S/4HANA in the Realize phase. 4
  • D. Data is migrated in System Conversion and converted in New Implementation of SAP S/4HANA in the Realize phase.

正解:A、B

解説:
* A is correct because custom code is adjusted in System Conversion and developed in New Implementation of SAP S/4HANA in the Realize phase. In System Conversion, the existing custom code needs to be adapted to run on SAP S/4HANA. In New Implementation, new custom code needs to be developed to meet the customer's specific requirements.
* D is correct because data is converted in System Conversion and migrated in New Implementation of SAP S/4HANA in the Realize phase. In System Conversion, the existing data needs to be converted to the new data structures and formats of SAP S/4HANA. In New Implementation, new data needs to be migrated from the legacy system or other sources to SAP S/4HANA. Verified References:
* : SAP Activate Project Management Certification Guide, page 127


質問 # 57
Which of the following tools can support you in managing requirements and software development for implementation projects? Note: There are 2 correct answers to this question

  • A. Focused Insights for SAP Solution Manager
  • B. Focused Build for SAP Solution Manager
  • C. SAP Cloud ALM
  • D. SAP Focused Run

正解:B、C

解説:
* B is correct because Focused Build for SAP Solution Manager is a tool that supports the management of requirements and software development for implementation projects. It provides features such as requirements-to-deploy process, collaboration platform, quality gate management, and test management.
* D is correct because SAP Cloud ALM is a tool that supports the management of requirements and software development for implementation projects. It provides features such as project task management, solution documentation, change request management, and test management. Verified References:
* : Focused Build for SAP Solution Manager
* : SAP Cloud ALM


質問 # 58
Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?

  • A. Relative effort estimate in Ideal Person Days that reflects the best estimate by the project ^ team
  • B. Project Manager's relative effort estimate that will be needed to implement and test the user ^ story
  • C. Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity
  • D. Detailed bottom-up effort estimate by the product owner that breaks up each story into short ^ tasks

正解:C

解説:
* A is correct because Planning poker is an estimation technique that you can use in an Agile delivery approach to size the user stories during sprint planning. Planning poker is a game where each team member uses a set of cards with numbers that represent the relative effort of a user story. The team members reveal their cards simultaneously and discuss their estimates until they reach a consensus. This technique is based on the concept of story points, which are units of measure for expressing the overall effort required to fully implement a user story. Story points are assigned to user stories based on their complexity, risk, and uncertainty. Verified References:
* : Planning Poker


質問 # 59
What tool would you use for managing project tasks and Solution Documentation when implementing SAP S/4HANA Cloud, public edition?

  • A. SAP Support Portal
  • B. SAP Cloud ALM
  • C. SAP Roadmap Viewer
  • D. SAP Transformation Navigator

正解:B

解説:
* D is correct because SAP Cloud ALM is a tool that can be used for managing project tasks and solution documentation when implementing SAP S/4HANA Cloud, public edition. It provides features such as project task management, solution documentation, change request management, and test management.
Verified References:
* : SAP Cloud ALM


質問 # 60
Which collaboration features are available in the SAP Community? Note: There are 2 correct answers to this question.

  • A. Comment on Key Deliverables
  • B. Update Key Deliverable wikis
  • C. Tweet questions
  • D. Ask questions

正解:A、D

解説:
* B is correct because asking questions is one of the collaboration features that are available in the SAP Community. The SAP Community allows users to post questions on various topics and get answers from other users, experts, or moderators.
* C is correct because commenting on key deliverables is one of the collaboration features that are available in the SAP Community. The SAP Community allows users to comment on the key deliverables that are published by SAP or other users, such as blog posts, articles, videos, podcasts, or webinars. Verified References:
* : SAP Community Home


質問 # 61
Which of the following are used to perform configuration in SAP S/4HANA Cloud, private edition? (Choose Two)

  • A. Self Service Configuration Uls (SSCUIs)
  • B. IMG (Implementation Guide)
  • C. SAP Central Business Configuration
  • D. SAP Solution Manager

正解:A、B

解説:
* B is correct because IMG (Implementation Guide) is a tool that can be used to perform configuration in SAP S/4HANA Cloud, private edition. It provides access to the configuration transactions and activities that are relevant for the project scope.
* C is correct because Self Service Configuration Uls (SSCUIs) are tools that can be used to perform configuration in SAP S/4HANA Cloud, private edition. They provide a user-friendly interface to configure the settings that are specific to the customer's business needs. Verified References:
* : SAP Activate Project Management Certification Guide, page 131


質問 # 62
You are transitioning to SAP S/4HANA.In which phase do you adjust custom code?

  • A. Realize
  • B. Deploy
  • C. Explore
  • D. Discover

正解:A

解説:
* A is correct because in the Realize phase, you adjust custom code when transitioning to SAP S/4HANA.
Custom code is the code that was developed by the customer or a partner to extend or modify the standard SAP functionality. Custom code needs to be adjusted to ensure compatibility and performance with SAP S/4HANA, as well as compliance with the simplification items and coding guidelines.
Verified References:
* : [SAP Activate Methodology for SAP S/4HANA On Premise], page 22


質問 # 63
What activity do you perform during the daily stand-up meeting?

  • A. Provide end users with a demo of the new features
  • B. Re-baseline the release plan
  • C. Report showstoppers.
  • D. Negotiate acceptance criteria

正解:C

解説:
* C is correct because reporting showstoppers is one of the activities that you perform during the daily stand-up meeting. A showstopper is an issue or impediment that prevents the team from completing their sprint goal or user story. The scrum master is responsible for resolving or escalating the showstoppers as soon as possible. Verified References:
* : SAP Activate Project Management Certification Guide, page 115