C_TS422_2021実際の問題解答PDFには100%カバー率リアル試験問題 [Q44-Q61]

Share

C_TS422_2021実際の問題解答PDFには100%カバー率リアル試験問題

C_TS422_2021試験問題解答


SAP C-TS422-2021認証試験は、180分以内に完了する必要がある80の複数選択質問で構成されています。この試験は、英語と日本語で入手できます。試験の合格スコアは65%です。試験に合格すると、候補者はSAP認定アプリケーションアソシエイト - SAP S/4HANA生産計画および製造2021認定を受け取ります。これは2年間有効です。全体として、SAP C-TS422-2021認定試験は、専門家がSAP S/4HANAの生産計画と製造スキルを検証し、キャリアの見通しを強化する優れた方法です。

 

質問 # 44
Which times elements does MRP consider in backward scheduling to determine he order dates for components from dependent requirements?

  • A. Total replenishment lead time
  • B. Operation duration
  • C. Planed delivery time
  • D. In-house production time

正解:C、D


質問 # 45
Which materials have a negative quantity in a bill of materials or in a recipe?

  • A. By-products
  • B. Bulk materials
  • C. Waste products
  • D. Continuous flow materials
  • E. Co-products

正解:A、D、E


質問 # 46
Which SAP application can be used for forcasting in Supply Chain Planning?

  • A. Material Requirements Planning (MRP)
  • B. Supply Chain Management(SCM)
  • C. Capacity Requirements Planning (CRP)
  • D. Integrated Business Planning (IBP)

正解:B、D


質問 # 47
When working with bouth cross-plant and plant-specific material statuses n the material master, which statuses has the higest priority?

  • A. The plant-specific status
  • B. The last restrictive status
  • C. The cross-plant status
  • D. The most restrictive status

正解:D


質問 # 48
Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing?

  • A. Run MRP with quota arrangement.
  • B. Assign planned orders manual lying the planning table.
  • C. Run PP/DS heuristics for repetitive manufacturing.
  • D. Run MRP with automatic selection of production version.

正解:A、C


質問 # 49
You want to use capacity availability checks for production orders. Which settings have to be made for this?

  • A. A checking rule must be assigned in the checking control
  • B. The PRT Availability Check must be set in the checking control.
  • C. The Relevant for Finite Scheduling indicator must be set
  • D. An overall profile must be assigned in the checking control.

正解:C、D


質問 # 50
Which of the following elements does MRP take into account during net requirement calculation?

  • A. Maximum stock level
  • B. Lot size
  • C. Purchase orders
  • D. Safety stock

正解:B、D


質問 # 51
You have maintained the parameters for simple discontinuation in the material master of a component. Which business process will be affected if the available stock is zero and the discontinuation date is in the past?

  • A. Material requirements planning
  • B. Kanban
  • C. Backflushing
  • D. Production order release

正解:A


質問 # 52
Which of the following is valid sequence of the main activities in production order processing?

  • A. Creation, availability check, release, material widrawal, confirmation
  • B. Creation, release, printing, goods issue, confirmation, goods receipt
  • C. Creation, printing, release, goods issue, confirmation, goods receipt
  • D. Creation, release, settlement, goods issue, confirmation, goods receipt

正解:A、B


質問 # 53
What happens to this dependent requirement when you convert the planned order into a production order?

  • A. They are converted into a production order.
  • B. They are converted into a schedule line.
  • C. They are converted into a planned order.
  • D. They are converted into a reservation.

正解:D


質問 # 54
Which time elements are relevant for lead time scheduling of a production order?

  • A. Total replenishment lead time
  • B. Planned delivery time
  • C. Setup time
  • D. Float after production

正解:B、D


質問 # 55
What could be the reason for multiple commitment of invidula capacities, where several operations have the same scheduled dates on a work center (or resource) after planing?

  • A. The work center has several invidula capacities.
  • B. The Change Planning Direction indicator is set in strategy profile.
  • C. Alternative work centers are fully occupied.
  • D. The finite Scheduling indicator is NOT set in the strategy profile.

正解:A、D


質問 # 56
You set up a material as a phantom assembly by entering the special procurement key in the material master.
How can you switch off the phantom assembly in a specific bill of material (BOM)?

  • A. Change the explosion type of the phantom assembly in the BOM.
  • B. Change the item category of the phantom assembly in the BOM.
  • C. Change the special procurement key of the phantom assembly in the BOM.
  • D. Change the phantom item indicator for the phantom assembly in the BOM.

正解:A


質問 # 57
Where do you maintain data to determine the duration of an operation for production?

  • A. Routing
  • B. Work center
  • C. Material master
  • D. Bill of material (BOM)

正解:A、B


質問 # 58
What does a line hierarchy in repetitive manufacturing represent?

  • A. A production line with prioritized alternative work centers
  • B. A production line with a parallel sequence in the routing
  • C. A production line with more than one work center
  • D. A production line with an alternative sequence in the routing

正解:C


質問 # 59
You use planning strategy Finite Scheduling - with Reverse adn want to allow scheduling in the past. How can you achive this?

  • A. Specify a negative lanning horizon in the strategy profile.
  • B. Specify a positive planning horizon in the strategy profile.
  • C. Specify a positive offset time in the strategy profile.
  • D. Specify a negative offset time in the strategy profile.

正解:D


質問 # 60
Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?

  • A. When multiple operations are maintained for one product
  • B. When multiple planned orders exist on one resource
  • C. When multiple production versions are maintained for one product
  • D. When alternate resources are used within one operation

正解:D


質問 # 61
......


SAP C-TS422-2021試験は、80個の選択肢に基づく問題に180分以内に回答する必要があります。試験は、需要管理、材料要件計画、生産オーダー、生産能力計画、作業場のコントロールなど、さまざまなトピックをカバーしています。試験に合格するには、候補者は最低65%のスコアを達成する必要があります。この認証は3年間有効であり、関連試験を合格するか、あるいは特定のトレーニング要件を完了することで更新することができます。全体として、SAP C-TS422-2021認証は、SAP S/4HANA生産計画と製造の分野でキャリアを進めたいプロフェッショナルにとって貴重な資産です。

 

C_TS422_2021試験練習テスト問題:https://www.goshiken.com/SAP/C_TS422_2021-mondaishu.html

合格させるC_TS422_2021試験情報と無料練習テスト:https://drive.google.com/open?id=1oPDEn747_RxWS4lcHcOJlqQyoWH_oAmo