質問 # 36
What findings do you document in the Explore Phase workshops? Note: There are 3 correct answers to this question.
- A. Confirmation of scope
- B. Detailed design of extensions
- C. Business role mapping
- D. Process models
- E. Key business decisions
正解:A、D、E
解説:
* B is correct because key business decisions are one of the findings that you document in the Explore Phase workshops. Key business decisions are the choices that the customer makes regarding their business processes, such as organizational structure, master data, reporting, or integration. These decisions affect the configuration and customization of the solution, and need to be documented and approved by the customer.
* D is correct because confirmation of scope is one of the findings that you document in the Explore Phase workshops. Confirmation of scope is the validation that the customer agrees with the scope items that are selected for their solution, and that they understand the functionality and limitations of each scope item. This helps to ensure that there are no misunderstandings or misalignments between the customer and the project team.
* E is correct because process models are one of the findings that you document in the Explore Phase workshops. Process models are graphical representations of the business processes that show the sequence of activities, roles, and systems involved in executing the process. Process models help to visualize and communicate the business requirements and scenarios, and identify any gaps or extensions that need to be addressed. Verified References:
* : SAP Activate Project Management Certification Guide, page 123
* : [SAP Activate - Explore Phase: Use Fit-to-Standard to Confirm Business Process Fit and Identify Gaps in Your SAP S/4HANA Cloud Implementation]
質問 # 37
Which of the following are levels in the structure of an SAP Best Practices for SAP S/4HANA Solution Package?Note: There are 2 correct answers to this question.
- A. Scope Items
- B. Configuration Guides
- C. Building Blocks
- D. Business Process Scenarios
正解:A、C
解説:
* B is correct because Scope Items are one of the levels in the structure of an SAP Best Practices for SAP S/4HANA Solution Package. A Scope Item is a unit of business functionality that covers one or more business processes. A Scope Item has a description, a list of configuration steps, and a set of test cases.
* C is correct because Building Blocks are one of the levels in the structure of an SAP Best Practices for SAP S/4HANA Solution Package. A Building Block is a reusable component that contains configuration data, master data, or transactional data for a specific business area. A Building Block can be assigned to one or more Scope Items. Verified References:
* : [SAP Best Practices Explorer]
質問 # 38
What is the objective of using scaling Scrum techniques when coordinating large teams in complex projects?
- A. To bring all specialists, such as the company legal advisors, into the scrum team
- B. To reallocate staff to skill-based teams such as developers in one single team
- C. To ensure alignment in architecture, configuration, and integration
- D. To manage the flow of information between the project and stakeholders
正解:C
解説:
C is correct because ensuring alignment in architecture, configuration, and integration is one of the objectives of using scaling Scrum techniques when coordinating large teams in complex projects. Scaling Scrum techniques are methods that help to apply Scrum principles and practices across multiple teams working on a large-scale product or program. Scaling Scrum techniques aim to ensure alignment in architecture, configuration, and integration by establishing a common vision, backlog, definition of done, and cadence for the teams, and by facilitating cross-team communication and collaboration
質問 # 39
Which additional scope option does the strategic advisory service for cloud analytics offer?Note: There are 2 correct answers to this question
- A. Extended package
- B. SAP S/4HANA for central finance
- C. SAP Activate methodology for the Intelligent Enterprise
- D. Baseline package
正解:A、D
解説:
* A is correct because the extended package is an additional scope option that the strategic advisory service for cloud analytics offers. It provides a deeper analysis of the customer's current analytics landscape and a more detailed roadmap for the cloud analytics transformation.
* C is correct because the baseline package is an additional scope option that the strategic advisory service for cloud analytics offers. It provides a high-level assessment of the customer's current analytics landscape and a general roadmap for the cloud analytics transformation. Verified References:
* : Strategic Advisory Service for Cloud Analytics
質問 # 40
Which products are addressed in the SAP Activate methodology for the Intelligent Enterprise roadmap? Note:
There are 2 correct answers to this question.
- A. SAP Ariba
- B. SAP Fieldglass
- C. SAP S/4HANA
- D. SAP Concur
正解:A、B
解説:
* B is correct because SAP Fieldglass is one of the products that are addressed in the SAP Activate methodology for the Intelligent Enterprise roadmap. SAP Fieldglass is a cloud-based solution that helps organizations manage their external workforce and services procurement. The SAP Activate methodology for the Intelligent Enterprise roadmap provides guidance on how to implement and integrate SAP Fieldglass with other SAP solutions, such as SAP S/4HANA, SAP SuccessFactors, or SAP Ariba.
* C is correct because SAP Ariba is one of the products that are addressed in the SAP Activate methodology for the Intelligent Enterprise roadmap. SAP Ariba is a cloud-based solution that helps organizations manage their procurement and supply chain processes. The SAP Activate methodology for the Intelligent Enterprise roadmap provides guidance on how to implement and integrate SAP Ariba with other SAP solutions, such as SAP S/4HANA, SAP Fieldglass, or SAP Concur. Verified References:
* : [SAP Activate Methodology for Intelligent Spend Management Roadmap]
質問 # 41
Which of the following characteristics are unique to SAP S/4HANA Cloud, public edition?Note:
There are
3 correct answers to this question.
