質問 33
The probability technical success filed is enabled for questionnaires. You have defined a questionnaire for portfolio items In customizing. When you want to fill out the questionnaire for the probability technical success filed an error message is displayed.
What is the reason for the error message?

  • A. The field service configuration of the parent bucket of the item is missing
  • B. The probability technical success field is configured as read only in the field control
  • C. The master switch for the interface settings for questionnaires it turned off
  • D. The field service configuration of the item is missing

正解: A

 

質問 34
You customer wants to involve the project manager, the staffing manager, and the candidate manager in the staffing of a project management project.
Which process requires a status change for each process step?

  • A. Staffing by authorization
  • B. Qualification determination
  • C. Role assignment and staffing
  • D. Extended staffing

正解: D

 

質問 35
You want to distribute capacity requirements in a project management project?
How can you distribute the values?
NOTE: There are 3 correct answers to this question

  • A. Copy values from resource assignments
  • B. Apply a distribution rule
  • C. Update the capacity requirements from the roll-up of task requirements
  • D. Enter the vales manually
  • E. Use a distribution function

正解: C,D,E

 

質問 36
What data influence the bottom-up scheduling of a project in portfolio management?
NOTE: There are 3 correct answers to this question.

  • A. Duration of tasks
  • B. Project type
  • C. Role demands
  • D. Relationships between phases
  • E. Relationships between tasks

正解: A,D,E

 

質問 37
How can you trigger a workflow for a portfolio item?
NOTE: There are 2 correct answers to this question.

  • A. Exceed the budget of the item
  • B. Choose the start workflow button
  • C. Change the item status
  • D. Change the master data of the item

正解: C,D

 

質問 38
Bucket A contains items and current located in bucket P1.
How do you move bucket A including the items to bucket p2.

  • A. Create a new bucket in bucket P2
    Move all items from bucket A to the new bucket
    Delete bucket A and rename the new bucket
  • B. Select bucket p2 in the move function as a target for bucket A
    Execute the move function
  • C. Select bucket A from the bucket dashboard
    Change the parent bucket field from P1 to P2
  • D. Move all items from bucket A to bucket p2.
    Move the empty bucket A to p2
    Copy all bucket A items from bucket p2 to bucket A

正解: A

 

質問 39
You want to split the financial planning values of portfolio item into two different buckets.
How do you do this?

  • A. Enable the split of financial values for the item type
    *Assign the item to two bucket of the portfolio
    *Maintain factors to split financial planning of the item
  • B. Enable the split of financial values for the item type.
    *Assign the item to two bucket of the classification hierarchy
    *Maintain factors to split financial planning of the item
  • C. Enable process change for multiple buckets.
    *Start process change to reassign the item two buckets
    *Maintain factors to split financial planning of the item
  • D. Enable financial planning for multiple buckets
    *Assign additional buckets in financial planning
    *Maintain factors to split financial planning of the item.

正解: B

 

質問 40
Which cost planning process can you use at item level?
NOTE: There are 2correct answers to this question.

  • A. Manual cost planning
  • B. Hierarchical cost planning
  • C. Rollup of cost planning
  • D. Integrated cost planning

正解: A,D

 

質問 41
What innovation management object is linked to SAP portfolio andprojectmanagement (PPM) out of the box?

  • A. Request
  • B. Opportunity
  • C. Idea
  • D. Campaign

正解: C

 

質問 42
What are valid breakdown period for financial planning in portfolio management?
NOTE: There are 2correct answers to this question.

  • A. months
  • B. Years
  • C. Days
  • D. Weeks

正解: A,B

 

質問 43
Where can you use the BCV report in SAP PPM?
NOTE: There are 3 correct answers to this question.

  • A. Bucket
  • B. Scoring model
  • C. Review
  • D. Item
  • E. Metrics

正解: A,C,D

 

質問 44
You have created a portfolio with the bucket levels and wants to create a portfolio item.
When can you create the portfolio item?

  • A. At any bucket level
  • B. At multiple bucket levels
  • C. At the lowest bucket level
  • D. At the highest bucket level

正解: C

 

質問 45
In project management, what data can be copied from a project template during creation of a new project?
NOTE: There are 3 correct answers to this question.

  • A. Responsible organizational unit
  • B. Authorizations
  • C. Project structure
  • D. Checklist
  • E. Dates

正解: A,B,C

 

質問 46
Which method can you use to update multiple values simultaneously in capacity planning for portfolio management?

  • A. Mass update
  • B. XML upload
  • C. Drag and drop
  • D. Distribution function

正解: D

 

質問 47
You have created a custom field and want to add this field to the item dashboard.
Where do you have to select the field to achieve this?
NOTE: There arecorrect answers to this question.

  • A. In the BCV settings for the item dashboard
  • B. In the Launchpad settings for the item dashboard
  • C. In the item dashboard settings
  • D. In customizing for item dashboard fields

正解: C,D

 

質問 48
Which data is transferred when you import a Microsoft project management?

  • A. Authorizations
  • B. Status reports
  • C. Cost
  • D. Task

正解: D

 

質問 49
Where can you use stakeholders in portfolio management?

  • A. Item
  • B. Bucket
  • C. Review
  • D. Initiative

正解: D

 

質問 50
What can you use scoring models for?
NOTE: There are 2correct answers to this question.

  • A. To derive field values of buckets
  • B. To derive field values of items
  • C. Top compare items in reviews
  • D. To compare bucket in reviews

正解: B,C

 

質問 51
You have configured a new consultant role type, when you create a new role for a project, the consultant role type is not available for selection.
How do you make this selection available?

  • A. Assign the consultant role type to the appropriate item type
  • B. Run a report to enable theconsultantrole type
  • C. Activate the consultant role type
  • D. Assign theconsultantrole type to the appropriate project type

正解: D

 

質問 52
How can an existing project management project be integrated with SAP controlling?
NOTE: There are 2correct answers to this question.

  • A. Transfer the project structure element internal orders
  • B. Assign the project definition to an existing PS project definition manually
  • C. Assign the project roles to an existing internal order manually
  • D. Transfer the project structure element to project system (PS)

正解: B,C

 

質問 53
What can you define in the item template?

  • A. Financial planning
  • B. Sequence of decision points
  • C. Category
  • D. Link to a project management project

正解: C

 

質問 54
......


SAP C_S4PPM_1909 認定試験の出題範囲:

トピック出題範囲
トピック 1
  • リソース管理プロセスの説明と構成
  • 財務およびキャパシティプランニング
トピック 2
  • 財務計画とキャパシティプランニング
  • プロジェクトとリソース計画の説明と構成
トピック 3
  • アンケートスコアリングと分析
  • ポートフォリオ構造の説明と構成

 