- A. Choice of hardware vendor
- B. Mandatory upgrades
- C. Customer data center deployment
- D. Optional 3-system landscape
- E. Software upgrades performed by SAP
正解:B、D、E
解説:
* A is correct because software upgrades performed by SAP are one of the characteristics that are unique to SAP S/4HANA Cloud, public edition. SAP takes care of the upgrade process and ensures that the system is always up to date with the latest features and innovations.
* D is correct because optional 3-system landscape is one of the characteristics that are unique to SAP S/4HANA Cloud, public edition. Customers can choose to have a 3-system landscape (development, quality, and production) or a 2-system landscape (quality and production) depending on their needs and preferences.
* E is correct because mandatory upgrades are one of the characteristics that are unique to SAP S/4HANA Cloud, public edition. Customers have to accept the upgrades that are delivered by SAP on a quarterly basis and cannot opt out or postpone them.
質問 # 42
What information does the project team need before they can correctly estimate the relative size of backlog user stories? Note: There are 2 correct answers to this question.
- A. Benchmark user story
- B. Available project resources
- C. Definition of Ready
- D. Definition of Done
正解:C、D
解説:
Definition of Done is the information that the project team needs before they can correctly estimate the relative size of backlog user stories. Definition of Done is a set of criteria that determines when a user story is considered complete and ready for acceptance by the product owner. It helps the team to align their expectations and assumptions on each user story, and provide consistent and reliable estimates.
質問 # 43
Which of the following Accelerators can you find in the SAP Best Practices Explorer?Note: There are 2 correct answers to this question
- A. Process Diagram
- B. Test Case
- C. Stakeholder Identification Guide
- D. Test Strategy
正解:A、B
解説:
* C is correct because Process Diagram is one of the accelerators that you can find in the SAP Best Practices Explorer. A Process Diagram is a graphical representation of a business process that shows the sequence of activities, roles, and systems involved in executing the process.
* D is correct because Test Case is one of the accelerators that you can find in the SAP Best Practices Explorer. A Test Case is a document that describes a scenario that needs to be tested, along with the expected results and test steps.
質問 # 44
When performing an SAP Readiness Check in system conversion, what areas are covered within the result?Note: There are 3 correct answers to this question
- A. Sizing for SAP S/4HANA
- B. Simplification database
- C. SAP and third party interfaces
- D. Recommended SAP Fiori apps
- E. Active business functions
正解:A、B、D
解説:
* A is correct because SAP Readiness Check in system conversion covers the area of recommended SAP Fiori apps, which are apps that are suggested by SAP based on the customer's current usage of SAP GUI transactions.
* C is correct because SAP Readiness Check in system conversion covers the area of sizing for SAP S/4HANA, which is an estimation of the hardware and software resources required to run SAP S/4HANA based on the customer's current system data.
* E is correct because SAP Readiness Check in system conversion covers the area of simplification database, which is a collection of simplification items that describe the changes and adaptations required for SAP S/4HANA compared to the previous SAP ERP releases. Verified References:
* : SAP Readiness Check 2.0 for SAP S/4HANA
質問 # 45
Which of the following best outlines the sequence of testing in the Realize phase?
- A. 1. String test 2. Integration Test 3. User Acceptance Test
- B. 1. Data Migration 2. String test 3. User Acceptance Test
- C. 1. String test 2. User Acceptance Test 3. Integration Test
- D. 1. Integration Test 2. User Acceptance Test 3. String test
正解:A
解説:
* B is correct because String test > Integration Test > User Acceptance Test is the best outline of the sequence of testing in the Realize phase. The String test is performed first to verify the end-to-end processes across the system landscape. The Integration Test is performed next to verify the integration of the solution with other systems and interfaces. The User Acceptance Test is performed last to verify that the solution meets the customer's business requirements and expectations. Verified References:
* : SAP Activate Project Management Certification Guide, page 120
質問 # 46
Which of the following considerations apply when determining the project methodology? Note: There are 3 correct answers to this question.
- A. Implementation fit
- B. Project fit
- C. Project Manager fit
- D. Solution fit
- E. Organizational fit
正解:A、B、E
解説:
* A is correct because implementation fit is one of the considerations that apply when determining the project methodology. It means that the project methodology should match the type and scope of the implementation, such as cloud, on-premise, hybrid, or mixed scenarios.
* C is correct because organizational fit is one of the considerations that apply when determining the project methodology. It means that the project methodology should suit the culture and maturity of the organization, such as its readiness for change, agility, and innovation.
* D is correct because project fit is one of the considerations that apply when determining the project methodology. It means that the project methodology should align with the characteristics and constraints of the project, such as its size, complexity, duration, and budget. Verified References:
* : SAP Activate Methodology for SAP S/4HANA Cloud, page 13
質問 # 47
Which tool do you use to configure SAP S/4HANA Cloud, public edition?
- A. SAP Solution Manager
- B. SAP Cloud ALM
- C. IMG (Implementation Guide)
- D. SAP Central Business Configuration
正解:D
解説:
* C is correct because SAP Central Business Configuration is the tool that you use to configure SAP S/4HANA Cloud, public edition. It provides a guided configuration process that helps you to activate your system, enter configuration data, and validate your settings. Verified References:
* : Central Business Configuration Overview
質問 # 48
You are transitioning to SAP S/4HANA.In which phase do you adjust custom code?
- A. Realize
- B. Deploy
- C. Discover
- D. Explore
正解:A
解説:
* A is correct because in the Realize phase, you adjust custom code when transitioning to SAP S/4HANA.
Custom code is the code that was developed by the customer or a partner to extend or modify the standard SAP functionality. Custom code needs to be adjusted to ensure compatibility and performance with SAP S/4HANA, as well as compliance with the simplification items and coding guidelines.
Verified References:
* : [SAP Activate Methodology for SAP S/4HANA On Premise], page 22
質問 # 49
Which new project roles are introduced with the SAP Activate methodology for the Agile delivery approach, compared to Waterfall?Note: There are 2 correct answers to this question.
- A. Integration lead
- B. Product owner
- C. Scrum master
- D. Design thinking coach
正解:B、C
解説:
* A is correct because the scrum master is a new project role that is introduced with the SAP Activate methodology for the Agile delivery approach, compared to Waterfall. The scrum master is responsible for facilitating and coaching the Scrum process, removing impediments, and ensuring the team's adherence to the Agile principles.
* B is correct because the product owner is a new project role that is introduced with the SAP Activate methodology for the Agile delivery approach, compared to Waterfall. The product owner is responsible for defining and prioritizing the product backlog, accepting or rejecting the user stories, and providing feedback and guidance to the team. Verified References:
* : SAP Activate Project Management Certification Guide, page 111
質問 # 50
Which of the following are workshop design principles/guidelines?Note: There are 2 correct answers to this question.
- A. Fit-to-standard
- B. Active participation
- C. Best Practices enablement
- D. Expert configuration definitions
正解:A、B
解説:
* A is correct because active participation is a key principle for designing effective workshops, as it ensures that all stakeholders are engaged and contribute to the workshop outcomes.
* B is correct because fit-to-standard is a workshop design guideline that aims to minimize customizations
* and leverage the standard SAP functionality as much as possible. Verified References:
* : SAP Activate Project Management Certification Guide, page 123
* : SAP Activate Methodology for SAP S/4HANA Cloud, page 40
質問 # 51
Which of the following tools facilitate secure communication between SAP cloud solutions and protected on-premise networks that CANNOT be accessed directly from the Internet?
- A. Identity Authentication service
- B. Cloud Integration Automation service
- C. SAP Business Technology Platform
- D. SAP Connectivity service
正解:D
解説:
* A is correct because SAP Connectivity service is one of the tools that facilitate secure communication between SAP cloud solutions and protected on-premise networks that cannot be accessed directly from the Internet. The SAP Connectivity service allows SAP cloud applications to access remote services that run on the Internet or on-premise via a secure tunnel established by the Cloud Connector. The Cloud Connector acts as a reverse proxy that connects to the SAP Connectivity service and exposes the on-premise systems to the cloud applications. Verified References:
* : Connectivity Service
* : SAP Cloud Platform Service: Connectivity
質問 # 52
Which systems are part of the private cloud edition landscape?Note. There are 2 correct answers to this question.
- A. Starter
- B. Production
- C. Evaluation
- D. Sandbox
正解:B、D
解説:
* A is correct because Production is one of the systems that are part of the private cloud edition landscape.
The Production system is the system where the solution is deployed and operated for the end users. It contains the live data and processes of the customer's business.
* B is correct because Sandbox is one of the systems that are part of the private cloud edition landscape.
The Sandbox system is an optional system that can be used for testing, prototyping, or training purposes.
It is a copy of the Production system that can be refreshed on demand.
質問 # 53
When conducting an upgrade of an SAP S/4HANA Cloud, public edition three system landscape, in which phase are the Business Roles updated?
- A. Explore
- B. Deploy
- C. Realize
- D. Discover
正解:A
解説:
* A is correct because in the Explore phase, the Business Roles are updated when conducting an upgrade of an SAP S/4HANA Cloud, public edition three system landscape. The Business Roles are the roles that define the access rights and authorizations for the users in the system. The Business Roles are updated to reflect the changes and enhancements that are introduced by the upgrade, such as new apps, features, or functions. Verified References:
* : SAP S/4HANA Cloud Upgrade Guide, page 11
質問 # 54
What is the primary purpose of the SAP Activate methodology?
- A. To enable access to the SAP ecosystem
- B. To manage solution documentation
- C. To provide end-to-end application lifecycle management
- D. To expedite all deployment options for SAP products
正解:D
解説:
C is correct because expediting all deployment options for SAP products is the primary purpose of the SAP Activate methodology. The SAP Activate methodology is a framework that provides guidance and best practices for implementing SAP solutions in different scenarios, such as cloud, on-premise, or hybrid. The SAP Activate methodology aims to accelerate and simplify the deployment process by combining ready-to-run business processes, proven implementation practices, and guided configuration tools.